Memorandum
To: Darren Indyke
From: Emad Hanna
Re: Paul Gandy Project Update
Date: 07-14-05
Phone System:
Gandy indicated his concerns regarding compatibility issues and increasing
costs with the installation and the increasing monthly costs. Scully is
negotiating with Innovative to reduce the mandatory 100 lines down to 50.
Paul has promised to deliver by Monday July 18th a summary with cost
basis.
Lighting:
Gandy had originally quoted a price under $ 100,000 based on the original
survey, which he admitted that he made a mistake on and it is his fault.
He now states the current estimate is about $ 200,000 higher than anticipated
based on the new site plan, which has considerably more pathways and
added all utility conduits and duct banks for future facilities and a fixture
cost around $ 1,200 per light.
Paul has promised to deliver by Monday July 18th a summary with cost
basis.
EFTA00586320
ℹ️ Document Details
SHA-256
43bc1fa10dc1aee802cdbec8a3ba9dd5f60eb91afe3fa392b4a9aa844a5db91a
Bates Number
EFTA00586320
Dataset
DataSet-9
Type
document
Pages
1
💬 Comments 0