EFTA01071350.pdf

DataSet-9 6 pages 1,157 words document
👁 1 💬 0
📄 Extracted Text (1,157 words)
61011 MAIN HOUSE POOL ID Task Name Duration Start Finish Predecessors May 4/10 I 4117 I 4/24 5/1 I 5/8 I 5/15 j 5.22 1 Procurement 60 days Mon 4/18/11 Frl 7/8/11 ifirrivrivintrivintrivrinivrivintrivintrivritrivrivintrivinivrivinivrivintrivinivrivinivrivintrivivrivirifirmanmannmannm 2 Site design 30 days Mon 4/18/11 Fri 5/27/11 Lielgil...... ... ' ... ... 3 Pool file 32 days Mon 411811 Tue 5/31/11 4 Site drains 40 days Mon elm 1 Fri 610111 Cr--- ._ 5 Coral tie 30 days Mon 412vi 1 Fri 5/27/1 6 Site lighting 40 days Mon 4,1/311 Fri 6/10/11 7 Rebar 15 days Mon 4,18,11 Fri 5/6/11 100% 8 CMU 5 days Mon 41611 Fri 4/22/11 9 Doors/Frames/Shutters 60 days Mon 41811 Fri 718111 c-:-..... .. ........ . ..............................................................................". 10 Interior doors 60 days Mon 4x1811 Fri 7/8111 ..... 11 Punish hardware 60 days: Mon 41811 Fri 703/11 12 Root framing 45 days Mon 41811 Fri 6.117/ 1 13 Roofing assembly 40 days Mon 41811 Fri 610111 .., 14 Copper gutters 20 days Mon 41811 Fri 513'11 woo. Cr 15 Shower enclosure 50 days Mon 41811 Fri 6124111 ...- 16 Coral flooring 30 days Mon 418/1 Fri 5/27/11 r 17 Vanity / Tops 45 days Mon 418/1 Fri 6/17/11: 18 Plumbing fixtures 45 days Mon 41811 Fri 6/17111 19 NC Systems 45 days Mon 4,1811 Fri 6/17111 20 Electrical fixtures 45 days Mon 4/18111 Fri 617111 ar ---""" 21 22 23 Sltework 105 days Mon 4/18/11 Fri 919111 giblIIIIIIIIIIIIIIIIIIIMMIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIMIII“ ,. 24 Underground utilities 15 days Mon 4/18/11 Fri 5611 100% 25 Pool tile 12 days Wed 6/1/11 Thu 01611 3 26 Diamond Wile 12 days Fri 6/17/11 Mon 7,411 25 27 Complete pool 0 days Mon 7/4/11 Mon 7/411:26 28 Drainage 10 days Mon 6/13/11 Fri 6124/114 29 Pool deck 20 days Mon 6/27/11 Fri 7/22/1128 30 Coral tie 20 days Mon 7/11/11 Fri 8/5/11 29F5-10 days 31 Stone walls 30 days Mon 7/11/11 Fri 8/19/11 29F5-10 days 32 Finish grade 5 days Mon 822/11 Fri 8/26/11 31 33 Landscaping 5 days Mon 8,29111 Fri 912!1132 34 Site lighting 10 days Mon 8 29111 Fri 9/9/1132 35 36 37 Cottage 64 147 days Mon 4/18/11 Tue11/8/11 ret, 'in...in...L....L , 38 Basement walls 15 days Mon 4118111 Fri 5/6/11 r::: ..... . ..... --------zI—tert % 39 Elevated slab 10 days Mon 519111 Fri 5/20/11 38 , - . ....... , 40 Waterproofing 2 days Mon WW11 Tue 5/10/1138 w 100% Critical Baseline 1 Project Summary ir; Critical Split Baseline Split ..,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,„, External Tasks Project: 1011 Updalel5Jull 1 Critical Progress Baseline Milestone O External Milestone G Date: Mon 7/18/11 Task Milestone . Deadline .2. Split Summary Progress unnuninuninnumussm Task Progress r i Summary Ur Page 1 EFTA01071350 #1011 MAIN HOUSE POOL ID Task Name Duration Sled Finish Predecessors May 4/10 I 4117 I 4124 5/1 I 5/8 I 5(15 I 5/22 41 Foundation drain 2 days Mon SIM Tue 5/10/1138 Tolson-10096 42 Cottage 114 backfil 3 days Wed 5,11111 Fri5/13/1141 a 0 100% 43 CMU 30 days Mon &Ell Fri 7/15/11 39FS+10 days 44 Root framing 10 days Mon 711)1.11 Fri 7/29/11 43 45 Root assembly 20 days Mon &1,'11 Fri 8/26/1144 46 Copper gutters 5 days Mon 8,22,'11 Fn a2a€1145FS-5 days 47 Downspouts 2 days Mon 8,29,11 Tue 8/30/1145 48 Stone veneer 30 days Mon 8,15111 Fri 9/23/11/45FS-10 days 49 Set door frames 3 days Mon &29/11 Wed &31/1145 50 Interior framing 5 days Mon 8,29(11 x.45 51 Interior plaster 15 days Mon 9.,5111 Fri 923/11 50 52 Interior doors 5 days Mon 9.,5,11 Fri 979/1150 53 Bathroom tile 5 days Mon 926,11 Fri 