landscaping (22) - Start End Total Est. Cost
Rear Planter Bed Notes Photo
6/1/13 $75,000.00 3/28/13 - Refurbishment & Maintenance
Front & Rear Parking Beds proposals from 3
companies forwarded to RK & DI
Bowel Garden
4/27/13 -JE approved Aspen Landscaping for Refurbishm
Aspen Grove ent
5/9/13 - New proposal forwarded to JE & RK, awaiting
Pinion Screen direction
5/16/13 - Final proposal forwarded to RK, will discuss with
JE
5/24/13 - Aspen agreed to $75,000
5/31/13 - $44,383.08 Deposit issued to Aspen
6/1/13 - Project Started X
6/8/13 - Work continues, soil preparation in progress
6/14/13 - Plant material starting to arrive, more due next
week
6/18/13 - More plant material arrived
6/21/13 - Planting & Irrigation complete at back parkin
g area.
6/22/13 - Planting & Irrigation continues around chess
set -
attached photos
Landscape Lighting Timers Replacement - Start End Total Est. Cost Notes Photo
$5,000.00 4/27/13 - JE approved
5/1/13 - Unable to move forward until Project 22 -
Landscaping
f has been resolved
6/1/13 - Brice to review with Aspen about location etc.
6/7/13 - Awaiting electrical proposal from RMC Electric
due
6/24/13
Landscaping - In House - Start Total Est. Cost Notes
Ponderosa Pines & Landscape Lights at 6/3/13 Photo
4/27/13 - JE approved the removal of dead pine in courtyard
Front Entrance &
Ponderosa Pines, Landscape Lights & relocate Pinions to
the area.
6/3/13 - Project Started
6/7/13 - Removal of Ponderosa Pines complete
6/18/13 - Removal of courtyard Pine complete
6/25/13 - Work to begin on landscape lighting
EFTA01124648
Zorro Projects - 6/22/13
Terraces (27) - Three B's Start End Total Est. Cost Notes
Terraces - 552,000.00 4/7/13 Photo
$56,200.00 12/12/12 - Bid Received
Stucco/Gutters/Painting - $4,200.00
3/20/13 - JE approved
4/7/13 - Project Started
4/20/13 - Library Membrane - installed.
5/16/13 - MBR Balustrade reinstalled
5/20/13 - MBR Membrane to be installed
5/31/13 - There was a fault in one of the rolls of mater
has reordered, will recover area once on site.
ial, vendor x
6/7/13 - Material on site, will continue 6/10/13
6/14/13 - Membranes & Gutters Complete - attached photo
s
6/18/13 - Stucco & Painting scheduled to start
6/21/13 - Stucco & Painting Complete - attached photo
s
6/24/13 - Final review of completed work
Front Gates Openers Call Boxes (30) - Start End Total Est. Cost Notes .Photo
4/20/13 - Bid received, requested vendor to make adjust
ments
5/9/13 - Received revised bid. Options & Equipment review
ed
5/12/13 - Options & Equipment selected, final bid due
5/21/13
5/21/13 - Final bid received via fax, unable to read, vendo
r will
resend.
6/8/13 - Final bid attached, also forwarded separately
to RK.
6/11/13 - RK requested material breakdown
6/14/13 - Material breakdown forwarded to RK
6/19/13 - Resubmitted revised pricing to RK - awaiting
direction
Cooling Tower (36) - JBH Start End Total Est. Cost Notes Photo
4/24/13 - RK approved bid from SPX & JBH. RK has all cost
details
5/3/13 - Deposit was to be forwarded, awaiting confirmatio
n
6/20/13 - Unit on site - attached photo
6/21/13 - Noting attached E Mail, JBH have pulled their
team off
moving forward with this project until RK makes conta
ct about
outstanding balance
EFTA01124649
Zorro Projects - 6/22/13
Replacement of Pool Pac (33) - Start End Total Est. Cost Notes
Engineering Inspection - $9,100.00 9/11/12 .Photo
_
4/29/13 - Quote forwarded to RK, who requested more
Unit Cost - $43,170.00 detail
5/8/13 - Revised quote forwarded to RK, awaiting direct
Camera Ducting Inspection - $1,214.91 ion
5/22/13 - Beaudin Ganze on site to review project
Ducting - TBA
5/29/13 - Beaudin Ganze report forwarded to JE & RK
5/29/13 - JE approved investigation via camera.
6/3/13 - JBH forwarded estimate
6/4/13 -JE approved moving ahead
6/11/13 -JBH due on site
6/12/13 - JBH on site, completed camera inspection, awaiti
ng
report/disc.
6/21/13 - Report/Disc forwarded to Beaudin Ganze, awaiti
ng
review
. .
