From: Richard Kahn
Sent: Tuesday, August 25, 2015 8:53 PM
To: jeffrey E.
Cc: Leighton Allenby; Merwin Dela Cruz
Subject: Luton Job at 71st Street along with pictures
i just spoke with Al from Clarity regarding the Lutron =roject and he told me the following:
Monday they opened up the 1st and 2nd =loor panels - They were forced to open both at once since they are both =ed
by the same circuit breaker The 4th floor panel =as not yet been touched and is fully operational along with the 3rd
=loor There will not be any lighting all week other =han temporary construction lighting (see photos below) which is
=flowing them to perform their work Unfortunately =hey cannot stop job as panels are already open and do not
anticipate =ny functionality until Friday afternoon At that =oint in time there will be moderate functionality of the 1st
and 2nd =loors with 3rd and 4th floors remaining fully operational
Richard Kahn
HBRK Associates Inc.
575 Lexington =venue 4th Floor
New York, NY 10022
On Aug 23, 2015, at 9:53 AM, =effrey E. <[email protected] <mailto:[email protected]> wrote:
yes
On Sat, Aug 22, 2015 at 4:47 PM, =ichard Kahn wrote:
Please advise it is ok for Lutron job to =esume Monday. Thank you.
Sent from =y iPhone
Begin forwarded =essage:
From: Al Buonanno
Date: August 21, 2015 at 3:00:11 PM EDT
To: Richard Kahn
EFTA_R1_01312405
EFTA02343881
Cc: Merwin Dela Cruz Leighton Allenby C.
Subject: RE: Luton Job
Hello Richard and =erwin,
I trust that everything is on schedule for us to begin =ismantling the system this coming Monday
morning. Please advise =s if there are any issues with us beginning then. Please note =hat lights will be out in most of
the residence. We will have =emporary lighting set up to allow us to work but certainly not enough =o cover the entire
home.
ON a similar note and am hopeful that Mr. =pstien was okay with our "work in progress"
appearance and that our =resence wasn't a great inconvenience.
Regards,
Al
Original =essage
From: Richard Kahn
Sent: Tuesday, August 18, 2015 11:11 =M
To: Al Buonanno
Cc: Merwin Dela Cruz 4 ; Leighton Allenby
Subject: Luton Job
I just spoke with mr =pstein and he said he will be returning wednesday evening or thursday =m
he would like the 1st and 2nd floor protection to be removed as of =ow job will resume monday august 24th sorry for
any additional work and =roubles this may cause
regarding glass mr epstein thinks we may =ave extra in the house - merwin please speak with
jojo as he may know =ocation of glass if we do have extra thank you
Richard Kahn
HBRK Associates Inc.
575 =exington Avenue 4th Floor
New =ork, NY 10022
Begin forwarded message:
From: =/b>"
Subject: =/b>Construction =ights
Date: =/b>August 25, 2015 at 4:47:32 PM =DT
2
EFTA_R1_01312406
EFTA02343882
To: =Th>Richard Kahn
These are the lights Al is talking about
First floor panel. Wires taken out from the breaker and ready =o be pulled out of the wall
Second floor: Here is the new panel
Merwin =ela Cruz
3
EFTA_R1_01312407
EFTA02343883
ℹ️ Document Details
SHA-256
7917a0bc200934ee0783e71ad1b0c71332b003c741bd9259a16ab9ee5a84b525
Bates Number
EFTA02343881
Dataset
DataSet-11
Document Type
document
Pages
3
Comments 0