To: Gary Kerney
From: Jeffrey Epstein
Sent: Mon 11/16/2009 2:25:14 PM
Subject: Re: Friday agenda
please bring photos .lots.. i am a bit concerned with the landscape , progress, sieve has been on
since june and i m not sure of the schedule.. I don't see things happening, and i am not shown
much to critique or choose.
On Mon, Nov 16, 2009 at 9:12 AM, Gary Kerney wrote:
Jeffrey,Fri.Nov.20th agenda.
Construction: two superintendents have been hired and are on site.
OFFICE: three main tasks to finish construction, the improvement to the top of the wall is complete and
ready for planting.
1.exterior crown molding and plaster profile approved, ordered and installed by Jan.15
2.wood floors complete by Dec.15
3.coral stone deck by Jan.15
Franchelli can get in after Dec.15th,the ceiling can be done after Franchelli and the furnishings can be
installed after the ceiling.
MASTER: all materials and subs have been contracted outstanding issues holding up construction. If we get
decisions Fri. we can make May.
1.collums, hope to have Gensler's new drawings by Fri.
2.tub,will go over Doug's spec's and get direction.
3.interiors,we need to make decisions on the materials that the decorator will select that effects
construction.
MASTER/OFFICE SITE: grading and walls under way two decisions outstanding.
1.finish of hardscape,Stevens plans
2.finish of Jeff drive ,Stephen has two concepts
MECH. BUILDINGS ELECT./DESAL.super assigned and site mobilization under way. Reviewing bids and
organizing
contracts.
MAIN HOUSE LAUNDRY/KITCHEN/REMODEL(phase one):we are working with Gensler to pull the permit
for the main house, which will permit the phase one work. While we are doing the physical work on the
improvements Gensler will make all the changes and finish the construction drawings for the main house.
Doug is going to L.A.and meet with Gensler the week after Thanksgiving to get the permit set produced as
soon as possible.
CZM: Stephen is preparing the plans for the submittal, pool plans are in the hands of the engineer .
1. if the CZM has issue, as I'm expecting, with the temporary kite house are you prepared to commit to a
permanent permitted structure there? if maybe, we can have Stephen prepare a backup plan.
TRAILS/WALLS:temp on hold all wall people are at office site, and we are going round and round with Porto
rico on the color for the concrete paving.
EFTA_R1_00192647
EFTA01819863
PAY STRUCTURE: Brice has forwarded recommendations to you, discuss.
MISCL.
1.accounting and job cost are to be working fine from my side.
2.1 have been in place two months, how am I doing? what do you not like?
3.how can I help the decision process less painful for you ?more frequent meetings?
***********************************************************
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
Jeffrey Epstein
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacationagmail.com, and
destroy this communication and all copies thereof,
including all attachments.
EFTA_R1_00192648
EFTA01819864
ℹ️ Document Details
SHA-256
12b47c29551306e38d361bcbcad1a58ff5d21cea2041a19723096e224e8bacd5
Bates Number
EFTA01819863
Dataset
DataSet-10
Document Type
document
Pages
2
Comments 0