From: Jermaine Rua
Sent: Tuesday, September 2, 2014 9:07 PM
To: Jeffrey Epstein
Subject: Tower Project Status
Good day =oss,
As per our conversation, here is the proposed schedule =or completion of the tower project :
* ./span>lf the second payment ($ 90,019.85 ) is =pproved and received this week the order can be made 9/8/14.
From =here:
o 3 Weeks for balance =f the equipment to arrive
o 1 Week to complete =SJ installation
o 1 Week to complete =TC installation
o 2 Weeks to finalize =11 sites including programming and active swaps for =ackup.
=o:p>
Does Terrence have permission =o work on adjusting the tower to the height of the berm this week =tarting tomorrow
9/3, while you are in residence?
Regards
JRuan
1