📄 Extracted Text (1,804 words)
From: Darren Indyke <
To: Jeffrey Epstein <[email protected]>
Subject: Fwd: Little St. James
Date: Tue, 12 Jul 2011 22:46:44 +0000
Attachments:
CZM Mmor_permit_for_Parcel_A_with_all_signatures.pdf
I sent this to Maria, so she has Oriol's status report to the Barnes which is part of the email chain below. Oriol is
basically saying that CZM will only send Army Corps. notice of the CZM's grant of permission for the
moorings, and not the dock structures, so Oriol does not see that as a problem, but Oriol also says that CZM will
only send that to Army Corps after the revised submerged land fees are negotiated and agreed to. Maria had
mentioned in her email to us the need to negotiate with CZM re increased or additional submerged land fees.
As to the application for permit modification for the spa, Oriol correctly points out that we have ignored the
requests in his March letter, and also says that we have not developed a plan for habitat restoration with the staff
which is one of the special conditions in the permit that we are asking to modify to include the spa. However,
there is no time frame in the language of the special condition provided in the permit for developing the plan.
The permit merely says that "The Permittee will develop a plan to address concerns regarding habitat
rehabilitation and restoration with Department staff." Moreover, the permit containing this special condition was
signed in December 2010, and almost immediately thereafter we applied to modify that permit to include the spa,
so there has been no time to really address the plan.
I am not sure that Cecile will make any progress without you in this matter. In his March letter, Oriol is
essentially asking for a list of every structure on the island and a designation of what particular permit covers
that structure. Oriol is also asking for status on all permits for which the scope of work has not been completed.
We did not respond to either request on the theory that they had no right to ask for this information as the
applications were already deemed complete, so they could not ask for more application materials. Moreover,
even though they asked for more info (to which they were not then entitled) before the end of the 60 day period
after the application was deemed complete, since CZM did not actually disapprove of the application within that
60 day period, then the application should be deemed approved. We did not have Maria press this issue while we
worked through the dock structure and mooring issues. So does Maria take the strong position now, or should
you and Cecile first meet with Barnes? I believe the latter approach would be better.
I have attached a copy of the permit, as well as the March 2011 letter from Oriol for your reference.
Darren K. Indyke
Darren K. Indyke, PLLC
301 East 66th Street, 10B
New York, New York 10065
Telephone:
Direct:
Fax:
email:
EFTA00914706
****
The information contained in this communication is confidential, may be attorney-client
privileged, and is intended only for the use of the addressee. It is the property of
Darren K. Indyke, PLLC. Unauthorized use, disclosure or copying of this communication
or any part thereof is strictly prohibited and may be unlawful. If you have received this
communication in error, please notify us immediately by return e-mail, and destroy this
communication and all copies thereof, including all attachments.
Copyright of Darren K. Indyke, PLLC - m 2011 Darren K.
Indyke, PLLC — All rights reserved.
Begin forwarded message:
From: Cecile de Jongh sc
Date: July 12, 2011 3:42:57 PM EDT
To: Darren Indyke scl
Subject: Fw: Little St. James
Reply-To: Cecile de Jongh ,rnt >
Should I share this with Maria as well?
With warm regards,
Cecile
DISCLAIMER: The information contained in this e-mail may be privileged,confidential, and protected from
disclosure. If you are not the intended recipient, you are hereby notified that any dissemination,
distribution or duplication of this communication is strictly prohibited. If you have received this
communication in error, please notify the sender immediately and delete all copies.
Forwarded Message -
From: Alicia V. Barnes
To: 'Cecile de Jongh'
Sent: Tuesday, July 12, 2011 3:23 PM
Subject: RE: Little St. James
Hi Cecile:
So happy that we are in agreement. I would love to meet sooner, but am preparing for the
department's budget hearing. Please advise of your availability on either July 26th, nth, or
28th. Also, kindly see the below e-mail from JP to me.
Thx,
AB
Original Message
From: Jean-Pierre Oriol [-
Sent: Tuesday, July 12, 2011 1:15 PM
To:
Subject: Isj, Ilc status
commissioner-
EFTA00914707
per your request, the following is an update for where we stand with some of the Isj, Ilc permits
and requests-
with respect to the dock and moorings- in June 2011, the modification of major czm permit no.
czt-5-99(w) was approved by the stt czm committee, allowing for the construction of two
pavilions on the ends of the dock, as well as the installation of two mooring buoys. as there are
new submerged lands being occupied (mooring buoys) the permit must be approved by the
governor, as well as the legislature. prior to that happening, Isj, Ilc and the department must
negotiate the fees.
