EFTA01857144.pdf
👁 1
💬 0
📄 Extracted Text (611 words)
To: Jeffrey epstein[jeevacation©gmail.com]
From: Gary Kerney
Sent: Wed 9/21/2011 8:19:47 PM
Subject: RE: RE:
This would be what I would expect a subcontractor to make and if he's good he'll work about 50% of the time all
in and the other 50% he will spend finding work and in between jobs.
their time starts and stops at the dock,we know what Marcos gets
Assume Tyson pays himself $50/hr.x45hr. $2250
lead stone mason Marcos gets $35/hr. x45hr. $1575
stone masons (2) @ 25 $50x45 82250
labor (2)@ 12 $24x45 $1080
From: Jeffrey epstein [[email protected]]
Sent: Wed 9/21/2011 3:42 PM
To: Gary Kerney
Subject: Re: RE:
You tell me if that looks like 1000 per week per person It seems so
Sorry for all the typos .Sent from my iPhonc
On Sep 21, 201 I, at 3:01 PM, "Gary Kerney" < > wrote:
tile layer $25,000 breakdown of my estimate
the terrace and pool deck will run just under $18,000 and take about 3 weeks ,crew
of Chris and 4 people. I allowed in the $25,000 some flexability to allow me to have Saint to do
the bath terrace, floors of the bath and cottage 4 in case our inhouse tile layers couldn't keep
up,which would also extend the time or add more people
Tyson $38,000 breakdown of my estimate
we got today a bill $10,908 for the past two weeks,leaving $27,000 bal.
I looked at the work to be done this morning and whats left is closer to $20,000 and at
least 3 weeks,and its Tyson and 5 workers
From: Jeffrey Epstein [mailto:[email protected]]
Sent: Wed 9/21/2011 7:31 AM
To: Gary Kerney
Subject: Re:
yes proceed.. , but explain how a tile layer with even 10 emplyces, full time on this , gets
EFTA_R1_00254743
EFTA01857144
12 thousand a week?
On Tue, Sep 20, 2011 at 4:57 PM, Gary Kerney ‹ >
wrote:
Jeffrey
over the next 30 days we have 3 subs listed below doing the work below on a cash basis.'
need your authorization to have them continue working and me give them local checks.
Rodney Rusphille did the collum wall and sea wall.
currently has a invoice in for $34,368.04 for the main terrace wall that needs a
check to pay his men and show back up.
I have him scheduled to do the balance of the motor court wall we laid out and
should start tomorrow.will be about $25,000 two draws and we're done with motor court
walls
Gassie Corner Stone ( Tyson) he is doing the stone veneer on cottage 4 and the little
bath,this was budgeted work that I explained the varience and the extra in my sept.l2th
email
he will bill another $38,000 in two or three draws over three weeks,and we're done
Saint Tile they did the flag pole coral deck.He is starting the big terrace tomorrow and then
the pool deck
$25,000 total ,he'll make two or three draws done in about three weeks
when you were here we talked about Brices cottage cabinets and their being over but other
line items being under and I was to proceed
Authorized for the above?
***********************************************************
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
EFTA_R1_00254744
EFTA01857145
Jeffrey Epstein
Unauthorized use, disclosure or copying of this
communication or any pan thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jeevacation@gmail,com, and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA_R1_00254745
EFTA01857146
ℹ️ Document Details
SHA-256
612846a5d0b94e60dfcf89b7d62169c3c8e9f6a38c4556dc84139475eb6625c8
Bates Number
EFTA01857144
Dataset
DataSet-10
Type
document
Pages
3
💬 Comments 0