📄 Extracted Text (11,765 words)
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
system or subsystem exceeding $10
million unless certain conditions were
Keyeite Yellow Flag - Negative Treatment
Distinguished by Gengler v. U.S. ex rel. its Dept. of Defense and met, and (2) Department's failure to
Navy. E.D.Cal.. August 24.2006 comply with statute's requirements did
F.3d 1368 not render contract void ab initio.
United States Court of Appeals,
Federal Circuit. Questions answered and case
remanded.
AMERICAN TELEPHONE
AND TELEGRAPH COMPANY, Rader, Circuit Judge, concurred in the
and result and filed opinion in which Mayer,
Lucent Technologies Inc., Chief Judge, and Lourie, Circuit Judge,
Plaintiffs—Appellants, joined.
v.
UNITED STATES, Plager, Circuit Judge, dissented in part,
Defendant/Cross—Appellant. concurred in part, and filed opinion.
Nos. 95- 5153, 95- 5154.
Opinion, 124 F.3d 1471, vacated.
May 26, 1999.
Synopsis West Headnotes (5)
Contractor sued Government under
Contract Disputes Act for recovery
Ill Public Contracts
of expenditures under research and
development contract. The Court of • Compensation
Federal Claims, John P. Wiese, J., 32 United States
Fed.CI. 672, ruled that contract was • Compensation
void and that quantum meruit relief Navy contract for
was available, but certified questions development of ship-towed.
for interlocutory appeal. The Court undersea surveillance system
of Appeals originally affirmed, but, was for "major system or
on rehearing en banc, the Court subsystem," for purposes
of Appeals, Pauline Newman, Circuit of statute prohibiting
Judge, held that: (1) Navy contracts for Department of Defense from
development of ship-towed, undersea entering into fixed price
surveillance system was for "major contracts for development of
system or subsystem," for purposes major system or subsystem
of statute prohibiting Department of exceeding $10 million unless
Defense from entering into fixed price certain conditions were
contracts for development of major met, notwithstanding either
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 1
EFTA00797875
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
agency's reliance on separate ab initio, as statute itself
statute to define major system did not announce sanction
as having $75 million floor of contract invalidity, and
or fact that contract was contract had been fully
funded over multiple years. performed. Act December 22,
10 U.S.C.A. § 2302(5); Act 1987, § 101(b), Sec. 8118, 101
December 22, 1987, § 101(b), Stat. 1329.
Sec. 8118, 101 Stat. 1329.
24 Cases that cite this
9 Cases that cite this headnote headnote
121 Administrative Law and 141 Public Contracts
Procedure offr. Unauthorized or Illegal
e- Erroneous or Contracts
unreasonable construction; United States
conflict with statute o- Unauthorized or Illegal
Although an agency's Contracts
interpretation of a statute Invalidation of government
it administers is indeed contract is not a necessary
entitled to deference, agency consequence when a statute
discretion does not extend or regulation has been
to changing a clearly stated contravened, but must be
dollar figure. considered in light of
the statutory or regulatory
Cases that cite this headnote purpose, with recognition
of the strong policy of
131 Public Contracts supporting the integrity of
1— Compensation contracts made by and with
United States the United States.
Compensation
13 Cases that cite this
Failure of Department headnote
of Defense to comply
with statute setting forth
internal review and reporting 151 Contracts
requirements for fixed price o- Nature and Essentials in
contract for development of General
major system or subsystem The invalidation of a contract
exceeding $10 million did not after it has been fully
render such contract void performed is not favored.
WESTLAW 2019 Thomson Reuters. No claim to original U.S. Government Works. 2
EFTA00797876
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
amicus curiae Federal Circuit Bar
11 Cases that cite this Association. With him on the brief was
headnote Clarence T. Kipps, Jr. Of counsel on the
brief were L. James D'Agostino, Reed
Smith Shaw & McClay, of McLean,
Virginia; and George Hutchinson,
Attorneys and Law Firms Executive Director, Federal Circuit Bar
Association, of Washington, DC.
