Little Saint James & Greater Saint James
Executive Summery — Confidential
Objective:
-To set up a living work load list that divides maintenance and construction projects along with
establishing construction project schedules into the following set up for owner review;
'Test Construction Project No. 1"
1) Pre-Construction
a) General Design / Owner Intent
b) Contractor Bidding / Bid review
c) Determine lead times on specified items
d) Produce "Construction Project Schedule"
e) Award Contract — include project schedule (tool for holding sub-contractors responsible on
times)
2) Construction
a) Phase 1— Site prep work (demo / grading / underground / etc)
b) Phase 2 — Above grade structural / trade work (plumbing / electrical /framing / concrete /
roofing)
c) Phase 3 — Finishes (millwork, flooring, tile, fixtures, painting)
3) Post Construction
a) Final Walk-Through
b) Issue final punch-list
c) Execute final punch-list
d) Receive any warranties from contractors (appliances, mechanical equipment, etc)
e) Sign offs stating work has been completed
f) Issue Payment of 15% retainer to contractor
Project List:
-The attached project list is inclusive of Little St James and Greater St James. The projects are
collection of maintenance, renovation and new construction projects. This list should also include a
priority number 1-10 at the owners discretion as to what projects are to take precedence to others.
EFTA00804944
ℹ️ Document Details
SHA-256
2dba9fc60b0d63388d6959ed291faa290a4926fa7734c7d22a740989e5ccfd6b
Bates Number
EFTA00804944
Dataset
DataSet-9
Type
document
Pages
1
💬 Comments 0