From: Ann Rodriquez
To: "jeffrey E." <[email protected]>
Cc: Rich Kahn , Daphne Wallace
Subject: Fwd: Big N
Date: Fri, 10 Jul 2015 14:48:53 +0000
Attachments: LSJ_Est_776.pdf
Inline-Images: tank.jpg; tank_2.jpg
Ann R.
Begin forwarded message:
From: gene kcal
Date: July 10, 2015 at 10:26:59 AM AST
To: Ann Rodriquez
Cc: Debra Lowry
Subject: Big N
Reply-To: gene kral cS>
Good Morning Anna-
I wanted to give you and update on the progress of the Big N. This morning we were ready to lift and install the port
engine. Bosco has informed us that the port engine is not ready, he has a few more things he needs to address. I
know you were looking into replacing the gear boxes but have had no success in finding new ones that are similar. I
am writing this email so we are all on the same page as far as a completion date. The majority of our work hinges
on having those engines installed. The exhaust system on each engine has to be finished, but in order for us to
complete this we have to have the engines in. The same goes for the new fuel lines and all the electrical
components that run to the engines. I know we discussed the end of this month/beginning of next month but each
day that we wait for the engines to be completed it delays us from our target date. A few issues have been
discovered while working on Big N. 1) The shaft logs on both sides are corroded beyond repair. We anticipated that
we might have this problem so it was factored into the quotation. 2) The port stern quarter looks like it might have
hit a dock which has separated some of the stringers on the inside. It is repairable and I told you we would repair it
under the quotation. 3) The fuel fill cover on both sides are compromised and need to be replaced. They are not
sealing properly and over the course of time have allowed salt water to seep in and contaminate the fuel tanks.
Which leads me to your biggest issue we have discovered while working in the rudder room where the fuel tanks
are located. The bottoms of the fuel tanks and several other areas are severely corroded. It is my recommendation
that these tanks be replaced. The only way for a proper repair are to replace both tanks. The original tanks got you
40 years so I don't see why the new ones we fabricate cant get the same amount of usage out of them. Attached
our a couple of pictures of the corrosion and an estimate to remove and replace both tanks. Please call or email
with any questions...
Gene Kral Sr.
EFTA01199322
EFTA01199323
EFTA01199324
ℹ️ Document Details
SHA-256
737680494615cbf58722b4fe73725667a978231d0b2ddd391b0e18f377772dfe
Bates Number
EFTA01199322
Dataset
DataSet-9
Document Type
document
Pages
3
Comments 0