LSJ CONSTRUCTION
Subcontractor Payout
Project: Mechanical Desal February 3, 2011
Trade: Water System
Requisition #05
Subcontractor TSG Technologies, Inc
Insurance expiration: March 1. 2011
Invoice # Requisition #05 Partial Final
Phase # 11-200 X
Original Contract Sum: $592.160.00
Change Orders Submitted & Approved: $6.905.00
New Change Orders: $0.00
Total Work Contracted to Date: $599,065.00
Total Work Completed to Date: 95% $569,457.00
Less Retainage: $0.00 /
Total Payments Made to Date: $533,944.001/
Total Current Payment Due: $35,513.00 OF
I
Balance to Finish including Retainage: $29,608.00
Sales Tax Liability:
install only / tax
a. Subcontractor/Supplier is liable. explaii
included in contract
b. Non-resident Subcontractor/Supplier Bond Applicable:
c. Use Tax to be paid by our company.
d. Shipping None
Total Outlays for this contract incl. Sales or Use Tax: $569,457 00
JEE approval attached Invoice Attached
YES NO YES NO
X <
Submitted Bill Approved by: Gary
Signed: j iff__ Signed:
Date: February 3. 2011 Date: February 3. 2011
Approved by: Emad Approved by:
Signed. Signed:
Date ) 1 1-1 (I Date:
I
EFTA_R1_02014084
EFTA02687177
LSJ CONSTRUCTION
Project Methanicat Desat
hiboonlractor • full legal name - SG l'ecnnolLiniet lik Data Revised r ate,
Phase M 1.2t!1
Trade Wale, System
Invoice d Region:Ion 405
enereeee 'Natation, '. Mail' Payment
Partial Final
X
InvoicefReqe Dale Cf0 Amount Releinattle Due Pod Date Paid Chacke Balance I
Contract Amount I 2i22.C9 1..IC. I00 00
COitt 10.1I; t a Watch Guard System 1.000 00
COS2 tOt 131IJ Slotar / Insurance 1.000 00
COs3 01.08111 Lost lime 4 905 00
C044
CON.5
Requisition PI 02/2210 Dottie') Phase • 8% 47.800 00 1100 47,800 00 47.800 %QV 000
Requisition a2 03e3w iti Procurement. 42% 248.280 00 C. (X) 24828000 248 280 Otiv , C, 000
Reqtrsition a3 08515+10 Ready to Snip 30% 171.548 0C 0 00 177,648 00 177.548 CUV 0.00
Requisition 44 tztat.ii 0 Equip on Ste - 10% 50.216 00 000 60.21800 60 215 On 0 01
Requisition 05 02/03/11 Substantial Cumpetion • .5% 20.604 00 U 00 2940600 29.808 00
02/03/11 CO's NZ 13 5.90500 000 5.905.00 590500
Requisition 46 Final COMPlObOn • 5%
Total 569,45700 000 569.457.00 533.944.00 _ 35.51300
C011eaCI AriltatiN • PeaSe
1:
Contract 0 Plant 592.160.00
Co., escn Guard i .000 00 Desorption
Co.? Swage i Insurance 1.00000 Div:mono
Lost limo 4.505 00 Description
C004 Oesonpuon
C015 Descupoon
Contracted To Date
Natant:* Cr Contract uaRetainatge L
599.065.00,1
29.608 00
EFTA_R1_02014085
EFTA02687178
:11: S IG
Wi r jrliK artagitibleWee- .;
Name I Me St James. LID 1Invoice Number 40-204-02-PRIM
Uo 4inancol Trust Company. Inc Dale 2/3/7011
Address 6100 Red Hook Ouaner B-3 Order No.
