isl • Island
Punch Ust/Project Ust
as of 1/3/2013
PRIORITIZE PROJECT DESCRIBTION taborets I Hours tabor Cost eknenoicea Total Estimated cost Stan Date End Date I Notes
1. Equipment and Vehicles
Brakes Black Bikes 1 1/3/2013 — reviewed & adjusted 1/3
Excess Oil Disposal 3,000.00 - proposal forward to Rich K 12/0, refowarded to Jeanne 12/29 awaiting direction
Electric Golf Cart Damage - forwarded photos to dealer 1/1 awaiting response
-2. five Palms
Picture Frame 036 x 70) 1/3/2013 1/22/20131Canyas on site- forwarded to framer 1/3 completion expected 1/22
3. Dock Boxes
Fabricated a lighter lid, still to heavy J— Investigating resin/plastic option, up to 0 ft high will forward 1/5
6. Roads
General re-grading of roads - ongoing
5. Landscaping - Peter's Ust
tine all Roads with Rocks - ongoing
Removed Palm Tree on MC Hill - replacement lEE to advise
Black Heli Under Pads - installation to begin existing pads
to be removed 1/10/2013
12. Stone Walls
Repair work to replace missing loose stones & complete Heli Pad
wall - after Employee Bathroom Project
20. Stores. Areas -
MI areas to be organized & inventoried
21. AC -
Proposing that the 2" unit from Kitchen is replaced & relocated
to a Hobbits
Bps
Maintenance contract option Brice to request proposal from Island Marine
Paint window frames
Danny Projects
Move lights on flag pole
Chinas bathroom electrical
Beach Office • repair outside light
Relax Bathroom . rewiring
Pool Cabana • change lights parking area
Screen Room • repair lamp
S Palms - repairs 2 floor Lamps
5 Palms - review exposed wires around coconut palms
berm - cover Electrical box
Info Center - review outside electrical box area
1 of 5
EFTA_R1_00345144
EFTA01909617
LSI • Island
Punch Ust/Project Ust
as of 1/3/2013
PRIORITIZE PROJECT DESCRIBTION I Laborersl Hours Labor Cost ram*,am Total Estimated cost Start Date End Date Note
Kite House & Pebble Beach - review solar, relocate solar panel to roof of Pebble Beach House
Tiki House - Instant hot water system to be installed' 1/9/2013
Tikl House - reinstall light cover in kitchen
Captains Office - installation new AC (on site)
Under Master Bedroom - repair AC unit
Lightbulb Replacement - Office. Library Blackboard & Coiling, Master Closet Area,
Beach Lighting - section out
Water Proof Covers - for all outside electrical areas - hanger, flag polo pool
Jennaino Projects
Beach Office - no Internet/phone
Phones Down - master bathroom, room 4, 5 Palms,
Various maintenance
'horde Sculpture - base painted same as wall color
Gym/Bathroom/Roof - repainted
Hanger Area - door resurface & stain
• paint concrete block supporting wind sock
TN, Kitchen Roof - replacement
Flag Pole Pool. resurface & finish outside table & benches
• fridge need to be bolted down
MC - replasteripaint rising lawn edging
• Nista°, upper ceiling St John 8 Courtyard
Office - repaint air vent
Wooden Planters (new & old) • seal
Captains Office - plaster/paint interior
Thatch - all locations require new sections
Fans • Rust
Info Center - review drainage in parking area
5. Landscaping
Loading Dock - requires redesign Peter 3 days
Sea Grape/Citrus Fenillter/Mukh/Plant Material - 1/8/2013 ordered - nursery reopens 1/7 awaiting ETA
Sunflower seeds 1/8/201 -ordered -John Deere reopens 1/7 awaiting ETA
Caribbean Plants with color Ingrid -Change jasmine qty to SO plants 100 bright red bougainvillea to order, 3 gal.
1/8/2013 Ingrid to work on order
Crave_protects 13.000.00 $ 13,000.00 3/2/2013 13 week contract ending 3/2/2013
MSI • bill $5,318.55 plus S4000 estimated fit out ( no list) - material on site, demo
1 Staff bathrooms $9,500.00 5 9,500.00 17/28/2012 1/18/2013 started 12/28 rough in plumbing complete, concrete work to begin 1/4
Porta potty $ 1.000.00 1,000.00
2 Pops garden $3,730.00 $ 3,730.00 2/15/2013 MSI - $ 3730 - Demo existing, construct new shade/planter area
Barge window frames $1,000.00 $ 1,000.00 Brice to provide material list wood and hinges
Beach Equipment/Toy Rack 2/9/2013
3 Planter boxes 1/10/2013 Adana 2 to go using materials on site
Barge chocks
Bronze sculpture gym To be raised
2 of 5
EFTA_R1_00345145
EFTA01909618
Isl• Island
Punch Ust/Pro$ect Ust
as of 1/3/2013
PRIORITIZE PROJECT DESCRIBTION I taborets Hours labor Cost ranwwww Total Estimated cost Start Date trio Date Note
TIM House - Propane Stand
Lattice Panels Installed - tunnel
Nap House/Staff Cottage - Replacement of all Screens
4 Audio equipment kitchen
Captains Office - AC Frame
Pergola Construction - High Road Benches - require design details/numbers from It
Redesign & Install all new beach signs
Cleaning. Organizing & Inventory of Wood Shop
17. Pools
Installation of x 2 variable speed pumps per pool 1/12/201 1/10/2013
Flag Pole Pool - steps to be installed - require JE direction
MC Pool - steps to be Installed to pool pump room
Heater 1/2/2013
14. Wet
Solar Vendors - Toshiba reps on site I/1. Toshiba have
