FIVE PALMS
PRELIMINARY SCHEDULE
II) a Task Name Duration Start Finish Predecessors I Ju [,ItAY
V 5122 1 929 6/5 6/12 6/19 6126 I 7/3 I 7/10 I 7/17
1 - Procurement 98 days Wed 841/11 Fri 10114/11 •
2 Design 23 days Wed 6/1/11 Fri 7/1/11
10 days Mon 7/4111 Fri 7/15/11 2 414 4
3 Budgeting - 0%
•
4 Approval 5 days Mon 7/18/11 Fri 7/22/11 3
5 Site lighting 60 days Mon 7/25/11 Fri 10/14/11 4
6 Coral tiles 40 days Mon 7/25/11 Fri 9/16/11 4
7 Roof trusses 30 days Mon 7/25/11 Fri 9/2/11 4
8 Roof tiles 30 days Mon 7/25/11 Fri 9/2/11 4
9 Exterior doors 25 days Mon 7/25/11 Fri 8/26/11 4
10 Finish hardware 20 days Mon 7/25/11 Fri 8/19/11 4
11 Hurricane shutters 25 days Mon 7/25/11 Fri 8/26/11 4
12 Sun shades 25 days Mon 7/25/11 Fri 8/26/11 4
13 A/C Systems 40 days Mon 7/25/11 Fri 9/16/11 4
14 Generator 60 days Mon 7/25/11 Fri 10/14/11 4
15 Electrical fixtures 60 days Mon 7/25/11 Fri 10/14/11 4
18
17 Sitework 83 days Mon 7/25/11 Wed 11118/11
18 Rough Site 3 days Mon 7/25/11 Wed 7/27/11 4
19 Underground utilities 2 days Thu 7/28/11 Fri 7/29/11 18
20 Install generator 3 days Mon 10/17/11 Wed 10/19/11 14
21 Site lighting 5 days Thu 11/10/11 Wed 11/16/11 24
22 Site concrete 10 days Mon 8/29/11 Fri 9/9/11 29
23 Stonework 20 days Mon 9/12/11 Fri 10/7/11 22
24 Finish grade 3 days Mon 1117/11 Wed 11/9/11 37
25 Landscaping 5 days Thu 11/10/11 Wed 11/16/11 24
26
27 Building 86 days Mon 811/11 Mon 11/28/11
28 Slab 5 days Mon 8/1/11 Fri 8/5/11 19
_ .
29 CMU 15 days Mon 8/8/11 Fri 8/26/1128
30 Roof truss system 5 days Mon 8/29/11 Fri 9/2/11 29
31 Roof dose in 20 days Wed 8/31/11 Tue 9/27/11 30FS-3 days
32 Gutter / Downspouts 3 days Mon 9/26/11 Wed 9/28/11 31FS-2 days
33 Set exterior doors 3 days Wed 9/28/11 Fri snotil 31
Critical Baseline Project Summary
Critical Split Baseline Split External Tasks
Project: Five Palms Prelim 01Jun11 Critical Progress Baseline Milestone External Milestone .
Date: Wed 6/1/11 Task Milestone • Deadline
Split Summary Progress ,
Task Progress Summary Iii .
Page 1
EFTA_R1_02030325
EFTA02690333
FIVE PALMS
PRELIMINARY SCHEDULE
ID
34
i© Task Name
Exterior stucco
Duration
15 days
Start
Mon 10/3/11
I Finish Predecessors
Frl 10/21/11 33
5/22 1
Julia
129 I 6/5 6112 6119
Woly
1 6/26 I 7/3 1 7/10 I 7117
35 Exterior painting 10 days Mon 10/17/11 Fri 10/28/11 34FS-5 days
36 Hurricane shutters 3 days Mon 10/31/11 Wed 11/2111 35
37 Sunshade 2 days Thu 11/3/11 Fri 11/4/11 36
38 Interior framing 5 days Wed 9/28/11 Tue 10/4/11 31
39 Interior plaster 20 days Wed 10/5/11 Tue 11/1/11 38
40 Flooring 5days Wed 11/2/11 Tue 11/8/11 39
41 Interior painting 5days Wed 11/9/11 Tue 11/1511140
42 NC Systems 30 days Wed 9/28/11 Tue 11/8/11 31
43 Electrical Rough 5 days Wed 10/5/11 Tue 10/11/11 38
44 Electrical Finish 3 days Wed 11/16/11 Fri 11/18/11 41
45 Punch List 3 days Mon 11/21/11 Wed 11/23/11 44
46 Clean up 2 days Thu 11/24/11 Fri 11/25/11 45
47 Inspection 1 day Mon 11/28/11 Mon 11/2811146
48 Completion 0 days Mon 11/28/11 lion 11128/1147
Critical Baseline Project Summary
Critical Split Baseline Split External Tasks
Project: Five Palms Prelim 01Junl 1 Critical Progress Baseline Milestone External Milestone
Date: Wed 6/1/11 Task Milestone • Deadline
Split Summary Progress
Task Progress Summary Iji .
Page 2
EFTA_R1_02030326
EFTA02690334
FIVE PALMS
PRELIMINARY SCHEDULE
August September October November I December
7/24 7131 8/7 8/14 8/21 8/28 9/4 9/11 9/18 1 9/25 102 10/9 10/16 10/23 1 10130 11/6 1 11/13 J 11f20 11/27 I 12/4
4 0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
4 0%
0%
0%
— 0%
0%
0%
4 0%
0%
0%
0%
► • ,0%
0%
Critical Baseline Project Summary
Critical Split Baseline Split External Tasks
Project: Five Palms Prelim 01Jun11 Critical Progress Baseline Milestone External Milestone
Date: Wed 6/1/11 Task Milestone • Deadline
Split Summary Progress
Task Progress Summary Iti m.
Page 3
EFTA_R1_02030327
EFTA02690335
FIVE PALMS
PRELIMINARY SCHEDULE
August September October November I December
- 7 2/111 7/31 8/7 1 8114 1 821 1 8/28 9/4 9/11 9118 1 9/25 10/2 10/9 10116 I 10/23 j 10/30 11/6 I 11113 J 11f20 11/27 I 12/4 I
0%
0%
0%
0%
0%
0%
‘11/28
Critical Baseline Project Summary
Critical Split Baseline Split External Tasks
Project: Frie Palms Prelim 01Junl 1 Critical Progress Baseline Milestone External Milestone
Date: Wed 6/1111 Task Milestone • Deadline
Split Summary Progress
Task Progress Summary Iji .
Page 4
EFTA_R1_02030328
EFTA02690336
ℹ️ Document Details
SHA-256
627c9292906f7c3a9e344dfc88b67f3bc00a0275cf72fe60cd692464a5df390e
Bates Number
EFTA02690333
Dataset
DataSet-11
Document Type
document
Pages
4