From: "Jean Huguen"
To: "Jeffrey E." <[email protected]>
Cc: Monet vilette'"
Subject: TR: 9 East 71st Street, NY - Cover letter, Revised Preliminary Budget R2 for Hammam, the
revised WO #2R1 & WO #3R I
Date: Wed, 01 Aug 2018 10:34:36 -0000
Attachments: 9_E_7 I st_Cover_2.pdf;
Preliminary_Budget_R2_for_Showeric_Steam_Room_at_9_East_71st_Street,_20 I 8.07.31.
pdf; WO_2_Rl_for Master_Bathroom_3-18_at_9_E_71st_Street,_2018.07.31.pdf;
WO_3_RI_ for_Painting_of Main_Staircase_walls_at_9_E_71st_Street,_2018.07.31.pdf
Dear Jeffrey
The 2 samples of carpets will be send to you at the end of August but the maker needs to have them back
Here is Plant estimate
They have included ,but it's a mistake,2 painters to help the artist who will do your bathroom's ceiling,as she will find
them herself
I am leaving tonight for holidays and will be back in 3 weeks
All furniture for the island will leave the first days of September
Thanks
De : Salavat Khusainov <[email protected]>
Envoye : mercredi 1 aoGt 2018 00:00
A:
Cc :'Jean Huguen' <1 .,; Randy Polumbo <[email protected]>; Jack Bales
<[email protected]>; Giselle Cashin <giselleO_plantnyc.net>
Objet : RE: 9 East 71st Street, NY - Cover letter, Revised Preliminary Budget R2 for Hammam, the revised WO #2R1 & WO
#3R1
Dear Lionel,
Please find attached the Cover letter, the revised Preliminary Budget R2 for Hammam and the revised WOs #2R1 & #3R1
that based on the site meeting at 07.12.2018 and your e-mails with the revised drawings, Plumbing fixtures cut sheets &
schedule that we have received after site meeting.
Please note:
• the Order of THG's plumbing fixtures is 10 — 12 weeks.
• the Order of Waterworks / Aero's Thermostatic Control valves is 14 - 16 weeks.
• the Order of Stone slab materials is 8 weeks.
• the Waterworks /Aero hard quotes for the some plumbing fittings from Europe are pending that indicated *A*
allowance.
The Preliminary Budget R2 for Hammam is indicated the last changes in R2 on the left margin.
The changes in the revised WOs #2R1 & #3R1 are in the bold text.
Please let us know if you have questions and confirm receipt of this e-mail with the attachments.
Best Regards,
EFTA01004385
Salavat Khusainov
Chief Estimator
Plant Construction LLC
181 Broadway, 5th Floor, NY, NY 10007
T: 212.693.6600 Ext.103
F: 212.693.6601
[email protected]
EFTA01004386
ℹ️ Document Details
SHA-256
4c5d15ccda3c4a3c4697415549c30bb06067674f942836c570650820ba2e4d3c
Bates Number
EFTA01004385
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0