From: Richard Kahn
Sent: Tuesday, March 12, 2019 8:00 PM
To: Jeffrey Epstein
Subject: Steel building
not =hat i am aware of..
problem is that if i do not push =veryone daily nothing gets done..
unfortunately =ately i have been busy with banks, brokerages and hedge =unds..
last =mails to glidden below..
Richard Kahn
HBRK Associates Inc.
575 =exington Avenue 4th Floor
New York, NY 10022
tel
fax
cel
On Mar 12, 2019, at 3:57 PM,1 <[email protected]> wrote:
Did we order the building steel
=nbsp;
Begin =orwarded message:
From: Richard Kahn c=
Subject: Fwd: 40x60 bldg.
Date: March 7, 2019 at 4:15:25 PM EST
To: michael glidden <
EFTA_R1_01851381
EFTA02631147
Cc: Daphne Wallace , Stephanie Remington
i =m not sure if you responded and i apologize if you did and i missed =t..
could you please update on status and next steps as =ee would like ordered asap
thank you
Richard Kahn
HBRK =ssociates Inc.
575 Lexington Avenue 4th =loor
New York NY 10022
tel
fax
cell
Begin =orwarded message:
From: Richard Kahn <[email protected]>
Subject: Fwd: 40x60 bldg.
Date: February 22, 2019 at 3:25:25 PM EST
To: michael glidden
Cc: Daphne Wallace Stephanie Remington
can you please review and reply ASAP
thanks
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue 4th Floor
New York, =Y 10022
tel
fax
cell
2
EFTA_R1_01851382
EFTA02631148
Begin forwarded message:
From: Brian Buck
Subject: RE: 40x60 bldg.
Date: February 21, 2019 at 1:30:57 PM EST
To: michael glidden
Cc: Daphne Wallace , Richard Kahn
Stephanie Remington
Michael,
I =ant to put together a drawing for you but I need to clarify a couple of =hings first.
• So the =uilding was not erected according to plans, it was modified somewhat in =he
field? The building was a fully sheeted building. So the =rector opened up the left end wall to 8'2" and the back =ide
wall to 10'6" but was sheeted 5'6" =ast the roof of the 14" slab. How deep is the retaining =all?
• Are the (2) 12' x 14' =oors on the marked up dwg you sent back (front side wall and right
end =all) to be included in these locations? Are we adding a third =ollup door in bay #3 of the front side wall where you
currently have a =5' rough opening?
Assuming the above is correct this is =hat I would propose.
We previously had the left end wall as = flush girt condition. I would change it to a bypass girt so
that =he girt would extend 10"(depth of girt) past the face of the =olumn. This way a) the panel would lap over the
retaining wall(if it is =0" or less deep) for a good seal and b) would allow us to shift =he columns in 10". This will clear
the existing anchor =olts which will be cut off and providing the pier is sufficient in =idth, would save a whole lot of time
and labor on those (4) left end =all columns.
I'd leave the back side wall =pen to 10'6", sheet above the roof and provide a wall =o roof
flashing. I'm assuming the slab is all even =levation?
I think if we change the bay spacings =lightly(less than a foot in most cases) we can avoid having
to do a lot =f the demolition.
What do you think?
Regards,
Brian Buck
President
Direct
Toll Free
3
EFTA_R1_01851383
EFTA02631149
Web www.bucksteel.com <http://www.bucksteel.com/> Follow us on social media!
6855 Lyons Technology Circle I =uite 18 I Coconut Creek FL 33073
1107 Battlewood Street I Suite 221 Franklin TN 37069
Legal Disclaimer: =his communication and any attachments contain information which is =onfidential and may also be
privileged. It is for the exclusive use of =he intended recipient(s). If you are not the intended recipient(s) =lease note that
any form of disclosure, distribution, copying or use of =his communication or the information in it or in any attachments
is =trictly prohibited and may be unlawful. Where the content of this email =s personal or otherwise unconnected with
the firm's or its clients' =usiness, Buck Steel accepts no responsibility or liability for such =ontent. E-mail communications
cannot be guaranteed to be secure or =rror free, as information could be intercepted, corrupted, amended, =ost,
destroyed, arrive late or incomplete, or contain viruses. We do =ot accept liability for any such matters or their
=onsequences.
From: michael =lidden
Sent: Wednesday, February 20, 2019 4:56 PM
To: Brian Buck
Cc: Daphne Wallace ; Richard Kahn
Stephanie Remington <
Su ject: Fw : 40x60 g.
Good =fternoon Brian.
I thought that this might help =nderstanding how the building was installed. The only openings
are as =arked up.
I will gather the information =omorrow that we discussed .
Begin forwarded message:
From: michael glidden
Subject: 40x60 bldg.
Date: February 20, 2019 at =:47:48 PM AST
To: [email protected]
Sent from my =Phone
=/div>
4
EFTA_R1_01851384
EFTA02631150
5
EFTA_R1_01851385
EFTA02631151
ℹ️ Document Details