*1369 C. Stanley Dees, McKenna &
Cueno, L.L.P., of Washington, DC, Before MAYER, Chief Judge,
argued for plaintiffs-appellants. With NEWMAN, PLAGER, LOURIE,
him on the brief was J. Keith Burt. Of CLEVENGER, RADER, SCHALL,
counsel on the brief were Thomas R. BRYSON, and GAJARSA, Circuit
Suher, and Dean L. Grayson, Lucent Judges. *
Technologies, Inc., of Washington,
DC. Opinion
Bryant G. Snee, Assistant Director,
Commercial Litigation Branch, Civil Opinion for the court filed by Circuit
Division, Department of Justice, Judge NEWMAN, in which Circuit
of Washington, DC, argued for Judges CLEVENGER, SCHALL,
defendant-cross appellants. With him BRYSON, and GAJARSA join.
on the brief was David M. Cohen, Opinion concurring in result filed by
Director. Of counsel on the brief were Circuit Judge RADER, in which Chief
Robert D. Hogue, James H. Haag, Judge MAYER and Circuit Judge
Attorneys, Office of General Counsel, LOURIE join. Opinion dissenting-in-
Department of the Navy, of Arlington, part and concurring-in-part filed by
Virginia. Circuit Judge PLAGER.
Caryl A. Potter, III, Sonnenschein NEWMAN, Circuit Judge.
Nath & Rosenthal, of Washington, DC,
We took this appeal and cross-appeal
for amicus curiae Electronic Industries
en banc to reconsider the questions
Alliance and Aerospace Industries
of law presented, upon certification
Association of America, Inc. With him
for interlocutory appeal, concerning
on the brief were Elizabeth A. Ferrell,
the applicability of § 8118 of the
of Washington, DC; Alan M. Posner,
Defense Appropriations Act of 1987 to
of Chicago, Illinois; and Roger K.
a contract between the Department of
Heidenreich, of St. Louis, Missouri.
the Navy and the American Telephone
John Lloyd Rice, Miller & Chevalier, and Telegraph Company. The Court of
Chartered, of Washington, DC, for Federal Claims ruled that in view of the
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 3
EFTA00797877
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
failure of the Department of Defense to Diameter Array. The contract was
comply with § 8118, the contract, which a "Total Package Procurement,"
had been performed, was void ab initio. requiring design of shipboard and
We now hold that the contract was shore-based electronics, ship-winch
not void, and remand to the Court of interface and tow cable, and an
Federal Claims for further proceedings acoustic and electronic array some
in accordance with this premise. 8,000 feet long, to meet the new Soviet
submarine capabilities. The contract
required research, development, and
The Reduced Diameter Array Contract the delivery and testing of an
This contract arose in Cold War engineering development model, at
response to the new ultra-quiet a fixed ceiling price of $19,221,630,
Soviet submarines, which were and included an option to the
difficult to monitor using available Navy to acquire a second engineering
technology and equipment. Effective development model at a fixed ceiling
antisubmarine response requires that price of $3,510,253, and an additional
hostile submarines be reliably detected, option to acquire three production-
classified, located, and tracked. The level models at a fixed ceiling price of
Navy, among its programs for this $8,475,466.
purpose, employed an integrated
undersea acoustic sonar system called The contract was successfully
the Surveillance Towed—Array Sensor performed by AT & T over a period of
System (SURTASS). In SURTASS a five years. With the price adjustments
suitably equipped surface vessel tows an to which the Navy agreed during
array of undersea detection equipment performance, the final fixed price
through the ocean, while the equipment was approximately $34.5 million. AT
collects and transmits appropriate data & T states that technical problems
for processing on shipboard and for and unknowns arose throughout
transmission to shore-based facilities. performance, and that its total cost was
The President's Annual Report *1370 at least $91 million. The Navy rejected
to the Congress for fiscal 1987, on AT & T's requests for restructuring the
the topic of Antisubmarine Warfare contract and other relief, although AT
Forces, referred to SURTASS as & T directed attention to § 8118 of
"[o]ne of our most important ongoing the Defense Appropriations Act and
programs in this area." Id. at 188. relevant Department of Defense policy
directives concerning procurement of
On December 31, 1987, after research and development for new
competitive bidding, the Navy awarded technologies.
AT & T a fixed price incentive
fee contract for a subsystem of
SURTASS, referred to as the Reduced
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 4
EFTA00797878
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
AT & T duly brought suit in the pursuant to unjust enrichment
Court of Federal Claims under the principles.
