LSJ CONSTRUCTION
Subcontractor Payout
Project: Flagpole Pool #1013 September 26, 2011
Trade: Pools
Requisition #6
Subcontractor Virgin Islands Gunite Pools
Insurance ex iration: Ma 14, 2012
nvoice # Requisition #6 Partial Final
Phase # 13-150 X
Original Contract Sum: $200,000.00
Change Orders Submitted & Approved: $25,213.44
New Change Orders: $0.00
Total Work Contracted to Date: $225,213.44
Total Work Completed to Date: 93% $210,471.25
Less Retainage: $0.00
Total Payments Made to Date: $170,471.25
Total Current Payment Due: $40,000.00
Balance to Finish including Retainage: $14,742.19
Sales Tax Liability:
a. Subcontractor/Supplier is liable, explaii Labor and materials
b. Non-resident Subcontractor/Supplier Bond Applicable:
c. Use Tax to be paid by our company:
d. Shipping incl.
Total Outlays for this contract incl. Sales or Use Tax: $210,471.25
,V)
JEE approval attached Invoice Attached
YES NO YES NO
X
Submitted Bill Approved by: Gary
Signed: Signed:
Date: September 26, 2011 Da : September 26, 2011
Approved by: Emad Approved/by:
Signed: Signed:
Date: Date:
EFTA01123619
LSJ CONSTRUCTION
Project Flagpole Pool #1013
:ontractor - full legal name: Virgin Islands Gunite Pools Date Revised: September 26, 2011
Phase # 13-150
Trade: Pools
Invoice #: Requisition #6
Insurance expiration: 5/14112 Payment
Partial Final
X
Invoice/Reg# Date C/O Amount Retainage Due Paid Date Paid Check# Balance
Contract 02/02/11 Pool 200.000.00
CON1 06/29/11 Change plaster 10.471.25
CO#2 09/06/11 upgrade board 9017.75
CO#3 09/06/11 Lighting 1460.44
CO*4 09/06/11 Cartridges 2.264.00
CO#5
Requisition #1 02/15/11 Deposit 40.000.00 0.00 40000.00 40000.00 0.00
Requisition #2 03/02/11 Steel Complete 40,000.00 0.00 40.000.00 40000.00 0.00
Requisition #3 03/22/11 Gunite Complete 40,000.00 0.00 4000000 40.00000 0.00
Requisition #4 06/10/11 Tile Complete 40.000.00 0.00 40.000.00 40.00000 000
Requisition #5 07/11/11 Change plaster 10.471.25 0.00 10,471.25 10.471.25 0.00
Requisition #6 09/06/11 Progress 40.000.00 0.00 40.000.00 40.000.00
Total 210.471.25 0.00 210,471.25 170471.25 40.000.00
Contract Amount - Phase
contract Pool 200.000.00
CO#1 Change plaster CO5 10.471 25
CO#2 upgrade board 9.017 75
CO#3 Lighting 3.460 44
CO#4 Cartridges 2.264 00
CO#5
Contracted To Date 225.213.44
Balance of Contract w/Retainage 14.742.19
EFTA01123620
„
Lake Havasu Gunite and Concrete/Virgin Island Gunite Pools
I r '
DATE
Invoice
INVOICE #
‘) 2t)I I 1011
TERMS DUE DATE
Net 30 10/06/201 1
BILL TO
AMOUNT DUE ENCLOSED
560,206.19
cle13O1 lop 'Nunn/. and whom %%ill. your payment chi- -wig
Activity Amount
• Final balance due upon start-up and use 40,000.00
• Change order #3 - Upgrade to 14 11. diving board 9,017.75
• Change order #8 - &-12V lights 3,460.44
• Addition • 6 LED pool lights, controllers, and transformers 5,461.00- '
• Addition - 16 new cartridges for clean and clear 520 sq. ft. filters 2,264.00
• Manifold bottom/pipe assembly - bulk head unions, O rings and labor to repair pool equipment caused by dead 0.00
heading equipment
Project: Flagpole Pool #1013 ri llenTfr owl
,
110000
-FSku Vir,q4 ‘ .
EFTA01123621
ℹ️ Document Details
SHA-256
5ed2b6908a27d58d2656168138c208f4c56bb86cdc4a0fe813e02dd92fcbf99b
Bates Number
EFTA01123619
Dataset
DataSet-9
Document Type
document
Pages
3
Comments 0