LSJ CONSTRUCTION
Subcontractor Payout
Project: Mechanical Desal #1010 February 2, 2011
Trade: Fire Protection
Requisition #01
Subcontractor Abbott & Lineham Mechanical
Insurance ex iration: March 26.2011
Invoice # Requisition #01 Partial Final
Phase # 15-500 X
Original Contract Sum: $43,500.00
Change Orders Submitted & Approved: $0.00
New Change Orders:
$0.00
Total Work Contracted to Date: $43,500.00
Total Work Completed to Date: 95% S41,325.00
Less Retainage: $2,066.25
Total Payments Made to Date: $0.00
Total Current Payment Due: i $39,258.75 7
Balance to Finish including Retainage: $4,241.25
Sales Tax Liability:
a. Subcontractor/Supplier is liable, explaitinstall only / tax
included in contract
b. Non-resident Subcontractor/Supplier Bond Applicable:
c. Use Tax to be paid by our company:
d. Shipping None
Total Outlays for this contract incl. Sales or Use Tax: $41,325.00
JEE approval attached Invoice Attached
YES NO YES NO
X
Submitted Bill Approved by: Gary
Signed: Signed:
Date: February 2. 2011 Date: February 2. 2011
Approved by: E d Approved by:
Signe.. Signed:
Dat: a\t\\‘\ Date:
EFTA00609235
EFTA00609236
EFTA00609237
Emad Hanna
From: Monique Harry
Sent: Friday, February 04, 2011 10:40 AM
To: Emad Hanna
Subject: Abbott & Lineham Req 1 Mech Desal Fire
Attachments: Abbott Mech Desal Fire Req 1.pdf
Emad,
Attached for payment Abbott & Lineham Mechanical Fire Protection Req 1 in the amount of $39,258.75. Project 1010
Code 15-500.
Monique
EFTA00609238
ℹ️ Document Details
SHA-256
18b77cbc5b24b4988eb88b57760d27d3952a076052e00795e36527376adb6302
Bates Number
EFTA00609235
Dataset
DataSet-9
Document Type
document
Pages
4
Comments 0