Contract Disputes Act. On cross
motions for summary judgment the A panel of the Federal Circuit, by split
issues arising from the enactment of decision, affirmed the ruling that the
§ 8118 were presented and argued. contract was void ab initio. The court
The Court of Federal Claims ruled also held that no relief was available
that § 8118 applied to this contract, to AT & T on any theory, except
that it had not been complied with perhaps to replevin the goods that had
by the Department of Defense, and been delivered to the Navy. Upon the
that the contract consequently was void petitions of both sides we have reheard
ab initio. Responding to AT & T's the matter en banc. I
proposal that the appropriate remedy
was to reform the contract into the
cost-reimbursement form favored by Section 8118 ofthe Defense
§ 8118, the Court of Federal Claims Appropriations Act of1987
held that since there had never been a Concern about the use of fixed price
valid contract it could not be reformed. contracts for research and development
The court held, however, that AT & *1371 phases pervades defense
T was entitled to compensation for procurement. In 1971 Department of
its work on the basis of quantum Defense Directive (DODD) 5000.1
meruit, on a theory of implied-in- stated that "[i]t is not possible to
fact contract. Before proceeding to determine the precise production cost
determine quantum, the court certified of a new complex defense system
for interlocutory appeal, in accordance before it is developed," and established
with 28 U.S.C. § 1292(d)(2), the the policy of using cost-reimbursement
following questions: price terms for procurement of research
and development. The Directive
(i) whether a contract executed in stated: "Fixed price contracts are
violation of statutory restrictions on normally not appropriate for research
the obligation and expenditure of and development phases." DODD
appropriated funds may be declared 5000.1 & D.9.g (as amended, Sept.
void from the start at the instance of 1, 1987). The Federal Acquisitions
the performing contractor, and, if so, Regulations governing R & D
contracts also embodied this policy.
(ii) whether compensation for See, e.g., 48 C.F.R. § 35.006(c)
benefits conferred upon the (1984-1998) ("Because the absence of
Government (pursuant to the voided precise specifications and difficulties
contract) can be predicated on an in estimating costs with accuracy
implied-in-fact contract with the (resulting in a lack of confidence in cost
amount of recovery to be determined estimates) normally precludes using
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 5
EFTA00797879
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
fixed-price contracting for R & D, the the cost-reimbursement type contract.
use of cost-reimbursement contracts is Id. at 11.
usually appropriate.")
At ensuing hearings on the 1988
The record states that in the 1980s, Defense budget, concern was expressed
despite these policy directives, the Navy about the continuing use of fixed
returned to fixed price contracting price contracts for high-cost, high-
for R & D as part of the risk development projects, as well
Total Package Procurement concept. as concern for meeting congressional
This in turn led to congressional oversight and allocation obligations
investigations and hearings. An under this form of procurement.
investigation conducted by the House Department of Defense Appropriations
Appropriations Committee concluded for 1988: Hearings Before the
that for the development phases Defense Subcomm. of the Comm. on
of new technologies, the Navy's Appropriations, 100th Cong., 454-
use of fixed price contracting 55 (1987). Legislatively implementing
resulted in program delays, cost these concerns, the House included in
overruns, contractor claims, non- the Defense Appropriations Act of 1987
participation, and litigation. See the provision that became § 8118:
Surveys & Investigations Staff, Report
to the Comm. on Appropriations, U.S. § 8118. None of the funds provided
House of Representatives: Navy Fixed for the Department of Defense in this
Price Contracting in the Research, Act may be obligated or expended for
Development, Test and Evaluation fixed price-type contracts in excess of
(RDT & E) Account, 100th Cong., $10,000,000 for the development of
1st Sess. (1987). The Report stated a major system or subsystem unless
that: "Although Navy officials at the Under Secretary of Defense for
the headquarters level have predicted Acquisition determines, in writing,
immense success for the acquisition that program risk has been reduced
policy, the opinions expressed by Navy to the extent that realistic pricing
and other Service field procurement can occur, and that the contract type
officials and technical experts indicated permits an equitable and sensible
that [fixed price contracting] generally allocation of program risk between
[has] proved unsuitable in an R the contracting parties: Provided,
& D environment." Id. at ii. The That the Under Secretary may
Report concluded that the nature not delegate this authority to any
of the work in research and persons who hold a position in the
exploratory development contracting Office of the Secretary of Defense
"most frequently necessitates" use of below the level of Assistant Under
Secretary of Defense: Provided
further, That the Under Secretary
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 6
EFTA00797880
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
report to the Committees on Department, and required quarterly
Appropriations of the Senate and reports of such awards to the House and
House of Representatives in writing, Senate Appropriations Committees.
on a quarterly basis, *1372 the The government argues first that '8118
contracts which have obligated did not apply to the Reduced Diameter
funds under such a fixed price-type Array contract, thus eliminating any
developmental contract. need for the Navy to have complied
with the statute. The Court of Federal
Pub.L. No. 100-202, § 8118, 101 Claims correctly held otherwise.
