File Alerts & Actions Forms 7 Week Look Ahead Schedule
glg Grid View • V Filter Maly 10 • B I U e>. • A • • Eal e -=
= Z , $ • .0. .00.
rl) E7! i Task Name Finish Assigned To Status Comments
1 GSJ Cottage 02/01/19 JPK In Progress Tile is being laid, siding to start, roof installation IP, window door install
LSJ Tiki Kitchen 01/25/19 LSJ In Progress Tile Samples awaiting approval. kitchen demed. tile is next step. then cabinets. etc
GSJ Big Tiki 01/31/19 BBates In Progress Brian to finish deck 2 days, Roof Starting (leaves 3.5 weeks for roof install and finishes)
Stone Wall Main Co 03/29/19 Danny Not Started Schedule and budget established starting on 10th of Jan.
O - Hut 02/15/19 EB In Progress EB starting the 14th of Jan (Mason broke his hip..) Max 4.5 weeks barring no DPNR issues
Pebble Beach 03/08/19 Kyle / Dupson In Progress Dupson / Kyle to begin next week on rebar footing and pour for FDs. Then Stone walls and roof schedule dependent
on walls 8 weeks tent finish
RO Building GSJ tbd TBD Not Started We need an Architect for Plumbing / Electric drawings for RO system design. This is will cause changes to layout
inside building drawn
Cabana 3 tbd JPK / LSJ In Progress Tile back up and pipes repaired. Awaiting arrival dates of the flooring company (2 weeks from arrival of flooring
company)
5 Palms tbd JPK/EB Not Started Awaiting JPK and EB bids for this, multiple emails and calls in still awaiting pricing for outlined scope (6 week
schedule)
LSJ Tile Roofs tbd JPK / Pokey / BWS Not Started tracking down copper and EIFS. Awaiting BIN Sub proposal. Pokey coming out Monday 9 am to look at (4.5 weeks
for each roof)
Grotto tbd EB? In Progress EB pricing received. Was told to put them off and sun louvre company will do this? EB can still do this if green light is
given it will be 2 weeks from start date
Jeffers 2 Roads tbd Jeffers Not Started Jeffers to Confirm Schedule / Tent start date Jan 14th Jeffers in discussion with his lawyers on credit
Waterfall LSJ Area tbd LSJ In Progress Need to establish layout of post. then pour slab (with post leave-outs)- erect post and shade sails? 2 weeks total
from start date
EFTA00795982
ℹ️ Document Details
SHA-256
1dcfa1d76ed82d95b139fcdc871f935aee0e932817d705c7a34b9f8a18b3fec3
Bates Number
EFTA00795982
Dataset
DataSet-9
Document Type
document
Pages
1
Comments 0