From: Stephanie Remington
To: J <[email protected]>
Cc: Patrick Cena , William B Hague >, Daphne
Wallace
Subject: Re: Progress Report_040119_040719
Date: Mon, 08 Apr 2019 18:08:06 +0000
Patrick and Boscoe went to PR to look at the Midship Marine 44 1/2 ft aluminum catamaran. With new engines,
possibly the bottom reskinned, and some paint and other cosmetic work, Boscoe and Patrick believe that this
could be a very nice crew boat to last for a long time. It had a COI for 54 people. It has a lot of space but is not
too big. Patrick says it's the perfect size for what we need. It's a very well built boat. They are researching now
the cost of engines, reskinning, etc. in order to have a full report for you while you are here. I am copying
Boscoe and Patrick so they can provide more details.
Details for engineering doors were confirmed and ordered. We do not yet have a ship date but I will work with
Daphne to expedite this information for you.
We are expecting the following this week (6 of 7 BOLs arriving today): Chromix for roads, new electric car, big
light order, 6 water heaters, Roof kits for Xmas Cove, Gemini shipment, doors for 5 Palms, 2 55 gallon drums of
rust bandit, lattice for tiki
Stephanie Remington
LSJE, LLC
On Mon, 8 Apr 2019 at 13:30, J [email protected]> wrote:
try to give more info what happened wtih crew boat , when are enginnering doors arrivimg. ?
On Mon, Apr 8, 2019 at 1:28 PM Stephanie Remington > wrote:
Please note:
This is a summary of the last week's focus, not a comprehension of all projects.
Carpentry. Lattice frames are complete. Estimated arrival for lattice is 4/9. Set cabinets in tiki.
Assisted with hauling fumiture for cabanas. Reassembled all beds for cabanas. Assembled desk in
FPP Cabana. Still working on gates for FPP. New latches purchased for lighter gates. Still
weatherproofing roof connection between tiki kitchen and main tiki on LSJ.
Electrical/Plumbing. Reassembled Cabana 3 sink, vanity, toilet. Ran new trench and conduit for
5 Palms power fiber optic — completed. Inventorying parts for water distribution manifold rebuild on
LSJ. This is the first step to redoing all the pumps to remedy the water pressure issues island
wide. Installed electrical for new dryer in staff cottage — LSJ. Fine tuned electric and plumbing in all
cabanas. Created drain in A/C unit under master to remedy dripping issue on wall.
Engineering.
Records updates. Plexy glass on cat 325. Prepare concrete car mix. Assist Cash in generator
room. Carry fumiture to cabanas. Prepare fuel truck for inspection. Bike maintenance. Clean
hammer on trackhoe. Kawasaki cart hand brakes. Troubleshoot door latch on cart. Pressure wash
fuel truck. Water to GSJ w new tractor. Ash (rust guy) working on blue and Polaris xp. Paint
generator lights.
Heavy Equipment. Dug trench for 5 Palms power and fiber repair; work complete.
Jackhammered stone at Pebble Beach. Several loads of water to GSJ for new plants and pool.
EFTA01033309
Took delivery of 4 loads of topsoil for new planter at main compound. Assisted with unloading BOL
shipments. Fuel truck re-registered. Delivered 2000 gallons of diesel - St. Thomas to GSJ.
Housekeeping. Cleaned and setup all cabanas, chillax, library (after rug installation), flagpole
pool, and master (after cistern work).
Landscaping/Masonry. Continuing at Pebble Beach. Assisted with rug install in library. Planting
by GSJ tiki. Planting at container building at Christmas Cove will occur once roof is in place as
scaffolding will need to be utilized.
Marine. Went to PR to assess possible crew boat.
Painters. Finished painting interior of all cabanas, chillax and bath. Paint ceiling to floor storage
room in tunnel after cleaning guys cleaned. Rust remediation and paint at tower antenna.
Following the rust guy and cleaning guys as needed.
RO/Maintenance. Oversee cistern cleaning and sealing. Second coat has been applied. Now
sealed and will cure for 7 days. Then will be ready for fill. New ozone system for cistern has been
purchased and is approximately one week out. Desal maintenance and pools.
Contractors on island:
Jeffers — Coloring will be delivered to LSJ Monday 4/8. Has been asked repeatedly by Daphne and
Mike for a start date. Could use a nudge from Rich.
Danny — Continuing work on MC Flower Bed.
Kitchen Solvers -- Countertops scheduled for install May 3-6.
Paul's Petroleum — will be on island week of April 22 to install high volume diesel nozzle so we can
fill our own truck
Other Notes:
Rust remediation. Rust guy tasked to set cabinets in tiki and address leaking a/c beneath master.
Now working on generator room. Very big rust project!
Master cistern. Second round of thoroseal complete. Being filled now.
Proposal for storm Shutters for RO, Generator, GSJ staff cottage, LSJ staff cottage — submitted to
Rich and was approved.
All interior and exterior doors for RO, generator buildings ordered.
40X60 replacement building for engineering has been ordered.
Construction drawings for GSJ staff cottage have been submitted.
Stephanie Remington
LSJE, LLC
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
EFTA01033310
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to [email protected], and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA01033311
ℹ️ Document Details
SHA-256
34b582492249bda3cbcd371b6a5d17348333755cf885d475bccee973fe5289ff
Bates Number
EFTA01033309
Dataset
DataSet-9
Type
document
Pages
3
💬 Comments 0