Stat. 1329, 1329-84 (Dec. 22, 1987).
The accompanying Conference Report Section 8118 by its terms applies to
reiterated congressional concern that "fixed price-type contracts in excess
the risks of failure and of cost of $10,000,000 for the development of
uncertainties be allocated equitably a major system or subsystem." The
between government and contractor, government argues that the Reduced
and stressed the desire to "maintain Diameter Array is not a "major
the government's credibility as a system," referring to a memorandum
reliable business partner." H.R. Conf. issued six weeks after enactment of §
Rep. No. 100-498 at 623 (Dec. 22, 8118 wherein the Under Secretary of
1987). Congress referred to the burden Defense defined "major system" for the
of a fixed price contract on the purposes of § 8118 as a system having
contractor when the miscalculation of a contract cost of over $75,000,000. In
development cost may have been that a Memorandum for Service Acquisition
of the government agency as well as Executives, Directors of the Defense
the contractor, and to the reluctance Agencies issued February 11, 1988,
of some highly qualified firms to enter Under Secretary of Defense for
into such contracts. The Conference Acquisition Costello instructed that
Report was unambiguous: "Fixed price "[t]he definition of major system at 10
contracts are normally not appropriate U.S.C. § 2302(5) is the definition of
for research and development phases." that term for the purpose of [§ 8118]."
Id. at 624. Thus Congress acted to This content was incorporated into
adjust the risks of developing the SECNAV Instruction 4210.6A (April
advanced technologies needed in the 13, 1988).
service of national defense.
121 Section 2302(5) is a provision
of chapter 137 of Subtitle A—
Application of Section 8118
General Military Law, which as then
[lj Section 8118 prohibited the award
written defined "major system" as a
of certain fixed price-type contracts
system costing more than $75,000,000
unless the program risk was evaluated
at a high level within the Defense
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works.
EFTA00797881
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
for research, development, test, and Inc., 467 U.S. 837, 842-43, 104 S.Ct.
evaluation: 2778, 81 L.Ed.2d 694 (1984) ("if the
intent of Congress is clear, that is the
10 U.S.C. § 2302(5). The term "major end of the matter").
system" means a combination of
elements that will function together In addition, the AT & T contract
to produce the capabilities required itself, and the Space and Naval
to fulfill a mission need. The elements Warfare Systems Command's guide
may include hardware, equipment, to the SURTASS, described the
software or any combination thereof, Reduced Diameter Array as a
but excludes construction or other "subsystem." Subsystems were not
improvements to real property. A defined in § 2305(5) and were not
system shall be considered a major mentioned in the Memorandum of the
system if (A) the Department of Under Secretary. However, subsystems
Defense is responsible for the costing more than $10,000,000 were
system and the total expenditures explicitly included in § 8118. Although
for research, development, test, the government now argues that the
and evaluation for the system Under Secretary's Memorandum and
are estimated to be more than SECNAV Instr. 4210.6A really covered
$75,000,000 (based on fiscal year a major system or a subsystem of
1980 constant dollars) or the eventual a major system, this interpretation is
total expenditure for procurement of contrary to the plain text of these
more than $300,000,000 (based on documents. It is apparent that the
fiscal year 1980 constant dollars).... Memorandum was contrary to the
statute, and in all events that it did not
The government argues that the agency
include subsystems such as the Reduced
had discretion to define the § 8118
Diameter Array.
"major system" in accordance with
'2302(5), and thereby to place a
The government also argues that not
$75,000,000 floor on the systems to
all of the funds expended under
which § 8118 would apply. However, it
the Reduced Diameter Array contract
was not within the agency's discretion
were appropriated in the corresponding
to rewrite § 8118 to replace the statutory
Appropriations Act, and thus that
threshold of $10,000,000 with that
the § 8118 prohibition on obligating
of $75,000,000. Although an agency's
or expending funds does not apply.