Repair Pool/Spa (29) - Start End Total Est. Cost Notes Photo
$12,600.00 5/9/13 - Vendor on site
5/16/13 - Bid breakdown forwarded to RK
JE requested work be completed in Sept
Water Sample of Tap Water - Start
, End Total Est. Cost Notes
6/12/13 Photo
4/27/13 - JE requested water samples be taken.
This will be completed once water system is balanced
5/10/13 - Dakota RO is down, pressure issues
6/2/13 - All Wells up and running
6/12/13 - Water samples taken. Results due back 6/24/1
3
. .
Exterior Doors Main House - Three B's Start End Total Est. Cost Notes Photo
4/27/13 - JE requested that all saddles on exterior doors
be
adjusted so doors will close correctly. Will be completed once
Terraces etc. complete
EFTA01124650
Zorro Projects - 6/22/13
Audio Upgrade - In House Start End Total Est. Cost Notes
New TV's 6/3/13 Photo
Installed - final programming required
DVD Players/Theater Upgrade
Installed - Programming of remotes required
5/14/13 - Awaiting replacement receiver for Gym before
moving
forward
5/24/13 - Receiver on site
6/3/13 - Work to begin
6/7/13 - Work 80% complete in Gym, Breakfast Rm,
Lodge & BH
6/12/13 - Gym, Lodge & BH Systems Complete
6/14/13 - Will exchange the Samsung DVD for a Maran
tz DVD in
Breakfast Rm
6/22/13 - Awaiting delivery of Marantz DVD
Kitchen Table Electrical - (35) -Three B's Start End Total Est. Cost Notes
Electrical & Data Cut In - $2,160.00 6/3/13 6/13/13 Photo
3/1/13 - Bid received Lead lime 1 Week
6/3/13 - Project Started
6/7/13 - Under floor conduit due to be completed 6/12/1
3
6/13/13 - Conduit installed, tiles replaced & grouted. Cat
5 still to
be pulled and punched down
Media Room Curtains (24) - Start End Total Est. Cost Notes
Blackout & Rings 2/24/13 Photo
$6,262.08 4/27/13 - JE selected fabric
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
Sarah's Office Curtains (25) - Start End Total Est. Cost Notes
Lined & Rings 2/24/13 Photo
I $2,527.01 4/27/13 - JE selected fabric
5/2/13 - Vendors/manufacturer cannot provide enoug
h yardage
of selected fabric
5/9/13 - Another fabric option forwarded to JE
5/10/13 - Project Request forwarded to JE & RK
5/17/13 - Resent Project Request to JE
5/31/13 - AWAITING DIRECTION
EFTA01124651
Zorro Projects - 6/22/13
Gym - Mirrored Doors - Three B;s Start End Total Est. Cost Notes
2/24/13', Photo
3/4/13 - Project Complete. JE requested further work,
which will
begin once Project 27 - Terraces complete
Phones Main House (31) - Start 1
End Total Est. Cost Notes Photo
4/27/13 - JE approved installation of new phones at
MH
Awaiting for service provision & estimated cost of
delivery of
services - Project 21Microwave & IT
6/22/13 - Awaiting response from Southwestern Wirele
ss on FCC
License Application & Router at MH
Phones Ranch Central (351- Start End Total Est. Cost Notes Photo
6/21/13 - Will forward proposal for phone system by 6/28/1
3
MIcrowaveALT - (21) - Start End Total En. Cost Notes Photo
4/27/13 - JE requested to investigate Microwave option
5/9/13 - Existing Microwave details forwarded to JE,
RK & JR,
awaiting direction
5/16/13 - JE requested contacting Dava Baumann refere
nce
delivery of service from Sandia Crest verses D Mark
5/17/13 - Dava Baumannhas forwarded details of
RSM Craig
Franck. Brice has been in contact with Craig will forward
details
5/24/13 - Received bid from Southwestern Wireless, have
call set
up for 5/28/13 to review bid
5/31/13 - Brice forwarded an update of Project to JE, RK
& JR
6/8/13 - Forwarded TW Telecom Proposal for Delivery
of Services
to JE & RK. Firm Bids due by 6/14/13
6/14/13 - Received bid from Southwestern Wireless, confir
ming
details before forwarding
6/15/13 - Informed JE, will forward once all details
confirmed
6/20/13 - JE approved South Western Wireless bid. RK
to
negotiate final bid
EFTA01124652
Zorro Projects - 6/22/13
Cell Repeaters & Wi-Fi - In House Start End Total Est. Cost Notes
Cell Repeater - Library _ Photo
Will have installed 6/28/13
Cell Repeater - Gym
Will have installed 6/28/13
Computers - _ Start End Total Est. Cost Notes
