EFTA00609231
EFTA00609235 DataSet-9
EFTA00609239

EFTA00609235.pdf

DataSet-9 4 pages 220 words document
V16 V11 V15 D1 P21
Open PDF directly ↗ View extracted text
👁 1 💬 0
📄 Extracted Text (220 words)
LSJ CONSTRUCTION Subcontractor Payout Project: Mechanical Desal #1010 February 2, 2011 Trade: Fire Protection Requisition #01 Subcontractor Abbott & Lineham Mechanical Insurance ex iration: March 26.2011 Invoice # Requisition #01 Partial Final Phase # 15-500 X Original Contract Sum: $43,500.00 Change Orders Submitted & Approved: $0.00 New Change Orders: $0.00 Total Work Contracted to Date: $43,500.00 Total Work Completed to Date: 95% S41,325.00 Less Retainage: $2,066.25 Total Payments Made to Date: $0.00 Total Current Payment Due: i $39,258.75 7 Balance to Finish including Retainage: $4,241.25 Sales Tax Liability: a. Subcontractor/Supplier is liable, explaitinstall only / tax included in contract b. Non-resident Subcontractor/Supplier Bond Applicable: c. Use Tax to be paid by our company: d. Shipping None Total Outlays for this contract incl. Sales or Use Tax: $41,325.00 JEE approval attached Invoice Attached YES NO YES NO X Submitted Bill Approved by: Gary Signed: Signed: Date: February 2. 2011 Date: February 2. 2011 Approved by: E d Approved by: Signe.. Signed: Dat: a\t\\‘\ Date: EFTA00609235 EFTA00609236 EFTA00609237 Emad Hanna From: Monique Harry Sent: Friday, February 04, 2011 10:40 AM To: Emad Hanna Subject: Abbott & Lineham Req 1 Mech Desal Fire Attachments: Abbott Mech Desal Fire Req 1.pdf Emad, Attached for payment Abbott & Lineham Mechanical Fire Protection Req 1 in the amount of $39,258.75. Project 1010 Code 15-500. Monique EFTA00609238
ℹ️ Document Details
SHA-256
18b77cbc5b24b4988eb88b57760d27d3952a076052e00795e36527376adb6302
Bates Number
EFTA00609235
Dataset
DataSet-9
Document Type
document
Pages
4

Comments 0

Loading comments…
Link copied!