ZORRO DEVELOPMENT
1/21/14
Satellite:
Deposit paid to Advanced Comm — 1/17
Meeting with Advancced Comm 1/23 to confirm network map & scope of work.
References/Updated Proposal from SpaceNet & Jim Cloud forwarded to Rich — 1/20
Meeting today with RMC Electric to confirm poles for links to MH & RC
Pool Reulaster/SDa Clean: attached photos
Plaster work finished, acid wash & filling started today
Bead Blasting of Spa Tile, unsucessful, have requested estimate to replace tile & grout
will forward once in hand
Gate:
Project Complete as of 1/21
Sony:
Issues with Tablet not communicating with equipment. New Tablet has been ordered
incase it is a Tablet issue
IR to be extended closer to seating area.
Installer back on site 1/23 to resolve issues
Installation of moulding on hold until all issues are resolved
Dakota Well:
Rig was due on site today, delayed due to an emergency call out.
Now due 1/23
Cactus Removal: attached photos
Fabrication of railway tracks for drags complete.
Removal of cactus continues as weather allows
EFTA_R1_02003813
EFTA02684213
ℹ️ Document Details
SHA-256
574579c37b4fc054c2ef717ed217530a564a85581e5600d35412b1bc4f27622b
Bates Number
EFTA02684213
Dataset
DataSet-11
Document Type
document
Pages
1
Comments 0