To: Craig Marti
From: Jeffrey Epstein
Sent Thur 5/10/2012 10:44:58 PM
Subject: Re: Pricing on Engineering Building Pad
Im sorry„ did i get an answer to what bill brian and john have been doing.
On Thu, May 10, 2012 at 5:45 PM, Craig Martin wrote:
We had discussed trying to get the building permitted.
In the future if you want to erect the building we would need a stamped pad plan by govt.
We can skip that if you want.
Tom had said there are drafting services in STT that could draw a simple plan.
The labor figure is using Tom's construction crew, plus a few more workers that they need on
the days they pour cement. I will get Tom to give a breakdown.
Craig
From: Jeffrey Epstein <.eevacation marl com>
To: Craig Martin
Cc: Richard Kahn
Sent: Thursday, May 10, 2012 4:06 PM
Subject: Re: Pricing on Engineering Building Pad
what does site drawings mean . who is doing. this makes no sense, who is doing earthwork
and for how long. i want now to see details , rich follow up
On Thu, May 10, 2012 at 3:55 PM, Craig Martin wrote:
Here is the quote on the engineering building pad.
This is for the pad only. Please see exceptions below.
This pad is designed to hold a future building. Bolts for building, minor drainage is included.
If only a pad is needed without provisions for a building the price could be reduced slightly.
Craig
New Engineering Building Pad
Outside
Material Labor Shipping Trucking Tax
Vendor
Temp 200 200
EFTA_R1_00299183
EFTA01884424
Enclosure/safety
Material Handling 600
Equipment Rental 1500
Misc Expenses 1000 1000
Layout/Survey 200 800
Earthwork and Demo 2500 2000
Site Drawings 1000
Pest Control 2800
Site Dranage 1000 1000
Pipes/Utilities 500 2000
Concrete 9350 8000 2500
Vapor Barrier 200 200
Ties/Accessories/bolts1500 1000
Rebar 2400 1200
Saw Cutting 250 400
Curing/Protection 300 400
Fine Grade 1000
Wood/Formwork 1200 1400
Fastners 400
Sub Totals 18500 4300 22700 4500
Total 50000
Note; This is a basic pad
No Utilities, septic sysyem, electrical, wall, or engineering
yard work
The pad will have 3 gray water drains. The pad will not have sanitary
drains
Includes min work on electrical vault
EFTA_R1_00299164
EFTA01884425
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
Jeffrey Epstein
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by c-mail to [email protected], and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
***********************************************************
The information contained in this communication is
confidential, may be attorney-client privileged, may
EFTA_R1_00299165
EFTA01884426
constitute inside information, and is intended only for
the use of the addressee. It is the property of
Jeffrey Epstein
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to [email protected], and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA_R1_00299166
EFTA01884427
ℹ️ Document Details
SHA-256
616f0b8ff02b2672888f49b1ff1e31f0d9774a2fa38aab887faefa77d1d085ac
Bates Number
EFTA01884424
Dataset
DataSet-10
Type
document
Pages
4
💬 Comments 0