Time Line
1311
May 23-25th: Floors are being refinished
May 28th: Painting starts
June 11: Ready for furniture
11P:
May 20: Carpet pulled up/prep work for floor refinish
May 3111: Painting starts
June 11: Ready for furniture
10B:
May 3111: Office move date
Week of June 4th: remove rest of furniture/desks, etc..
Week of June 11th: Floors refinished
Week of June 113th: Painting starts
July 2: Install furniture
10F
May 3111: Office move date
Week of June 4th: remove rest of furniture/desks, etc..
Week of June 11th: Floors refinished
Week of June 181h: Painting starts
July 2: Install furniture