Three week look ahead to OCT.7
MASTER
1. Walls and ceiling painted.
2. Floor leveler applied.
3. Floor underlayment down prepared for wood flooring.
4. Thassos going on walls
5. Coral laid up to shower, patched around columns
COTTAGES
1. Roofs painted
2. Cabinets set tops on
3. Ion painting walls
4. Doors and shutters complete on tt2 in progress on 1&2
5. Baths complete
6. Ac operational
KITCHEN
1. Walls standing
2. Roof framing starting
LAUNDRY
1. Forms stripped
2. Stairs formed and poured.
3. Stone veneer 50% done
4. New road at grade for approval
5. Jeffrey drive walls mocked up for approval.
6. Interior walls being plastered.
EFTA00583514
ELECTRICAL BUILDING
1. Generators in place
2. Switch gear in place
3. Fuel piping underway
4. Fire system complete
DESAL BUILDING
1. Backfill continuing
2. Second storey wall standing
3. Top slab 'A formed
LIBRARY
1. Remove furniture/francilli working
BEACH
1. Deck poured ready for tile
WALLS
1.entry done
2.gym mostly done
TREES
1.we are diging holes
2.barge schedule to P.R. next week
3.trees will take 6 weeks to plant
BOATS
1.barge operational
2.little C operational
3.nanna engines on and painted,windows on order
EFTA00583515
EFTA00583516
ℹ️ Document Details
SHA-256
11fde24c5870992f5434b33ab89ce2102cb86fc736a65f2d4acaf42a72882a61
Bates Number
EFTA00583514
Dataset
DataSet-9
Document Type
document
Pages
3
Comments 0