9/30/1151 54 Shower enclosure 1 clay Mon 10,311 Mon 10/3/1153 55 Vanity / Tops 2 clays Mon 10.311 Tue 10!4/1153 56 Accessories 2 clays Tue 104'11 Wed 10/5/11 54 57 Interior painting 5 clays Mon 9,26,11 Fri 9/30/1151 58 Flooring 5 clays Mon 10.2111 Fri 10/7/1157 59 Plumbing Rough 5 clays_ Mon 925111 Fri 919/1150 60 Plumbing Finish 5 days Wed 10/5/11 Tue 10/11/1155 61 NC Systems 30 days Mon 9/5/11 Fri 10/14/11 50 62 Electrical Rough 5 days Mon 9/5/11 Fri 9/9/11 50 63 Electrical Finish 5 days Mon 10/10/11 Fri 10/14/11 58 64 Decorative Painting 10 clays Mon 10/17/11 Fri 10/28/1163 65 Punch List 3 clays Mon 10/31/11 Wed 11/211164 66 Clean up 2 clays Thu 11/3/11 Fri 11/4/11 65 67 Inspection 1 day M01111/7/11 Mon 11/7/1166 68 Furnishings 1 day Tue 11/8111 Tue 1118/1167 69 Completion 0 clays Tue 11/8111 Tue 11/8/11 68 Critical - Baseline Project Summary Critical Split Baseline Split Project: 1011 Update15Jul11 Critical Progress Baseline Milestone 0 External Milestone G Date: Mon 7/18/11 Task Milestone . Deadline Split Summary Progress unnuninuninnuniullum Task Progress Summary V Page 2 EFTA01071351 61011 MAIN HOUSE POOL June I July I August 5122 I 5323 I 615 I 6/12 I 6119 I 6326 7/3 I 7/10 I 7/17 I 7/24 I 7/31 I 817 I 814 100% mm ,Izam,...„„mum 100% ....I l00% •••••.-tee low, -I fix% .......a............... """"... • -, 100% " 7:t = 100% z 100% 100% 100% -- --------- 4 100% . 100". Lua 100% —.du 100% :::zra 100% c. 1+100% c. +100k . 7/4 1' in% i 25% *r _ i 1Oo% Critical Baseline Project Summary ..- NT? Critical Split Baseline Split ..,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,„, External Tasks Project: 1011 Update15Jul11 Critical Progress 1 Baseline Milestone O External Milestone G Date: Mon 7/18/11 Task Milestone Deadline • Split Summary Progress nautamaammuumuum Task Progress Summary • • Page 3 EFTA01071352 #1011 MAIN HOUSE POOL I June I Jul) I Arms( 5/22 I 5329 I 6/5 I 6/12 I 6119 I 6/26 7/3 I 7/10 I 7117 I 7/24 I 7/31 I 87 I al4 Critical Baseline Project Summary I•1 Critical Split Baseline Split ..„„„„,„„„,„„„„,„„„„, External Tasks Project: 1011 Update15Jul11 Critical Progress Baseline Milestone O External Milestone G Date: Mon 7/18/11 Task Milestone . Deadline Split Summary Progress ummumumuumumnuo Task Progress Summary Page 4 EFTA01071353 01011 MAIN HOUSE POOL I September I October I November 8121 I 8,28 I 9/0 I 9/11 I 9/18 I 9/25 I 10/2 I 10/9 I 10/16 I loin I urao I 11:6 I 11!13 . 53% 0% 25:o Critical Baseline Project Summary V G Critical Split Baseline Split Project: 1011 Updale15Jul11 Critical Progress Baseline Milestone O External Milestone G Date: Mon 7/18/11 Task Milestone • Deadline Split Summary Progress rummunmummumnum Task Progress Summary • Page 5 EFTA01071354 #1011 MAIN HOUSE POOL I September I October I November 8/21 I 8/28 I 9/4 I 9/11 I 9118 I 9/25 I 10/2 I 10/9 I 10/16 I 10/23 I 10/30 I 1116 I 1L13 ' )0% 0% *at 0% w 0% 0% v , 0% 0% 0% 0% 0% 7 0% * .-934 14=t ook • "a11/8 Critical L Baseline Project Summary 7 . 7- G - Critical Split Baseline Split Project: 1011 Update15Jul11 Critical Progress Baseline Milestone O External Milestone G Date: Mon 7/18111 Task il o Milestone • Deadline Split Summary Progress tunnunnumunnumunto Task Progress Summary .i . Page 6 EFTA01071355
ℹ️ Document Details
SHA-256
79290dd0903acdc826234860b2049b8eecccb525ff52fb80dd026ec070767f96
Bates Number
EFTA01071350
Dataset
DataSet-9
Type
document
Pages
6

Community Rating

Sign in to rate this document

📋 What Is This?

Loading…
Sign in to add a description

💬 Comments 0

Sign in to join the discussion
Loading comments…
Link copied!