From: Richard Kah
To: "Jeffrey E." <[email protected]>
Subject: LSJ - Jimmy F
Date: Tue, 08 Aug 2017 20:57:08 +0000
daphne and i spoke with Jimmy Fraguela on two items this morning:
I. The site visit for the WAPA project will take place on Wednesday, 8/9 - Anna, he is still awaiting a time from
the electrician - once we have that information then we can set up the logistics as they will need to visit both
islands - this is for the WAPA electrical link for LSJ and GSJ
2. The scope of work for the RIO and Mechanical buildings sheds project - Jimmy asked if he has the green light
to begin the project on Monday, 8/14. If not, he has to re-schedule the 10-man crew. He also said he needs an
answer because the materials need to be ordered as detailed on the Scope of work presentation.
last time we spoke about Jimmy you said you wanted firm numbers. unfortunately not yet firm but below is
outline that daphne and i composed of anticipated costs for the RIO-Mechanical Buildings Steel Sheds Project:
Materials: Steel, Form Lumber, Concrete (Jimmy Fraguela) - $ 70,000.00
Labor: Concrete Work only - 40 hour/8 weeks (Jimmy Fraguela) - $ 90,000.00
Steel Buildings: 3 buildings, freight to FL port (Buck Steel) - $ 110,000.00
Shipping: FL port to STT port (Tropical Shipping) to LSJ - $ 25,000.00
Building Erection: 3 buildings (Jimmy Fraguela) - $ 60,000.00 - anticipating about $20K per
building
Contingency: Misc, Etc, (10%) - $ 35,000.00
- $390,000.00 **
** not this figure does not include any finishings such as electrical, plumbing and doors for buildings..
please advise if ok for jimmy to begin 8/14 on his 8 week schedule
thank you
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue 4th Floor
New York NY 10022
EFTA00626831
ℹ️ Document Details
SHA-256
149ad24a014fc8553f20fa841aaeddde013fb76385dafa92a9c5c438d4d313a5
Bates Number
EFTA00626831
Dataset
DataSet-9
Type
document
Pages
1
💬 Comments 0