postponed on site visit. Awaiting final proposal Question Toshiba on new meter to measure line loss and solar batter life in salt air
7. Inseam
• Chiller - estimate forwarded //24 to lE for review. 12 week
lead time for equipment. 2 to 3 weeks Installation 130,000.00 BM from Atlanta refrimratIon ( contact Kent) alternative bids to be obtained
9 Steel Shed
Paid in advance Buck steal; 2nd building shipped 1.2.2013 ETA 1.5.2013 on STT ; Roll up
Structure $ 43,140.00 1/18/2013 2/28/2013 door ETA at Tropical 1.4.2013 sailing 1.9.2013 ETA STT 1.12.2013
Shipping and trucking $ 7,554.55 12/19/2012 -ex.... cwitennnnewdonum ittaduntIl Imtammummuur. tweniniwiumna Nis
Fit out $ 6300.00 • UgMs, Switches, Electrical Equipment order - Danny to finalize 1/5
Tools TBA
Accommodations $ 7,92000 1/18/2013 1/29/2013 $ 200/nt 3 units 11ins plus @20%
Alr 2,401.90 Paid In advance spirit
Food TBA
Existing shed
Reskin 12,008.00 1/18/2013 2/28/2013 - Refit Existing Shed- sheeting etc ETA 1/5 roll up door to sail
Fit Out lights 1,500.00
Bid approved 11/8 Material on site. Start to empty dsterns 1/3. Walt to start 1/11
Expected completion by 2/13 $11,500 deposit made - All furniture in rooms I & 2 needs
to be removed or covered before work begins . After repair complete . laundry,
13. Cisterns 13,200.00 1/11/2013 2/13/2013 Hobbits, Bathroom, Pump Rm, Tech Rm all require repair/plaster/paint
8. Hangar
Fuel Containment Pad - Plan ready for submission Plans sent out for new bid
18. Roads -
3 ofS
EFTA_R1_00345146
EFTA01909619
Isl • Island
Punch List/Project Ust
as of 1/3/2013
PRIORITIZE PROJECT DESCRIBTION I taborets I Hours labor Cost MA'AM ova Total Estimated cost Start Date End Date Notes
- Other solutions to be Investigated
22. Fire System -
- Pipe that feeds the 300,000 gal system needs to be replaced.
Draining of tank started 1; I Will forward complete costing once
Pipe is inspected & scope of work determined 1/3/2013
Derust and Paint equipment Hire individual to paint equipment - one month time
4. Boats
Lady G - sell - will remain at Nanny Ca`/ until sold.
Midnight Express . sell 1/15/2012 - buyer on site 12/21 will make contact by 1/15
Purchase Yacht Tender - options forwarded to JE awaiting direction
Purchase New Boat to replace Midnight 1.46 - require budget
Repower Little C 4- Jeanne investigating
10. Equipment/Household Purchase and Delivery
Italian Deck Chain 12/20/2012 1/23/2013 - shipped from Italy 12/20 ETA STT 1/23
Pool Towels - on site - JE not happy with leer prefers previous towels.= investigating other op
- shipped to incorrect address - reordered - again delivered 12/28 to incorrect address.
Pace Clocks x 2 units Daphne trying to track down awaiting ETA
Ride on Mower - with bag option. $ 9.500.00 Brice to provide commercial invoice JE approved. Rick K to finalize
Fuel Truck - repair work estimate 515K. Larry to get quote Review purchasing new unit.
Tool Boxes - will forward options MAP
Pool Ladders - ETA VII 1/11/2013
Outside lanterns - unable to get replacements, investigating other options
Media Center - Relax Room - Copenhagen unit selected, will forward options
Desk . Flagpole Pool Cabana - still in Paris awaiting ETA
Rug - Flagpole Pool Cabana - ordered ETA mid Feb
Portable Electric Oven 12/26/2012 1/8/2013 - shipped to FL 12/26 ETA FL 1/8
Small Refigerator ( 4 to 8 bottles) five palms
11. Containers - RO & Generators in remaining container 1/5/2013 - possible offer due 1/5
15. Media -
Stewart Screen 15,500.00 Larry investigating purchase
Blue Ray DUD Played Screen Rm)
Sub and Mini System (Kitchen) Move exsisting system to NY
16. Cell Repeater & Broadband -
YAGI and repeater $ 2,200.00 1/8/2013 HE approved lermaine to order
Hangers for Lice Jackets I Carlos to purchase 8
4 of 5
EFTA_R1_00345147
EFTA01909620
Ui • Island
Punch Ust/Project Ust
as of 1/3/2013
PRIORITIZE PROJECT DESCRIBTION I laborers I Hours tabor Con rants ova Total Estimated cost Start Date End Date I Notes
a
I. Equipment and Vehicles
- No equipment or vehicles etc off the Island unless approved
19. Mos rings —
Dempsey had requested Inspection - Hodge preparing letter to DPNR(JP Oriel) and is
- Request inspection from USCG - Darren completing army corp certification form
8. It ngafel
rfu le .
Fuel Containment Pad - Plan ready bar submission,
Permit status i Permit has been reviewed awaiting P. Smiths signature
Bolke and fuel availability _ I.V to discuss with Bolke
tease _ 1/8/2013 tease to be submitted on Tuesday. Jan 8, 2013
Cell_tosvers Draft letter for review with DM re ATT real estate division requesting tower
Internetservice Option to install Broadband VI at one location I S99) a month 10 meges Continual . 5 up
full time house keeper
IT Support I
Big N Barge Captain
land scene supervisor • once a week i
S of S
EFTA_R1_00345148
EFTA01909621
ℹ️ Document Details
SHA-256
28a18c3524dbec9b1fd2b5ea4d777d8c71a465cd498da5e729142ee0b0744590
Bates Number
EFTA01909617
Dataset
DataSet-10
Type
document
Pages
5
💬 Comments 0