Good morning Mr. Epstein the net work cable was completed by sawyers to all SCU controller
locations on 5-12-11. The contract with siemens was signed by Rich Kahn on 5-31-11. The
contract reads under project schedule engineering submittals material ordering, equipment
delivery ,installation,start up & commissioning will take two months from contract date for
completion which is 7-31-11. Equipment is on order and will be delivered to 71 st street,the
project engineer was at 71st on friday 6-17-11 to make a back up of the scu controller
information . He told me he would contact me when controllers are ready to ship to 9 east
7lst.Richard Barnett.
Date: Sun, 19 Jun 2011 07:44:05 -0400
Subject:
From: 'eevacation a ail.com
To:
siemans ? house uprgrade ? where arc we?
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
Jeffrey Epstein
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to k_c‘ [email protected], and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA_R1_00261333
EFTA01861074
ℹ️ Document Details
SHA-256
5e83d46da8e6197fe015f8517ffd725b383886f4bbf8b09378ffeb9367a97540
Bates Number
EFTA01861074
Dataset
DataSet-10
Document Type
document
Pages
1
Comments 0