📄 Extracted Text (1,148 words)
Master Suite Expansion
Preliminary Budget LSJ Performed Work
May 18, 2009 Subcontractor performed work
Total costs
Phase Description Qty Unit Price Shipping Sub Material Labor Totals
General Conditions $42,300.00
01-514 Phones 6 mos $300.00 $0.00 LSJ $1,800.00
01-522 Temporary Enclosures 1 tot $2,000.00 $0.00 LSJ $2,000.00
01-610 Material Handling 20 wks $600.00 $0.00 LSJ $12,000.00
01-621 Temporary Protection 1 tot $3,000.00 $0.00 LSJ $3,000.00
01-624 Construction Cleaning 20 wks $300.00 $0.00 LSJ $6,000.00
01-645 Expendables 5 mos $1,500.00 $0.00 LSJ $7,500.00
01-665 Equipment Rental 4 mos $1,000.00 $0.00 LSJ $4,000.00
01-900 General Requirements- Labor I tot $3,000.00 50.00 LSJ $3,000.00
01-900 General Requirements-Mat. I tot $3,000.00 $0.00 LSJ $3,000.00
Inspections/Testing $15,000.00
02-000 Krauss Manning - Subcontractor $15,000.00 SUB $15.000.00
02-000 Rebar inspections 10 SUB
02-000 Concrete placement inspections 10 SUB
02-000 Concrete test cylinders 50 SUB
02-000 Close in inspections 2 SUB
02-000 Electrical inspections 2 SUB
02-000 Plumbing inspections 1 SUB
SUB
Survey $3,500.00
02-005 SUB Mosley I total $3,500.00 50.00 SUB $3.500.00
Demolition $23,070.00
Remove / Dispose outdoor
02-070 bathing area 16 hrs $25.00 LSJ $400.00
02-070 Excavate for slab & foundation 20 hrs $25.00 $520.00
Remove / DisposeSouth wall at
02.070 extg. Indoor bathing area 40 hrs $15.00 LSJ $600.00
Remove / Dispose roof at extg.
02.070 indoor bathing area 80 hrs $20.00 LSJ $1,600.00
Remove / Dispose extg. roof
02-070 structure at new structure area 80 hrs $20.00 LSJ $1,600.00
02-070 Cap existing utilities 8 hrs $20.00 LSJ $160.00
02-070 Remove all plumbing fixtures 8 hrs $15.00 LSJ $120.00
Remove / Dispose existing
02.070 interior partitions 80 hrs $15.00 LSJ $1,200.00
Remove / Dispose all exterior
02.070 doors, windows and shutters . 16 hrs $15.00 LSJ $240.00
02.070 floor tile 80 hrs $15.00 LSJ $1,200.00
Remove / Dispose existing
02-070 wood flooring 40 hrs $15.00 LSJ $600.00
Remove / Dispose existing
02-070 terrace rails and posts 2 hrs $15.00 LSJ $30.00
Remove / Dispose existing
02.070 terrace columns 200 hrs $15.00 LSJ $3,000.00
02.070
Remove / Dispose existing
02.070 elevated terrace beam 200 hrs $15.00 LSJ $3,000.00
Remove dumster debris from
02-071 island 11 ea $800.00 $&800.00
EFTA00602026
Phase Description Qty Unit Price Shipping Sub Material Labor Totals
Shoring $10,000.00
Shore extg. roof at Dressing/Master
01-150 Bath & remove LSJ $1,440.00
Shore extg. roof at Master BRM SW
01-150 Corner & remove LSJ $480.00
01-150 Shore terrace roof & remove LSJ $2,080.00
01-150 Estimated materials LSJ $6,000.00
Pest Control $2,260.001
02-281 Pest control 2260 sft S1.00 $0.00 SUB $2.260.00
Concrete $56,146.00
03-120 Complete cast in place concrete 1 $32,000.00 $0.00 LSJ $32,000.00
03-130 4000# concrete 50 cyd $150.00 $0.00 LSJ $7,500.00
03-173 Slab on Grade - Labor 756 sft $3.50 $0.00 LSJ $2,646.00
03-301 Admixtures 50 cyd $20.00 50.00 LSJ $1,000.00
03-350 Cementitious Coatings 2000 sft $2.00 50.00 LSJ $4,000.00
03-362 Concrete Pumping 1 tot $9,000.00 $0.00 SUB $9.000.00
Masonry $32,310.00
04-220 CMU Labor 1782 ea $2.00 $0.00 LSJ $3,564.00
04-221 CMU material 1782 ea $3.00 5346
04-450 Native Stone Veneer labor 900 ft $22.00 $0.00 LSJ $19,800.00
04.451 Native stone material labor 900 ft S4.00 $3,600.00
Metals $11,070.00
05-050 Metal Fastening 1 tot $5,000.00 $0.00 LSJ 2500 $2,500.00
05-500 Lintels - Labor 16 hrs $20.00 $0.00 LSJ $320.00
05-500 Lintels - Material 1 tot $5,000.00 $750.00 LSJ $5,750.00
Wood $158,000.00
06-050 Fasteners - Material 1 tot $3,000.00 $500.00 LSJ $3,500.00
06-100 Rough Carpentry - Labor 1 tot $25,000.00 $0.00 LSJ $25,000.00
06-100 Rough Carpentry - Materials 1 tot $30,000.00 $3,000.00 LSJ $33,000.00
06-130 Heavy Timber Framing 1 tot $20,000.00 $4,000.00 LSJ $24,000.00
06-200 Finish Carpentry - Labor 1 tot S15.000.00 $0.00 SUB $15.000.00