*1373 interpretation of a statute
Indeed, the contract was structured
it administers is indeed entitled to
for multi-year incremental funding.
deference, agency discretion does not
However, it is undisputed that the
extend to changing a clearly stated
starting research and development
dollar figure. See Chevron, U.S.A., Inc.
effort drew on several millions of
v. Natural Resources Defense Council,
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 8
EFTA00797882
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
dollars of appropriated funds. The the Senate and House Appropriations
multi-year funding does not excuse the Committees. Although the government
Defense Department from compliance stresses that the contract was awarded
with § 8118. only nine days after the enactment of §
8118, this does not excuse the failure of
Moreover, contrary to the all compliance.
government's argument, which is made
but not strongly pressed, this case does
not involve a funding deficiency or Consequences ofAgency
implicate the Anti—Deficiency Act, 31 Noncompliance With § 8118
U.S.C. § 1341. See Hercules Inc. v. PI We turn to the certified question
United States, 516 U.S. 417, 427, 116 of the consequences of this failure
S.Ct. 981, 134 L.Ed.2d 47 (1996) ("The of compliance by the Department of
Anti-Deficiency Act bars a federal Defense. AT & T states that § 8118
employee or agency from entering into was enacted at least in part for its
a contract for future payment of money protection, and that the agency, by
in advance of, or in excess of, an failing to obey the law, can not deprive
existing appropriation."); see generally AT & T of the protection of the
Ferris v. United States, 27 Ct.CI. law. AT & T argues that § 8118
542, 546 (1892) ("An appropriation is a "mandatory statute" restricting
per se merely imposes limitations the agency's authority to obligate and
upon the Government's own agents ... expend funds, and that the Navy's
its insufficiency does not pay the direct contravention of § 8118 rendered
Government's debts, nor cancel its the Reduced Diameter Array contract
obligations, nor defeat the rights of void ab initio.
other parties.") There is no issue in this
case of lack of appropriated funds. The government responds that
Congress chose and intended to enforce
We affirm the determination of the § 8118 *1374 through its oversight
Court of Federal Claims that § powers, and that AT & T can not
8118 applies to this contract. The benefit from whatever lapses may
government does not dispute that have occurred within the Department
the requirements of § 8118 were not of Defense in its compliance with
met by the Department of Defense. congressional oversight legislation. The
There is no assertion that the Under government stresses that § 8118 did not
Secretary of Defense for Acquisitions provide that these fixed price contracts
made or had made the program risk were prohibited, but only that the
and pricing determinations required Defense Department must review the
by § 8118, and no report of this risk and its allocation at a specified
contract is stated to have been made to executive level, and must report to
Congress on a quarterly basis.
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 9
EFTA00797883
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
history"). Congress simply tightened
14] Legislative intent and precedent the reporting provision, by moving
both lead to the conclusion that the from after-the-fact quarterly reports
AT & T contract was not void ab to before-award reports. Indeed, the
initio as a consequence of the agency's House version of § 8118 had initially
noncompliance. Invalidation of the required before-award reports, but
contract is not a necessary consequence this was dropped in Conference in
when a statute or regulation has been favor of the Senate version "to
contravened, but must be considered reduce the appearance of congressional
in light of the statutory or regulatory micromanagement." H.R. Conf. Rep.
purpose, with recognition of the strong No. 100-498 at 623 (Dec. 22, 1987).
policy of supporting the integrity of
contracts made by and with the United The Conference Report stated that if
States. In United States v. Mississippi Defense Department policy did not
Valley Generating Co., 364 U.S. 520, become more uniform, "more severe
81 S.Ct. 294, 5 L.Ed.2d 268 (1961) the restrictions" would be imposed. Id. This
Court explained that when a statute remark carries no hint of, and indeed
"does not specifically provide for the belies, an interpretation that § 8118 was
invalidation of contracts which are intended, upon enactment, to invalidate
made in violation of [its provisions]" any contract made without meeting
the court shall inquire "whether its internal review and reporting
the sanction of nonenforcement is requirements, for such a "restriction"
consistent with and essential to would already be extremely "severe."
effectuating the public policy embodied The statutory shift to before-award
in [the statute]." Id. at 563, 81 reports in succeeding years would be a
S.Ct. 294. Thus the policy underlying trivial discipline indeed, if meanwhile
the enactment must be considered all of the fixed price contracts within the
in determining the remedy for its statutory scope, although in the process
violation, when the statute itself does of performance, or as in this case fully
not announce the sanction of contract performed, were void ab initio.
invalidity.
