From: Daphne Wallace
To: Jeffrey Epstein <[email protected]>
Cc: ann rodriquez < >, Rich Kahn
Subject: Re:
Date: Wed, 14 Oct 2015 23:42:42 +0000
Greetings Sir,
Boyson hopes to be back in service Friday, 10/16. If so, and we can recommence with the crusher run on
Monday, 10/19, the 20 loads of crusher run remaining could be completed by Friday, 10/23.
The asphalt could start the following week, 10/26, and if you permit the project to extend into the first week of
November, Better Roads may be able to complete 40% of the asphalt work - they would begin at the Kite House
area and work their way out.
I am scheduled to speak with Mr. Justin of Justin Brothers about his preliminary numbers tomorrow. He picked
up the plans last Friday, but was not ready on Monday when I called him. He said Thursday and will also let me
know when he can go out to see the site.
Respectfully, Daphne
road schedule jardian all in budget?
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation®gmail.com, and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA00843523
ℹ️ Document Details
SHA-256
0d6c8cf7d1c4158c1d00beebd010a498eaaa0c7671c7d7e46dc8c277698eba8e
Bates Number
EFTA00843523
Dataset
DataSet-9
Type
document
Pages
1
💬 Comments 0