JE Punch List —Sept 16, 2012
1. Clean Up - make as many barge runs as necessary
2. Equipment and Vehicles
- Sell equipment
- No machinery off the island unless approved
- New seats for gators and pro gators — ordered, 2 on back order
- Remaining 2 Queen Seats — leaves Tropical 9/19
- Red Polaris Bike - Power Steering Module for ordered due NM 9/26
Grease & review transmission
3. Computers/Phones
- Rm 3 Phone not working — Danny will review
4. 5 Palms
- Painting Outside — Primer/Base Coat — color as existing — Danny to schedule Ti and Gerry
- Furniture — outside furniture in place — Karen to tie down cushions to resolve wind issues, completed by 10/10
- Picture Frame — measurements forwarded to Sarah - 86 x 70
- Mirrored siding — will continue to reglue — possible mural work
- Piano — retune ASAP, awaiting firm date from Monique
- Transformer Shed — painting 90% complete — door installation pending
- Fiber Work — $2,956.25 quote approved to re-pull fiber, Jermaine coordinate with Danny to begin installation
5. Grotto
- Mattress cover — JE approved buying fabric, making cover locally, will have fabric by 9/23
- Electronic Remote Starter, auto start from Kite House — Danny will install week of 9/23
6. Berm/Too of Hill
- Hydroseed outside — in progress
7. Triangle -
- Must design triangle — awaiting JE direction
- Hydroseed entire area - week of 9/17
8. Flagpole Pool Cabana
- Furniture — desk from Paris ready to ship early September - Sue
9. Floating Dock
- Jet ski bumpers — complete — reviewing whether this type resolves the issues with the jet skis
- Table/Dock Box - Dock box top to be revarnished — Carlos has a possible solution
- Swim Ladder — direction from JE on placement required
10. Chillax Room
— Requires furniture piece for electrical/media equipment, review pieces that are stored in PBI — Sarah
11. Chillax Bathroom
- require blue rugs for bathroom & vanity area — Sarah
12. Mechanical Building Transformer — on STT 9/11 — will schedule pick up week of 9/17
13. Boats
- Lady G — sell — in hurricane storage — offer $60K via JE, Rich to neoigigate pricing
- Lady K — sell — survey forwarded to Darren & Rich, suggested price $225,000
- Big N — repair — at AYH dock — Brice contacting Subbase for quote on completion of punch list items
- inside cleaning 3 days/2 pers $720.00 supervised by Carlos — approved JE
- cylinders in PR, will confirm delivery date 9/17
- Little C — splash and diagnostic testing by Offshore Marine 9/17
14. AC
- Set all air conditioning to 80 degrees EXCEPT gym, guest rooms, and storage areas — they remain at 85 degrees
15. Beach lighting — per JE, replace existing transformers for the beach lighting of palms around the salt pond and
beach — in progress — 70% complete - completion by 9/21
16. Transient Surge Protection — Due Tropical 9/21
EFTA01107304
17. Landscaping — Peter's List
- Pop's Garden — need deer fencing, or some other method of protection, review of shade cloth
- Clean mess, cut grass; trim all vines, acacia — owner's drive, blue beach, gym — work in progress
- Peter to clean the sides of the road — work in progress
- Black Heli Under Pads — install at top of bike path at MC — not enough on site to complete project. Larry forwarding
details
- Review growth of sea grape - engineering area
- Hydroseed all pull box areas & engineering
- Continue to line all roads with stones
- PR Coconut Palms — (5) 12' and (5) 15' palms — order placed 9/14 — wire sent 9/14 — scheduling sailing on Friday 9/21,
EDA on STT and LSJ 9/22
18. Roads
- Priority is Gym road grading — remove sand and re-grade — week of 9/17
- General re-grading of roads — ongoing — Peter
- Betteroads quotes from triangle to crest of road above gym — Asphalt - $71,5000, Concrete - $103,600. Brice to
review details with Betteroads 9/17
19. Library
- AC quote forwarded to Rich Barnett, who had design concerns, awaiting reply from vendor
20. New Employee Bathrooms
21. Gym
- New punching bag — installation to be completed by 9/21
- New front & back doors installation completed by 9/26
22. Beach Office
- complete electrical overall required
- waterproofing/sealing/painting/replace rotten wood required
23. LSJ Mooring — Darren forwarded to Army Corp for final approval — awaiting response
24. Hangar
- Fuel Containment Pad — draft approved, drainage incorporated — survey complete by 9/18-19, forward to the
architect so he can complete the plan by 9/21, submit to DPNR for permitting week of 9/24 (Cecile's update as of 9/14)
25. Main compound
- Projector Screen — new limit switches and motor required — Danny will review 9/17
26. Steel shed — Buck Steel (FL) — Brice to review quote with Carlos 9/17
27. Equipment to be Purchased
— (1) light generator, (2) arms with lights to be hard wired
- (1) skid steer at Tropical — sailing 9/1
- (1) John Deere box and blade — Brice has recommended JD 5101E AWD — loader, scraper, digger, 100hp, enclosed cab
- (1) man-lift
- (1) golf cart — at Tropical 9/17 — sailing 9/19
- (1) dump truck — JE approved purchase, Rich working on price
28. LSJ Mats — for all locations — ordered 9/11
29. Engineering — start empting/relocating items in remaining 20ft containers 10/9
30. Stone Walls — Repair work to replace missing loose stones — Gerry & TJ — Danny to schedule them
31. Solar Lights — installation COMPLETE JE does not like the "white light", likes a "soft white" light — JE to review when
on site
32. Solar Quote — due 9/20
33. Part Time Employees — Anna continues to work on list, interviewing housekeeper's week of 9/17
34. Heli Pad - reinstall windsock to north side of helipad
-JE & Larry for review lights and windsock location when next on site
35. Cisterns — need to be cleaned and sealed work to begin 11/1
EFTA01107305
ℹ️ Document Details
SHA-256
4c2035fd4a9180a226c9af75faea3a384c80b799959403734e14eacc9b20001a
Bates Number
EFTA01107304
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0