Lap Top - Lodge Photo
Requesting Approval to Purchase
Desk Top - RC Office
Requesting Approval to Purchase
Well K (37) - Start End Total Est. Cost Notes
Plugging First Hole Photo
$15,000.00 Estimate to plug 1st hole
Lod e Roof Start _ 4 Total Est. Cost Notes
Repair/Replace Broken Sections Photo
Three B's will complete while on site for upcoming projec
ts
Yurt - (23) - Start End Total En. Cost Notes
Replacement Walls/Roof/Door/Windows 5/9/13 Photo
$6,355.00 4/27/13 -JE approved investigating options
plus shipping 5/9/13 - Project Request forwarded to RK
& JE
charges of 5/9/13 - JE approved Project, awaiting direct
ion on deposit
approx. payment from RK
$480.00 5/13/13 - Deposit forwarded to vendor $3,177.50
6/24/13 - Removal of furniture, deconstruction of existing
walls/roof/windows & door to begin. Then reconstruction
of base,
resanding/sealing floor required - in house
7/3/13 - Scheduled Ship Date
Repair/Painting Work -Ion Start End Total Est. Cost Notes Photo
5/7/13 - E Mailed Photos to JE showing work required
5/23/13 - Forwarded all work details to Ion, including work
that
will be required after MBR Terrace is completed
EFTA01124653
Zorro Projects - 6/22/13
Painting/Staining/Sealing - In House (
Start End Total Est. Cost
Stables - including outside/Inside lights Notes Photo
6/27/13 - - Work to begin
Adobe - Including wooden deck & front
Work to begin once stables complete
Log Cabin
Work to begin once all painting/staining projects complete at
RC
Lodge
Work to begin once all painting/staining projects complete
at RC
Reservoir
Work be begin once all painting/staining/sealing projects
complete
Fuel Storage Tanks
Work to begin once all painting/staining/sealing projects
complete
RC Office Interior
Work scheduled for Winter
RC Mechanical Bays - Interiors
Work scheduled for Winter
RC Garages - interiors
Work scheduled for Winter
Fuel Storage Tank Area - In House Start End Total Est. Cost Notes
Removal of grass. Matting & edging to be Photo
installed
Gravel/Edge Work RC Paths -In House Start End Total Est. Cost Notes
All paths to be dug out, edged and gravel Photo
to be installed
Log Cabin - In House Start End Total Est. Cost Notes
Step Outside - Repair/Replace Broken Photo
Section
Caboose - In House Start End Total Est. Cost Notes
Installation of Retaining Wall Photo
EFTA01124654
Zorro Projects - 6/22/13
4 Bay Garages - In House Start End Total Est. Cost Notes
Repair Leaking Roof
Repair Damaged Wall
Pole Barn Water Truck Parking Start End Total Est. Cost Notes
Installation of a Retaining Wall Photo
To begin late Fall, Early winter
Cactus Removal - In House Start End Total Est. Cost Notes Ph
oto
Removal of Cactus to begin late Fall, early Winter
Vehicles Start End Total Est. Cost
2013 Ford Expedition - review Captain Notes Photo
3/27/13 5/2/13 - Estimate received - $11,528.74
Seats to be installed
5/31/13 - as of date unable to get a 2nd estimate,
ft E Start End Total Est. Cost Notes Photo
4/27/13 -JE approved investigating purchase of 2 dogs.
Researching
Inventory/Clean Work Shops - In House Start End Total Est. Cost Notes
6/6/13 Photo
6/20/13 - Landscaping, Paint & Wash Bay 90% complete
-
attached photos. All these location will be painted over the winte
r
6/21/13 - Work continues as time allows - complete dean up
&
inventory of all work shops at RC & MH
Purchases Start End Total Est. Cost
Big Ums - Outside MH Notes Photo
4/27/13 - JE approved Terre Cotto constructed Urns
Outside Pool Furniture
Investigating Options
Pool Pace Clock
4/25/13 - Ordered, lead time 4 to 5 weeks. Trying to track
large Chrome Pool Clock this down
Investigating Options
Facial Machine
o purchase
Wells - Dakota & K
Combined Usage as of date 6/14/13
6.86 afa
EFTA01124655
Zorro Projects - 6/22/13
2014 Budget
Bunkhouse I
Bag End Total Est. Cost
Window/Doors - Total Replacement Photo
EFTA01124656
ℹ️ Document Details
SHA-256
980c3dec76c98024be2d99247cb04843f4579866ccdd4795dc7bb397b6f80e9a
Bates Number
EFTA01124648
Dataset
DataSet-9
Document Type
document
Pages
9
Comments 0