From: Daphne Wallace
To: Jeffrey Epstein <[email protected]>
Cc: Rich Kahn Jimmy Fraguela
Subject: Proposed Landing Site for WAPA link between LSJ and GSJ - August 10, 2017
Date: Thu, 10 Aug 2017 19:27:03 +0000
Attachments: Proposed_Landing_Site_for_WAPAiink_from_LSJ_to_GSJ_-_August_10,_2017.pdf
Greetings Sir,
Attached below is Mr. Fraguela's and Mt Felix Rey's (WAPA) proposed landing site on GSJ for the electrical
power cable from LSJ.
They are proposing following the same route as the cable from St. Thomas, and coming onto GSJ at a point that
will avoid disturbing the area that is known to contain an underwater grass that is protected.
Mr. Fraguela recommends digging a trench 3 feet in depth that will bring the cable from the point of landing to
the point that you have indicated you wish to have the main power vault constructed.
With you approval of Mr. Fraguela's proposal, he is requesting Ms. Dempsey dive the area to confirm that the
grass is not present. Plan drawings can then be created, sent to WAPA for final review and approval, and the
permit application submitted to DPNR.
Respectfully submitted,
Daphne
EFTA00676933
ℹ️ Document Details
SHA-256
3f6944b051edf5850cdf25802e142031bfb5cf1a5df47bd1d3b3dd6703f72390
Bates Number
EFTA00676933
Dataset
DataSet-9
Document Type
document
Pages
1
Comments 0