From: Stephanie Remington
To: J <'eevacation4 mail.com>, Richard Kahn < , Daphne Wallace
, michael glidden , Patrick Cena
Subject: Progress Report_032519_033119
Date: Fri, 29 Mar 2019 19:36:24 +0000
Please note:
This is a summary of the last week's focus, not a comprehension of all projects.
Carpentry. Continue work on lattice frames for tiki. Assisted with added tiki tile. Tile work complete.
Building new doors for FPP. Weatherproofing roof connection between tiki kitchen and main tiki on
LSJ. Loaded F450 with all GSJ kitchen cabinets and appliances from tunnel storage and transferred to
GSJ container.
Electrical/Plumbing. Install new lights in FPP kitchen. Replaced lights and bulbs in library. Installed
new water pump at FPP cabana for bathroom and kitchen. Added landscape lighting up to LSJ
Cabana drive. Assisted with emptying and moving containers and relocating contents.
Engineering. Fluid check — all equipment. Commissioned new lull. Tropical run for hitch, installed on
new tractor. Inaugural water wagon run w JD tractor to GSJ and went well. Installed hammer (again)
on Cat 325. Clean carmix. New tires, change electrical cable on bikes. Polaris work. Worked on
Polaris, Quadski, Dump Truck. Change batteries on roller compactor. Clean F450. Clean tire changing
room. Put tracks back on 307 cat. Clean wreck shop and vehicle storage area.
Heavy Equipment. Transitioned and set containers from LSJ to GSJ. Trenching for Liston at LSJ
tower. Made more stone at pebble beach for Dupson. Clear out entire footprint of "The Barn" on GSJ.
Assisted with landscaping on GSJ beach area (grass, seagrapes, ficus). Cleaned Blue Beach.
Ongoing seaweed battle.
Housekeeping. Usual rounds. Laborers brought in to move heavy items in storage areas and clean
underground spaces.
Landscaping/Masonry. Received and caring for large ABC shipment that looks mostly dead but they
will work their magic. Pebble beach is ongoing. Completed forming 5 Palms bunker. Will be poured
Monday morning, weather permitting.
Marine. Maintenance on trailers — tongues, tires, hubs, stands, wheel bearings,carpeting, derusting.
Replaced steering cylinder on Little C. New props on Little C. Haulout and pressure wash Sportis and
Zodiac. Nanna maintenance, oil change, fuel filters.
Painters. Continued painting hardware around main compound. Began fresh coat of paint in Cabanas.
RO/Maintenance. Oversee cistern cleaning and sealing. Acquired pump for FPP kitchen/bath.
Standard pool and RO maintenance.
Contractors on island:
Absolute Flooring — work complete.
Jeffers — Coloring shipping next week.
EFTA01034720
Danny — Continuing work on MC Flower Bed.
Kitchen Solvers - Countertops scheduled for install May 3-6.
Paul's Petroleum — added check valve to gasoline pump to eliminate delay.
Other Notes:
Rust remediation. Attaching photo file.
Master cistern. Cleaned. First round of thoroseal complete. Will repeat thoroseal in one week.
5 Palms Power. Trenching to begin Tuesday.
Rubbish. All trash bins on GSJ emptied.
Proposal for storm Shutters for RO, Generator, GSJ staff cottage, LSJ staff cottage — submitted to
Rich and was approved.
All interior and exterior doors for RO, generator buildings ordered.
40X60 replacement building for engineering has been ordered.
Construction drawings for GSJ staff cottage have been submitted.
Next week's focus will be putting cabanas 1-4, the flagpole pool, chillax room and bath, and library
back together after floors have adequately cured.
Stephanie Remington
LSJE, LLC
EFTA01034721
ℹ️ Document Details
SHA-256
85bdc4c2ddb33a73a65168e198b1fe1f5621e87cf050c3e0db6283c5a13657c0
Bates Number
EFTA01034720
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0