City St Thomas TSG Called Bob Petoisen
Slate USVI Zip 00802 Michael Maio
Phone (340) 779-8054 Phone (340) 778-7766
All:, Gary Kerney Fax (340)774-9489
7tavywantmt . .44. .Z. 7ralliffliititi . Wit Prb0 Eit04550r9040
1 Pay Request 45 529608 00
t Change Order 112 51.00000
I Change Order 1/3 54.905 00
Payment Schedule:
a Task Percentage Payment
I Design Phase- NIP -t 8% 54/.80000
2 Begin Procurement - NTP 2 42% 5248.780 00
3 Ready to Ship 30% 5177648.00
Charge Order al 51.000.00
1 kquipment on Site 10% 559.21600
Cnartge Order rt2 51900 00
Change Order 43 54.905 40
5 Substanbal Completion 5% 529.608 00
6 Final Completion 5% 529.608 00
Total 100% 5599.065.00
Total per Contract 5599.065.00
Less Previously Invoiced: 5533.944.00
Total this Invoice: 535.513 00
Remaining Contract Value $29.608.00
Subtotal 635.513 00
Shipping and Handling
Taxes $0.00
Total invoice amount 535.513.00
Wire information.
TSG Technologies. Inc
Darby Bank and Trust
Routing number 061211168
Account number 133442
EFTA_R1_02014086
EFTA02687179
task TSG
MAXIK I VIRY DROP COulil
TO: DATE: October 13, 2010
FROM: TSG Technologies
CONTRACTOR CHANGE ORDER REQUEST
PROJECT NAME: Little St. James RO
PROJECT NUMBER:
ORIGINAL CONTRACT SUM $ 592.160 00
(Contract Dated - February 11. 2010)
PREVIOUSLY APPROVED CHANGE ORDERS $ 1 000 00
(Total Number of Approved Change Orders- 1)
REQUESTED CHANGE ORDER NO. 2 S 1 000 00
TOTAL $ 594 160 00
Description of Request (include time. schedule. authorizing associate)
Item1: Storage/insurance for RO equipment through December 2010 $1.000
TSG TECHNOLOGIES L.S.J., LLC
IbtLL-464L
Page 1 of
EFTA_R1_02014087
EFTA02687180
••••••
TSG
MAKING (WRY DROP COW
TO • K rn DATE January 18. 2011
FROM- TSG Tecbnolo ies
CONTRACTOR CHANGE ORDER REQUEST
PROJECT NAME. Little St. James RO
PROJECT NUMBER: 40.204.02
ORIGINAL CONTRACT SUM. $ 592 160,00
(Contract Dated - February 11. 2010)
PREVIOUSLY APPROVED CHANGE ORDERS $ 2 000 00
(Total Number of Approved Change Orders- 2)
REQUESTED CHANGE ORDER NO. 3 $ 4 905 00
TOTAL $ 599.065.00
Description of Request /include time, schedule, authorizing associate)
Item 1: Time lost due to power nol being available to TSG staff as of 1/19/11. Newest information
conveyed to TSG has power available at end of day 1/21/11. for a loss of 3 days.
Installers: 2 people x 9 hrs/day x $50/hr x 3 days $2.700
Project Manager: 1 person x 9 hrs/day x $65/hr x 3 days $1,755
Per Diem: 3 people x $50/day x 3 days $450
If work cannot be completed by 1/28/11. TSG's original finish date, then extra charges will be incurred for
housing and change ticket fees.
TSG TECHNOLOGIES LLC
Page 1 of I
EFTA_R1_02014086
EFTA02687181
Emad Hanna
From: Monique Har
Sent: Friday, February 04, 2011 10:42 AM
To: Emad Hanna
Subject: TSG
Attachments: TSG Req 5.pdf
Emad,
Attached for payment TSG Technologies, Inc Req 5 in the amount of $35,513.00. Project 1010 Code 11-200.
Monique
EFTA_R1_02014089
EFTA02687182
ℹ️ Document Details
SHA-256
96520d5959e2c2581d7b7243efcca896c82912e3fc8ce6f6866e38bb9166f9a4
Bates Number
EFTA02687177
Dataset
DataSet-11
Document Type
document
Pages
6
Comments 0