Only a few months after enactment
The policy embodied in § 8118 of § 8118 the House Appropriations
is elucidated in the congressional Committee reported that the
response when § 8118 did not receive "enforcement of existing policy in this
full compliance from the Department of area has not yet been demonstrated,"
Defense. See Alabama Rural Fire Ins. H.R.Rep. No. 100-681 at 147 (June 10,
Co. v. United States, 215 Ct.C1. 442, 572 1988), and recommended a pre-award
F.2d 727, 733 (1978) ("illegality may reporting requirement (which was
be proved with reference to legislative included in the enactment for the next
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 10
EFTA00797884
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
fiscal year). The Senate Armed Services negate any reasonable inference that
Committee, considering this renewal, Congress intended simply to render
stated explicitly that noncompliance void ab initio, even after full
was not intended to be "the basis for performance, any fixed price contract
litigating the propriety of an otherwise for which the Under Secretary's review
valid contract": of risk allocation and the report to
the Committees were omitted. Congress
The committee recognizes that there can not have intended to charge
are circumstances in which fixed- the contracting partner with adverse
price development contracts are consequences depending on whether
appropriate (e.g., when costs and the Defense Department carried out the
foreseeable program risks can be internal responsibilities and filed the
reasonably anticipated), and the reports that Congress required.
committee expects the Department to
establish clear guidelines under this Nor is it the judicial role to
section for use of such contracts. discipline the agency's noncompliance
with the supervisory and reporting
*1375 It is the intent of the
instructions of congressional oversight.
committee that this section be
See Longshore v. United States,
applied in a manner that best serves
77 F.3d 440, 443 (Fed.Cir.1996)
the government's interests in the long
("Congress has undoubted capacity to
term health of the defense industry,
oversee the performance of Executive
and that this section not be used as
Branch agencies, consistent with its
the basisfor litigating the propriety of
constitutional authority. It is not for
an otherwise valid contract. Nothing
this court to instruct Congress on how
in this section shall be construed
to oversee and manage its creations.");
to affect the requirements of section
E. Walters & Co. v. United States, 217
8118 of the Department of Defense
Ct.CI. 254, 576 F.2d 362, 367 (1978)
Appropriations Act, 1988.
("The fact that a procurement practice
(Emphasis added.) S.Rep. No. 100- is prohibited does not necessarily mean
326, 100th Cong., 2d Sess. at 105 that it is therefore actionable. The
(May 4, 1988). This explicit statement discipline to be administered in such
of intent weighs heavily against cases is a responsibility of the cognizant
judicial invalidation of "an otherwise procurement officials within the agency
valid contract," for the clearly stated [and not] by this court"); cf. National
congressional purpose is contrary. Treasury Employees Union v. Campbell,
654 F.2d 784, 794 (D.C.Cir.1981)
These congressional responses, made (by statutory requirement that the
with knowledge of the agency's Comptroller General report on certain
imperfect compliance with § 8118, expenditures "Congress itself is in a
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 11
EFTA00797885
American Tel. 8 Tel. Co. v. U.S., 177 F.3d 1368 (1999)
position to monitor and enforce its Schoenbrod v. United States, 187 Ct.CI.
spending limitations. It is not for 627, 410 F.2d 400, 403-04 (1969). We
us to question the effectiveness of take incidental note that the case at
existing remedies and infer additional bar also involved a disappointed bidder
remedies.") raising post-award objections, *1376
and that none of the objections were
Both the DoD administration of § based on § 8118.
8118, and the congressional response
to this administration, make clear In Harbor Gateway Commercial
that Congress did not intend that Property Owners' Ass'n v. United States
this enactment would terminate fully Environmental Protection Agency, 167
performed contracts because of this F.3d 602 (D.C.Cir.1999), a case stressed
flawed compliance. in the dissenting opinion hereto, the
court voided an EPA action because the
151 Precedent reinforces our conclusion Governor had not signed the request
that the Reduced Diameter Array as the statute required. However,
contract is not void ab initio. The there was no issue of performance,
invalidation of a contract after it has or reliance, or any other contractual
been fully performed is not favored. element. It is not before us to decide
Precedent shows that those contracts whether either party to the Reduced
that have been nullified, based on a Diameter Array contract could have
failure to meet a statutory or regulatory voided the contract early in its life
requirement, are contracts that have and without penalty; the contract was
not been substantially performed. E.g., performed for over five years, with no
Alabama Rural Fire Ins. Co. v. United record suggestion from either party that
States, 215 Ct.CI. 442, 572 F.2d 727, because of § 8118 there was no contract.
