From: Richard Kahn
Sent: Friday, May 27, 2016 8:07 PM
To: jeffrey E.
Cc: Karina Shuliak
Subject: Bathroom Tile & GC - 9 e 71st
Attachments: ACS QUOTE - 9 E 71ST.docx; Untitled attachment 00068.htm; bottocino.png; Untitled
attachment 00071.htm
Attached are emails from contractors:
a) General Contractor - Mike Browne =hose quote covers protection / demo / electrical / plumbing / =arpentry
- there was no amount bid as he =osed some questions and needs more direction
- i =stimate his bid for this scope to be in 35-45k range which does not =nclude any new plumbing or electrical fixtures
we would =upply
b) Tile =endor - Peter bid was for all tile materials and labor - he quoted job =s rooms currently exist however you may
decide to change =cope
- bid was 65,500 - i think i =robably can negotiate down 10% or so
Depending on your answers to the =ollowing question below i believe cost for entire bathroom will be =00,000+- 10%
Please provide guidance on the following questions:
1) please confirm =ocation of toilet / shower plumbing fixtures and vanity will remain in =ame spots
2) will we purchase a new vanity? =edicine cabinet? plumbing fixtures? toilet? lighting - sconces and =anity lights
3) will we source materials or have =C source?
4) shower area - will we keep mirrored =helves or build a niche? if so what size and location / new mirror on =hower
wall?
5) doors - currently brass (i believe) =nd heavy - new style / color with lighter marble being used in =ooms
6) radiant heat - would you like us to add to =loor in entryway area (cost approximately 1,500)
7) =labs currently have a bullnose edge - keep this or different =dging
8) crown molding - keep or replace with =nother style or design
9) extend entryway =here we currently have wood / molding in entryway arch
10) steam room - keep benches same as is?
11) will marble on corner of entryway be 2 cm vs 3 cm in =hickness
12) Timing to do work - both vendors =ppear hungry for work and that may impact negotiations..
Thank you
Richard Kahn
HBRK Associates Inc.
EFTA_R1_02112497
EFTA02708852
Forwarded message
From: Mike Browne
Date: Tue, May 24, 2016 at 10:02 PM
Subject: =ichard Kahn
To: Richard Kahn < >
Cc: skuhn =It;[email protected] <
Hi Richard
Here's what I got from our visit today. Below is a list of =uestions.
Let me know if I missed anything. Thank you.
Richard Kahn
Scope of work:
Prep Work:
-Protecting of the entry way, stairs, elevator, hallway and work area =sing zip walls, ramboard, Masonite etc.
-Setting up of a negative air machine with HEPA filters to reduce the =ust.
-Removal of the vanity, medicine cabinet, toilet, light fixtures, and 3 =oors to save for possible reuse.
Demo:
-Removal and disposal of all stone surfaces including the shower, steam =oom, toilet area, walls and floor.
-Removal and disposal of the Durock and Sheetrock down to the studs.
-Removal and disposal of the lead bend.
Plumbing:
-Installation of the new shutoff valves.
-Supply and installation of a new Mr Steam steam unit.
-Installation of a new owner supplied shower body, volume controls, =andheld, sink and toilet.
-Fabrication and installation of 2 lead pans- 1is 5 x 4, the other is =x6 with two bench seats wrapping 2 sides 12x12.
-Installation of the new owner supplied toilet, sink and vanity.
Framing:
-Reframing of the walls, ceiling, shower curbs and benches to restore =he integrity of the walls.
-Installation of blocking as required.
Electrical:
-Supply and installation of a warmly yours floor heating mat and =hermostat. Approx 100sq ft.
-Installation of a disconnect as necessary for the steam unit as well as =ocating and wiring the thermostat.
-Installation of the owner supplied sconces in existing locations.
-Installation of the owner supplied side lights for the medicine =abinet.
-Supply and installation of 4 new dimmers with screwless plates.
-Supply and installation of a new gfi outlet in a new location.
2
EFTA_R1_02112498
EFTA02708853
Durock/Greenboard:
-Supply and installation of 30 sheets of 5/8 Durock.
-Supply and installation of 12 sheets of 5/8 Greenboard.
Questions?
Who supplies lighting?
Are lighting fixtures in existing locations?
Who supplies plumbing fixtures?
Who supplies med cabinet? Vanity?
Do you want radiant heat?
New steam unit?
Regards,
Michael Browne
T.C. Browne Co
6.61 GB (44%) of 15 GB used
Manage
Terms - Privacy
Last account =ctivity: 20 minutes ago
Details
Begin forwarded =essage:
From: peter strifas
Subject: quotation for 9 e 71st
Date: May 25, 2016 at 9:57:42 PM EDT
To: Richard Kahn <
Rich
See =ttached quotation , quoting the beige marble I had sent you photos of a =ouple of days ago.
Lets chat tomorrow.
3
EFTA_R1_02112499
EFTA02708854
Thanks
Peter D. Strifas
Principal
ACS STONE WORKS =ORP.
4
EFTA_R1_02112500
EFTA02708855
ℹ️ Document Details
SHA-256
03bec925dcc9f6f556741c9e5ee66aefd4754585f28637818f2bc2bdb86209e5
Bates Number
EFTA02708852
Dataset
DataSet-11
Document Type
document
Pages
4
Comments 0