From: Emad Hanna <
Sent: Friday, February 4, 2011 5:21 PM
To: Jeffrey Epstein
Cc: Rich Kahn
Subject: LSJ Mechanical Building Wire Request
Attachments: 02-04-11 Abbott & Lineham Mechanical Req4.pdf
Jeffrey,
The attached is a request of $ 31,265.93 (will hold =ntil your review of work on LSJ)
The set budget line total on the Plumbing and fire protection is $ 304,892 and this contract is for a total of $ 287,100
=hich we have paid $ 227,841.82 leaving after the current request is processed $ 27,992.25 left on the contract.
Thank you
<=p>
Emad Hanna
Project Controller
HBRK Associates
301 East 66th St
Suite 10F
New York, NY 10065
Cell
LSJ Office
St. Thomas Office
NY Office
Fax
1
EFTA_R1_02012201
EFTA02686497
2
EFTA_R1_02012202
EFTA02686498
ℹ️ Document Details
SHA-256
8ef9899d81624f9691442d906f134202e0337aa2787b03c82be3af549489c1c2
Bates Number
EFTA02686497
Dataset
DataSet-11
Document Type
document
Pages
2
Comments 0