CROWN BAY MARINA
Hurricane Irma Repair Estimate by Ketih Pomeroy, PFPE & Fran Woods, Meridian L.P.
See Crown Bay Marina Hurricane Damage Evaluation 10 Jan, 2018 by Paul Ferreras, PE
MV Culebra II 9,282
45' Sailboat 55,549
Seatow 40' 347
Carabena 375,959
LS1 1 123,585
Run Aweigh 1,642
Morningstar/ Evening Star 239,947
MV Skyfall 2.0 136,644
Cruz Bay 1 2,242
Sub-total 945,197
Contingency 20% 189,039
Direct cost 1,134,236
Construction Managers Fee 33,082
Construction Supervision 60,000
Total 1,227,318
EFTA00811381
COST ANALYSIS SHEET
Project CROWN BAY MARINA RECONSTRUCTION
Date: 1/74/2018
c", sion no LABOR MATERIAL EQUIPMENT SUB TOTAL COST
DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL TRADES UNIT PRICE TOTAL
L511 landing Craft
B Dock 3-5 120'
Finger Pier ea 72'
Demolition 1 LS 15000 15,000
Dolphin Pilings 3-4 6 ea 0 0 0 30000 5000 30.000
Replace Steel Piles 0 ea 6,000 0
Rebuild Finger Pier 1 section 0 11500 11500 0 5000 5,000 16,500
Pile Cap 1 ea 5000 5,000 5.000
Repair Bulk Head 56 II 250 14000 150 8400 100 5600 500 28,000
Side Walk Repair 336 sq.ft. 10 3,360
SUBTOTAL 14000 19900 5600 97.860
OVERHEAD 10% 9.786
FEE 10% 9.786
BOND COST n/a
GROSS RECEIPTS TAX 5% 6.153
OTHER
TOTAL COST 123,585
EFTA00811382
ℹ️ Document Details
SHA-256
3734676b5088bc45a0d432f76a4c4e3166a0df4b9b9469f1ccf4780d0079ed9f
Bates Number
EFTA00811381
Dataset
DataSet-9
Type
document
Pages
2
💬 Comments 0