From: Richard Kahn
To: "Jeffrey E." <[email protected]>
Subject: Update from Brandon on Library and Stairs at 71st
Date: Wed, 21 Jan 2015 18:58:09 +0000
Richard Kahn
HBRK Associates Inc.
Begin forwarded message:
Date: January 20, 2015 at 10:25:44 PM EST
From: Brandon Thomason <
To: Richard Kahn <
Subject: stairs
Dear Mr. Kahn,
Today, was a day of a lot of surprises. But first of all, I would like to update you about the work in the Library.
As you well know, I have contract with you to wax the Library. When we removed the Tapestries, I found the
wooden panels very, very dry. As a matter of fact, now that we moved the Italian Cabinet to the center of the
room, you can see the difference between already treated panels and newly exposed panels ( wall adjacent to
the street ) that are lacking wonderful vibrant color and life. They are very pale, due to dryness. What I actually
did is to change the method of the treatment, because the boards in the panels were so dry, they started to
"scale".
I decided to treat the wood with combination of oils, predominately, Linseed Oil, Lemon Oil, Danish Oil and
some additions. I saturated the surface with Oils and let it absorb for 4-6 hours. Result was stunning. The
panels became color rich and beautiful. Next we removed excess Oil and the surface became thy to touch. Next
we applied Renaissance Wax. We applied the Wax two or three times.
Have I applied the Wax only, the wooden panels would become pale after two-three days.
The Tops of two Cabinets on the North side of the Room, were scratched so badly, that I removed them to my
studio, so I could fill the scratches ( which went through the finish and removed the stain in the process ) and
re-polish the Tops.
The inner edges of the Doors were not stained and inner Door Frame as well. I air-brushed the color, so all is
uniform right now.
I did this and I never asked you for additional money on this all additional work.
I would like to do my very best for my customers. Since I moved to NY three years ago, I would like to
establish credibility and new client base.
As far as the Stairs are concern, the new thing that came out is the old carpet glue, which was hidden under the
rug under-layment. The glue is old and very hard. Instead of sanding it and eventually making dents in the
stairs, the best way to treat the Steps is to remove completely; glue and finish.
Even before you can start this work, you have to de-nail hundreds of nails, screws and staples. The under-
EFTA00866039
moldings are not immune to the damage. We may replace them. Please, come and see.
Brandon Thompson
EFTA00866040
ℹ️ Document Details
SHA-256
567f0b9eb2f9a428760d613dae10020ac8b8f04e978cf2154b24f650ff2aaadf
Bates Number
EFTA00866039
Dataset
DataSet-9
Type
document
Pages
2
💬 Comments 0