when permit no. czt-5-99(w) was issued on march 30, 2000, the fees associated with the permit
were for $2500, and covered the dock, the water area around the dock, and the floating swim
platform. section 9(c) of the permit further stated that on the first 5th year anniversary, the
permit fees would be adjusted, and that failure of the permittee to re-negotiate the fees would
result in the automatic increase of the fees by 25%. subsequent five year anniversaries also
would require adjustments. to date, no fee adjustments have ever occurred under this permit.
further, additional structures have been added to the dock and shoreline area, and the fees do
not reflect these additions. therefore, with the upcoming negotiation of fees, all of these things
will be taken into consideration and a new fee will be assessed.
it is customary for the department to forward to the corps of engineers a consistency
determination following approval by either the commissioner or committee on a project involving
submerged lands; however, this determination is not sent prior to the fees being negotiated
because the fees are required under section 911 of the act, and thus part of the "consistency."
once we have agreed to a new annual fee with the permittee, the determination will be sent to
the corps, and a new permit document will be drafted and forwarded to the office of the
governor. again, just like the application that was sent to the army corps, the consistency
determination will only reference the installation of the mooring buoys as this is the only new
action regarding submerged lands; the pavilions will not be referenced.
with respect to the spa- in december 2010, czm permit nos czt-25, czt-26 and czt-27 were issued
to Isj, Ilc. the process of approving these was long and drawn out because the department felt
that there were some conditions of other permits that were not being complied with, whereas
the permittee felt that construction under said permits had not taken place within a year,
therefore were null and void and that they should not be subject to those conditions. it really
boils down to the fact that there are too many ongoing permits for this area, and with the
cumulative impacts fo all these smaller permits, the activity should be covered under one major
czm permit.
notwithstading this issue, within a week of being issued the above-mentioned permits, Isj, Ilc
came in to the department for a modification of one of the permits for the construction of a spa.
in a letter dated march 16, 2011, a response was sent to the permittee stating that before any
more development would be approved on the island, a detailed inventory of all existing
structures with corresponding permit numbers must be submitted to the department, and that a
status report of all permits issued to Isj, Ilc for which the scope of work has not been completed
must be submitted to the department. this, in addition to the special condition on the last
permits, which required the permittee to develop a plan to address the concerns regarding
habitat rehabilitation and restoration with department staff, would allow for the department to
have an accurate, up to date picture of everthing that is ongoing on little st. james island. the
permittee has neither complied with thhe permit condition, nor submitted any of the status
reports requested by the department. to that end, the modification request is on hold by the
department.
we have recently submitted for your approval a certificate of occupancy. you should see it in
your stt office the next time you are here.
EFTA00914708
that concludes the status of where we are with regards to Isj, Ilc requests
Regards,
Jean-Pierre L. Oriol
Director
VICZMP
DPNR-Division of Coastal Zone Management
8100 Lindberg Bay, Suite 61
St. Thomas, VI 00802
www.czm.dpnr.gov.vi
From: Cecile de Jongh [mailto:
Sent: Tuesday, July 12, 2011 4:20 AM
To: Alicia V. Barnes
Subject: Re: Little St. James
Good morning Alicia,
I agree that we probably need to meet. When would you like to do so?
With warm regards,
Cecile
Sent from my iPhone
On Jul 11, 2011, at 8:01 PM, "Alicia V. Barnes" < > wrote:
Hi Cecile:
The dock portion of project was never submitted to the ACOE. Also, the mooring
permit also has a legislative level of approval, due to a change in the code. I really
think we need to meet to clarify the overall procedure(s) and next steps in this regard.
Thx,
AB
Sent from my iPad
On Jul 11, 2011, at 4:23 PM, Cecile de Jongh < > wrote:
Good afternoon Alicia,
I wanted to follow up with you on the approval for the dock and mooring. After
speaking with Mr. Epstein and Atty Hodge, they would really like to be able to get an
apporved mooring letter from DPNR separate from the dock approval. They
understand that everything (dock and mooring) was approved as one approval but
EFTA00914709
that will cause problems with the Army Corp of Engineers due to the previously
recognized mooring issue which the ACE has determined can stay as is. I would like
to speak to you about this, if possible.
With warm regards,
Cecile
DISCLAIMER: The information contained in this e-mail may be privileged,confidential, and protected
from disclosure. If you are not the intended recipient, you are hereby notified that any dissemination,
distribution or duplication of this communication is strictly prohibited. If you have received this
communication in error, please notify the sender immediately and delete all copies.
EFTA00914710
ℹ️ Document Details
SHA-256
0703c5798308e34d8d0306f9784ab468e0d5385efc30957d934b951fc9533162
Bates Number
EFTA00914706
Dataset
DataSet-9
Document Type
document
Pages
5