From: Jeffery Edwards <[email protected]>
Sent: Monday, August 11, 2008 10:17 PM
To: Rich Kahn
Subject: Re:
The deal we s=ruck with him was that we anticipated the project would take approximately =0 weeks. I was initially
more conservative at 12 weeks, knowing that =ock can come out slow, but I was instructed to submit it at 10 weeks.
=Alain agreed to hold his price for as long as it took to remove the excavat=on from the Mechanical Building site. He has
spent about 6 to 7 weeks=on this task. As you are aware, Dan pulled him off this job periodica=ly to complete other
island tasks. I would estimate that, once we com=ence excavation again, it will take three weeks to clean up the site.
=Alain has been paid for eight weeks under our lease agreement. This e=compassed the time from 1/9/08 to 3/5/08.
I don't know =hat other info you desire on his truck. Let me know or ask him direct=y tomorrow.
I would be gl=d to provide a reference on his behalf... Do I count...?
Let me know i= you desire any additional information.
Thanks!
William Rowles
Lafayette Contractors, LLC
6100 Red Hook Quarter A2-7
St. Thomas, VI 00802
1
EFTA_R1_00101542
EFTA01782043
ℹ️ Document Details
SHA-256
250b48288acc0bd8cf036bee86066e40bc00a16ae14337912e8d59ab45efb86a
Bates Number
EFTA01782043
Dataset
DataSet-10
Type
document
Pages
1
💬 Comments 0