To: Richard Kahn
From: Jeffrey Epstein
Sent Tue 7/17/2012 6:56:53 PM
Subject: Re: Zorro Ranch Revised
ok
On Tue, Jul 17, 2012 at 2:47 PM, Richard Kahn wrote:
I just spoke with the owner Bill Whaley who was reluctant to discount his pricing any further
than the $1,600 offered in this email.
I was able to persuade him to agree to a total discount of $6,000 which represents a 4.85%
discount from original quote. Accordingly their price to drill would be $117,221
They will be ready to start next week around July 25th + or - a day
Please note that this quote is priced for the full 800 feet of drilling
If we only drill 700 feet then the cost will be reduced by approximately $6,300
Other costs involved with drilling other than HGS $117,221 are as follows:
a) Casey Cook - consultant to oversee job and file reports - approximately $12,500 (billing rate
of $150 per hour)
-costs already incurred and paid in 2012 with identifying well, meeting with Brice and filing
permits, etc. amount to $9,000
b) RMC Electric - approximately $17,500 per Brice (i will forward his quote and negotiate with
him as well)
Estimated total drilling costs with gross receipts tax: $165,974
(this number includes $9,000 costs already incurred and New Mexico gross receipts tax rate of
6.625% - darren is looking into why gross receipts is applicable)
Please advise
PLEASE NOTE EFFECTIVE JUNE 5TH MY CONTACT INFO WILL BE AS
FOLLOWS:
Richard Kahn
HBRK Associates Inc.
EFTA_R1_00283967
EFTA01875410
Begin forwarded message:
From: Casey Cook <a
Date: July 17, 2012 10:17:42 AM EDT
To: Richard Kahn a>
Cc: brice gordon
Subject: Fwd: Zorro Ranch Revised
Richard K.;
Hydrogeologic Services sent the attached revised draft contract with a price adjustment on the 8-inch
screen. The price is reduced from $28/foot to $24/foot from the original bid, which reduces
the total well cost by $1600. The other unit costs are the same as in the original bid. Please
note that the estimated cost of the pump may change depending on the tested well capacity,
which may be more or less than the 100 gpm planned for estimating purposes. A larger
pump will cost more, a smaller pump less. Also, the drilled and constructed depth may be
less than the planned 800 feet depending on determination in the field of the final depth. I
understand HGS will invoice Cypress, Inc for the actual footage drilled and cased on the basis
of the proposed unit prices.
Hydrogeologic Services indicates they are available to mobilize to the Ranch next week to begin drilling.
I recommend Cypress. Inc. award the contract to Hydrogeologic Services for drilling the 8-inch well at
Zorro Ranch because of their lower bid price and earlier availability than the other responsive
bidder (Yellow Jacket Drilling), and for their previous experience drilling a similar well into the
target formation at the Ranch.
Please call with any questions you may have, or if you wish to discuss this in further detail.
Casey W. Cook, P.E.
Belleau Groundwater, Inc.
Forwarded message
From: Esperanza Cordova
Date: Mon, Jul 16, 2012 at 4:53 PM
Subject: Zorro Ranch Revised
To: "Casey W. Cook"
EFTA_R1_00283968
EFTA01875411
Thanks.
Esperanza D. Meis
Office Administrator
HydroGeologic Services, Inc.
The information contained in this communication is
confidential, may be attorney-client privileged, may
constitute inside information, and is intended only for
the use of the addressee. It is the property of
Jeffrey Epstein
Unauthorized use, disclosure or copying of this
communication or any part thereof is strictly prohibited
and may be unlawful. If you have received this
communication in error, please notify us immediately by
return e-mail or by e-mail to jecvacation@gmail,com, and
destroy this communication and all copies thereof,
including all attachments. copyright -all rights reserved
EFTA_R1_00283969
EFTA01875412
ℹ️ Document Details
SHA-256
959a487cc2a77de6b9714967f0284e94e8cac922f735ad794e4db5e4f85cc955
Bates Number
EFTA01875410
Dataset
DataSet-10
Document Type
document
Pages
3
Comments 0