733-34 (1978). In Prestex, Inc. v.
United States, 162 Ct.CI. 620, 320 F.2d Judicial reluctance to annul performed
367, 374-75 (1963), the court held a contracts when the government did not
contract invalid, and refused to allow comply with a statutory or regulatory
any recovery because no performance requirement was explained by the Court
had occurred. It is not surprising that of Claims in John Reiner & Co. v.
much of the litigation raising issues of United States, 163 Ct.CI. 381, 325 F.2d
violation of statute or regulation at the 438, 440 (1963), stating that "the court
inception of government contracts has should ordinarily impose the binding
arisen in the bid protest context, where stamp of nullity only when the illegality
the asserted illegality has been explored is plain." In Reiner the court recognized
before substantial performance has the "dilemma" of a contractor who
occurred. E.g., CACI, Inc. v. Stone, becomes aware, while deep in the
990 F.2d 1233, 1235 (Fed.Cir.1993); performance of a contract, of a possible
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 12
EFTA00797886
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
procurement illegality he did not cause: (1978) the court sustained a contract
the contractor must either continue that was awarded after the contracting
to perform a contract of uncertain officer had negligently failed to meet
validity, or discontinue performance a regulatory responsibility; the court
and risk severe penalties if a court later held that the non-compliance with
disagrees with his assessment of the regulation was "a matter for internal
illegality. resolution" and "did not render the
resultant contract a nullity." In Clark
When a contract or a provision v. United States, 95 U.S. 539, 542, 24
thereof is in violation of law but L.Ed. 518 (1877) the Court held a parol
has been fully performed, the courts contract void for violation of the statute
have variously sustained the contract, of frauds, but allowed recovery on an
reformed it to correct the illegal implied contract theory.
term, or allowed recovery under an
implied contract theory; the courts The entirety of precedent strongly
have not, however, simply declared the supports our conclusion that the
contract void ab initio. For example, Reduced Diameter Array contract
in LaBarge Products v. West, 46 is not void ab initio. Precedent
F.3d 1547, 1552-53 (Fed.Cir.1995) does not favor the invalidation,
there was an illegal disclosure by based on governmental noncompliance
the government during bidding; this with internal review and reporting
court noted that the contract had procedures, of a contract that has been
been substantially performed and held fully performed by either contracting
that a valid contract existed despite party. 2
the violation. In Beta Systems, Inc. v.
United States, 838 F.2d 1179, 1185- *1377 Although the parties discuss
86 (Fed.Cir.1988) the court allowed possible remedies, the issue of what
reformation of the contract price term relief may be available to AT & T
to correct a regulatory violation, stating is not before us, for the Court of
that "[t]he risk of unintentional failure Federal Claims did not consider AT
of a contract term to comply with a & T's claims on the premise that the
legal requirement does not fall solely underlying contract was not void. We
on the contractor." In Urban Data have not considered this issue, and
Systems, Inc. v. United States, 699 F.2d express no view thereon.
1147, 1154 (Fed.Cir.1983) the court
held that a contract price term that
was contrary to law did not invalidate Answers to the Certified Questions
the fully performed contract. In Trilon For the reasons we have discussed, we
Educational Corp. v. United States, conclude that the agency's failure to
217 Ct.C1. 266, 578 F.2d 1356, 1360 comply with the obligations of § 8118
WESTLAW © 2019 Thomson Reuters. No claim to original U.S. Government Works. 13
EFTA00797887
American Tel. & Tel. Co. v. U.S., 177 F.3d 1368 (1999)
did not render the Reduced Diameter price-type contracts in
Array contract void ab initio. Any excess of $10,000,000
failure by the Department of Defense in for the development
its internal compliance with § 8118 can of a major system or
not be invoked, particularly after full subs
ℹ️ Document Details
SHA-256
2e86ef0f0de01b6b34bf06ce3c0b68ba8b992a4a74f554d61aef8377a22f8be3
Bates Number
EFTA00797875
Dataset
DataSet-9
Document Type
document
Pages
27
Comments 0