06-202 Finish Carpentry - Materials 1 tot $7,500.00 $0.00 LSJ $7,500.00
06-400 Architectural Woodwork 1 sub S50,000.00 $0.00 SUB $50.000.00
Moisture / Thermal $115,112.00
07-212 Rigid Insulation - Labor 896 sft $0.75 50.00 LSJ $672.00
07-212 Rigid Insulation - Material 896 sft $2.50 $400.00 LSJ $2,640.00
07-240 EIFS Cornice/Gutter 224 Ift $50.00 $0.00 SUB $11.200.00
07-413 Metal Roofing - Labor 3200 sft S6.00 $0.00 SUB $19.200.00
07-412 Metal Roofing - Mat. 3200 sft $12.00 $3,000.00 LSJ $41,400.00
07.623 Copper Flashings - Labor 1 tot S12.000.00 $0.00 SUB $12.000.00
07.623 Copper Flashings - Material 1 tot $20,000.00 $1,000.00 LSJ $21,000.00
07.632 Downspout Rough - L&M 1 tot $4,000.00 $0.00 LSJ 2000 $2,000.00
07-900 Joint Sealants - L&M 1 tot $3,000.00 $0.00 LSJ 2000 $1,000.00
Doors and Windows $166,080.00
08-210 Wood Doors/Frames/Shutters - La 8 ea $350.00 $0.00 LSJ $2,800.00
08-210 Wood Doors/Frames/Shutters - M; 8 ea $10,000.00 $2,000.00 LSJ $82,000.00
08-215 GlassSliding doors / role down
shutters 2 ea $350.00 $700.00
GlassSliding doors / role down
08-215
shutters 2 ea $8,000.00 $1,500.00 $17,500.00
08-211 Int. Doors & Frames - Mat. 3 ea $5,000.00 $0.00 LSJ $15,000.00
08.211 Int. Doors & Frames - labor 3 ea $350.00 $0.00 LSJ $1,050.00
08-370 Glass Shower Enclosures 1 allow S15,000.00 $0.00 SUB $15,000.00
08-610 Windows/Shutters - Labor 1 ea $350.00 $0.00 LSJ $350.00
EFTA00602027
Phase Description City Unit Price Shipping Sub Material Labor Totals
I
08-610 Windows/Shutters - Material 1 tot $2,500.00 $750.00 LSJ $3,250.00
08-710 Finish Hardware - Labor 40 hrs $25.00 $0.00 LSJ $1,000.00
08-710 Finish Hardware - Material 1 total $25,000.00 $0.00 LSJ $25,000.00
08-810 Mirror Glass - L&M 54 sft $45.00 $0.00 SUB $2.430.00
Finishes $146,795.00
09-120 Ceiling Support - Flat 1 tot $13,000.00 $2.000.00 LSJ $15,000.00
09-200 Plaster 900 sft $10.00 50.00 LSJ $9,000.00
09-300 Wall Stone Tile - Labor 1600 sft $5.00 $0.00 SUB $8.000.00
09-300 Wall Stone Tile - Material 1600 sft $5.00 $2,200.00 LSJ $10,200.00
09-300 Stone Stone tile Flooring - Labor 1172 sft $5.00 $0.00 LSJ $5.860.00
09-300 Stone stone tile Flooring Material 1172 sft $5.00 $1,800.00 LSJ $7,660.00
09-500 Wood Ceilings 1 tot $35,000.00 $4,000.00 SUB $39.000.00
09-560 Wood Flooring 488 sft $25.00 $500.00 SUB $12.700.00
Granite Countertops/ tub
09-600
slabs/steam room 75 sft $225.00 $0.00 SUB $16.875.00
I
09-910 Exterior Painting
09-920 Interior Painting
1
I
tot
tot
$5,000.00 $0.00
$0.00
LSJ
LSJ 7500
$5,000.00
$10,000.00
Specialties $9,330.00
10-800 Toilet Accessories - Mat. 1 tot $8,500.00 $350.00 LSJ $8,850.00
10-800 Toilet Accessories - Labor 24 hrs $20.00 $0.00 LSJ $480.00
Steam Room Equipment $19.200.00
13-130 Steam Room Equipment 1 total $18,000.00 $1,200.00 LSJ $19,200.00
Plumbing $23,500.00
15-400 - Supply, waste piping, rough in $12,000.00 SUB $12.000.00
15-450 - Fixtures allowance $10,000.00 1500 LSJ $11,500.00
HVAC $87,600.00
Remove and relocate exisitng AC
15-800 condensing units - $2,600.00 SUB $2.600.00
15-800 Installing all new system similar to the Office Pavilion $85.000.00
Electrical $75,000.00
16-000 Electrical Complete 1 sub $35,000.00 $0.00 SUB $35.000.00
16-500 Fixtures I allow $35,000.00 50.00 LSJ $35,000.00
16-700 Communications I allow $5,000.00 50.00 LSJ $5,000.00
Sub Total $996.273.00 $380,425.00 $412.456.00 $203.392.00 6996.273.00
Contingency, 5% $49,813.65 $19,021.25 $20.622.80 $10.169.60 $49.813.65
Total 61.046.086.65 5399,446.25 5433.078.80 6213.561.60 61.046.086.65
Landscaping not included
Furnishings not included
General Conditions does not Include costs for Supervisors, Project Managers or Project Assistants, as
per Previous Office Pavillion & Mechanical Budgets
EFTA00602028
ℹ️ Document Details
SHA-256
6681a4b0e16dcc33551881372ed799f2d08b1e5ef0ee58da3c6f4c774fe904f8
Bates Number
EFTA00602026
Dataset
DataSet-9
Document Type
document
Pages
3
Comments 0