To: Jeffrey EpsteingeevacationGigmail.comj
From: Richard Kahn
Sent Wed 10/23/2013 9:29:46 PM
Subject Jimmy
I spoke with Jimmy who was does not want to come back to LSJE unless paid in full which totals
22,636.
Original Estimate 14,994
Three additional days @ 2194 per day 6,582
Trucker paid by Jimmy 1.060
Total Due Jimmy before additional 18" 22,636
He would not budge on his position with Ma or Daphne. I reminded him that his original fee of
14,994 included acting as Construction Manager for entire job which is not complete.
He agreed to come back to LSJE if we released 18,000.
He will need two days to complete 18" (1 day of framing and next day to pour)
That additional cost will be 2,194 per clay ifjimmy is part of crew or 1,300 per day ifjimmy does
not come with his crew.
Please advise if ok to pay jimmy 18,000.
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor,
New York, New York 10022
EFTA_R1_00415406
EFTA01949890
ℹ️ Document Details
SHA-256
672097450001396f1b26d9408921df9f803842292de3b65a284a734f802350fe
Bates Number
EFTA01949890
Dataset
DataSet-10
Document Type
document
Pages
1
Comments 0