American Yacht Harbor
Facility Condition Status Report
September 2015
Addressing specific issues raised July 2015
-- MARINAS
IGY
EFTA01084560
Hurricane Shutters - Completed
Original pictures of the hurricane Pictures of same, repaired and painted
shutters outside upper level office in July/August 2015
,„--
EFTA01084561
Wall Paint - Completed
Original Pictures of exterior walls Pictures of same, repaired and painted
around upper level office in July/August 2015
6MINIIMMIONO-01,001° 6.
EFTA01084562
Dock beam repairs - Completed
Original picture of dock area near slip Picture of same repaired September
B-26 2015
EFTA01084563
Main Flag - Completed
Original picture of flag with tattered
edge Picture of same, replaced July 2015
EFTA01084564
Parking deck walls - Completed
Original pictures of lower parking deck Pictures of same, repaired and painted
walls July/August 2015
EFTA01084565
Parking Deck Columns - Completed
Original picture of column needing Picture of same painted July 2015 — other
paint columns were painted as needed.
GARAGE PARKING
GARAGE PARKING BEFORE 9AM WITH
BEFORE 9AM WITi. CURRENT PASS ONLY
CURRENT PASS ON
LC)ITERIN
OLICITIK 9
EFTA01084566
Dock planking — In-Progress
Original pictures (4 samples of many) Sample pictures of recent and in-progress
of various dock planking trouble spots dock repairs — September 2015
EFTA01084567
Security Fencing — In Progress
Picture of same. As vegetation in this area
Original pictures showing fence regrows, the fencing choice is more
transition understandable.
EFTA01084568
Piling wrap — In Progress
Original picture of pile with failing Sample of a pile with completed wood
wrap. A project is underway to replace
wood wrap failed wrapping on 24 concrete piles.
Expected completion in October 2015
EFTA01084569
Support columns — In Progress
Original pictures of support column
bases lifted off brick deck Action Plan:
• Bases will be split open, lowered, and
reinstalled to be flush with brick deck
• Contractor quoted price approx. $75 per
columns
• 133 columns on B & C (Main) Building, for
total price of about $10,000
• Contractor is currently lowering 5 bases to
test feasibility
• If solution is workable, we will move forward
strategically to address most visible columns
first, and continue until aesthetics are
satisfactory
EFTA01084570
Parking Deck Ceiling — In Progress
Original pictures of damaged drop
ceiling in the lower parking deck Action Plan:
• Materials are on order to begin replacement
of damaged ceiling tiles, support structure
and light fixtures.
• Drop ceiling near parking deck entrance is
being cut back to be flush and neat with
entranceway (areas shown in bottom to
picture on the left)
• The above efforts will lift aesthetics to
acceptable levels while we plan long term
solution
• Long term replacement or refurbishment
options are being explored and quoted for
completion in 2016
EFTA01084571
Elevator — In Progress
Original pictures of scraped paint on
the elevator doors Action Plan:
• Doors have been repainted, but elevator use
for freight will continually scrape paint
• Elevator doors and trim areas are being fitted
with stainless steel rub rails/guards to protect
paint while remaining aesthetically pleasing
• Interior of elevator cab is also being
refurbished, including polishing of stainless
steel, new paint and new flooring.
• Completion expected in Q4 2015
EFTA01084572
Brick Pavers — In Progress
Original pictures of various areas of the
brick paver deck needing attention Action Plan:
• Brick paint is being color custom color
matched to better blend repair areas with
original brick.
• Patch and replacement bricks are installed
where need.
• Long term resurfacing or repainting option
are being explored by local contractors. Two
primary options are 1) Coating with a heavy
duty masonry paint or 2) removal and
replacement of entire system of brick pavers
• Either option above will be a significant
undertaking, expected to start and complete
project in 2016
EFTA01084573
Stairways — In Progress
Original pictures of stairways Action Plan:
• Local structural engineer Paul Ferreras, PE has
inspected the property's stairways and written a
letter recommending refurbishment over
replacement
• Two local welding contractors are producing job
quotes to address all structural steel issues with
stairways
• Concrete stair treads will be painted to match
paver bricks on surrounding decks
• Steel will be repainted black after above repairs
are complete
• All repairs expected to be completed in Q4 2015
EFTA01084574
P Dock — In Progress
Original pictures of areas around
P-Dock Action plan:
• P-Dock is owned by 3rd party and slips are
managed by AYH
• Dock owner is refurbishing entire dock
structure and utilities starting October 2015
• AYH/IGY management team working with P-
Dock owner to ensure rebuilt dock meets
safety and aesthetics standard.
• Expected completion January 2016.
EFTA01084575
ℹ️ Document Details
SHA-256
262a913b2f42c465aae97b880b0bf020fb9a2f41ea64829faeb66229fd81f29c
Bates Number
EFTA01084560
Dataset
DataSet-9
Document Type
document
Pages
16
Comments 0