From: Richard Kahn
To: Jeffrey Epstein <[email protected]>
Subject: Fwd:
Date: Tue, 23 May 2017 11:17:39 +0000
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue, 4th Floor
New York NY 10022
tel
fax
cell
Begin forwarded message:
From: Amy Dempsey
Subject: Re:
Date: May 23, 2017 at 6:50:19 AM EDT
To: Richard Kahn <
Cc: Hugo Hodge <
We are presenting at the Interagency Meeting on the 2Ist of June and submitting the next day. I have finishing up the EAR now. I still
need the final stuff from Hugo, but I take it that you got him the generator information so he can finish those things up. We are actually
out today and tomorrow finishing the surveys for the new layout...
Amy Claire Dempsey, M.A.
President, Bioimpact, Inc.
P.O. Box 132 Kingshill
Vi Islan s 00851
On Mon, May 22, 2017 at 6:26 PM, Richard Kahn < > wrote:
any updates on moving this forward
please advise
thank you
Richard Kahn
HBRK Associates Inc.
575 Lexington Avenue 4th Floor
New York, NY 10022
EFTA00696517
to
fax
cell
On May 16, 2017, at 7:49 AM, Amy Dempsey > wrote:
Sorry I was with the COE from 2pm on and will be again today, we are doing site visits (but not on the boat so no GSJ).
Amy Claire Dempsey, M.A.
President, Bioimpact, Inc.
P.O. Box 132 Kingshill
St. Croix J.S. Vi 'n Islands 00851
ax
On Mon, May 15, 2017 at 6:50 PM, Hugo Hodge > wrote:
Good evening All,
While we wait for everyone to confirm availability for the call, I have received some specs for the
generators. On the first glance, I believe it can work but it will require some re-designing. The 2
generators will have to work in parallel and it will require a redesign of the switchgear on both islands.
Additionally some other equipment, like step up transformers, will be needed for the new scheme to
work.
This work is outside of the agreed upon scope and I will need to send you a proposal to do this design.
This makes it a good thing that we didn't order the switchgear. I will also need to submit the new design
to WAPA for approval.
HH
On Mon, May 15, 2017 at 7:19 AM, Hugo Hodge <1 > wrote:
Good morning All,
Amy is correct. I requested additional information about the generator to determine if there will be
issues with it being the backup for both islands.
Additionally, we have not ordered any of the switchgear, cable, etc. for the project.
HH
On Sun, May 14, 2017 at 3:17 PM, Amy Dempsey <1 > wrote:
I think we are quickly wrapping everything up, there were some things Hugo needed in relationship to the existing generator
and its ability to carry both islands etc„ but finally have the landings set which allows me to finalize all my pieces. and get
the sections finished for the EAR.
Amy Claire Dempsey, M.A.
President, Bioimpact, Inc.
EFTA00696518
P.O. Box 132 Kingshill
Vi 'n Islands 00851
Fax
On Sun, May 14, 2017 at 3:04 PM, jeffrey E. <[email protected]> wrote:
are we set?
please note
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
JEE
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to [email protected], and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA00696519
ℹ️ Document Details
SHA-256
8334adb256d4b59d3d5ac0e796d9cb839aada1e08a7d05b45975fe92240248bb
Bates Number
EFTA00696517
Dataset
DataSet-9
Type
document
Pages
3
💬 Comments 0