Movie Room:
New equipment install completed, One blown sub woofer, options to be forwarded
Gun Cabinet panels leather inserts completed
Chaises and Chairs ordered, estimated delivery last week of July
Pool/Gym sound system:
Completed
Surge Protection:
90% Complete
Main Distribution Pumps:
New Skid ordered, estimated delivery, week of the 8th June
Install will take 3 days
Present status, have one pump running, manual operation only,.
Outdoor Rugs:
Ordered, expect delivery, week of the 8th June
Bunkhouse Sofa:
Ordered, delivery estimated last week of July
Outside Furniture Lodge:
Purchasing wood 8th June, completion end of July
JJ's:
Bunkhouse windows delivered yesterday, work starts today
Lodge Deck Roof, completed
LV Tennis Court resurface, weather delayed, work started Tues this week
Painting:
Workshop and wash bay interior completed
Pole Barn and Eves of Workshops completed
Picket Fences RC and LV Fence completed
Bunk House exterior to begin once windows are installed
Chess fountain basin sealed, completed
RC Bumpers week of the 8 June
MH and Estancia doors waxing week of the 8 June
Masterbed room window sills week of the 8 June
Landscaping:
New Sod at Pool Area, complete
Hydroseeder, on sight, hydroseeding MH and LV next week
Planter beds MH, anticipate to start clearing 17th June
Log Cabin Grading, anticipate to start rock collecting etc 15th June
Working on new design to include terraces
New JD Ride on Mower RC, pickup 8th June
Cottonwood trees RC end of June
EFTA00642764
Auto:
5500 Mercedes, Transfer to NM registration today
Awaiting directing regarding Paint/Rust
Flat Bed Trailer, purchase today, pickup Monday 8th
Poolpak:
New compressor due today
Trane to install next week
HVAC controls
Investigating second bid that allows wifi thermostat control.
Water Development:
Abandoned Well plugged, plan has been filed with State
Application to move Dakota Water Right to Well B has been file, awaiting OSE approval
Casey Cook is recommending the construction of a irrigation pond.
The State need to advise if pond can has to be in the " Place of Use" or can be constructed outside this area.
We need OSE direction on pond location to confirm estimated cost of final 2 phases of this Project..
regards Brice
Brice Gordon
Stanley, NM
Ph:
EFTA00642765
ℹ️ Document Details
SHA-256
997ae41281702a7990bb397b02f3ad70e436158c031a5f8982282aabea910883
Bates Number
EFTA00642764
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0