Jeffrey,
The Bell 430 annual will not be completed until Mid next week,. April 10th estimate.
we are waiting on back order parts from Bell:
-Main wheel assembly.
-tail rotor drive shaft seal,
completing upgrade to Main rotor hydraulic actuators,.minor corrosion will be addressed on passenger window
frame require paint work, area of 6 inches for touch up paint. Over all the helicopter was very clean during this
first BELL factory annual.
thx,
Larry