📄 Extracted Text (126 words)
SCHEDULE B PRICE AND PAYMENT SCHEDULE
TOTAL PRICE OF THIS CONTRACT IS: 318,000.00
Based on 3600 sft of tile in place at 34.75 per sft
- Includes nine (9) steps and associated risers at $100.00 each
Price may be adjusted if quantities vary
Requisitions to be submittedfor payment every week, based on squarefootage installed.
Payment via local check by Owner.
Applicable Gross Receipts Taxes to be paid by Saint Tile, LLC
No deposit payment on labor.
SCHEDULE
Time limits stated herein are of the essence of the contract.
Work to be substantially completed within three (3) weeks of the date ofcommencement
Date ofCommencement is the date of this contract.
Work to be coordinated and scheduled with Tom Melnick, Site Superintendent (340-244-8564)
DATE: INITIAL: DATE: 7/4919/g
EFTA01071771
ℹ️ Document Details
SHA-256
2038d1ba8fa87467a2ac5bd26eea247f9a2aaf7fca3176ffba305cec4d34eb83
Bates Number
EFTA01071771
Dataset
DataSet-9
Document Type
document
Pages
1
Comments 0