12/23/10 Job Estimates vs. Actuals Detail for 1006 - Laundry
All Transactions
Est. Cost Act. Cost (8) Diff.
Service
Laundry
01 Direct Expenses
01.100 - Holiday Allocation 0.00 296.31 296.31
01.101 • Burden 0 00 176.93 176.93
01410 - Material Handling 2400.00 1287.12 -1,112.88
01421 Temporary Protection 1,500.00 80.00 •1.420.00
01-624 • Construction Cleaning 1.440.00 769.88 470.12
01-645 - Expendables 2.250.00 1.278.77 -971.23
01.646 - Small Tools 1,700.00 533.40 -1.166.60
01.665 • Equipment Rental 1.500.00 0.00 -1.500.00
01-900 • Misc. Expenses 500.00 184.00 -316.00
Total 01 Direct Expenses 11.290 00 4.606 41 -6.683.59
02 Site Work
02-000 - Inspection-Testing 3.500.00 3.60800 108.00
02-005 - Layout/Survey 1,500.00 1.104 00 -396.00
02-200 • Excavation•Backfill 10.000 00 10.437 86 437.86
02.281 - Pest Control 1,176 00 1.175.00 -1.00
02480 - Landscaping 3.000,00 0.00 -3.000.00
02-740 • Septic System 10.500.00 10.228.00 -272.00
Total 02 Site Work 29.676 00 26.552 86 -3.123.14
03 Concrete
03.111 - Footing 8.300.00 8.276.40 -23.60
03.130 • 4000* Concrete 9,405.00 8.746.92 -658.08
03-154 - Shoring 900.00 855.20 -44.80
03.171 - Stairs 2,225.00 2,201 44 -23.56
03-173 • Slab on Grade 1.350,00 1.332.80 -17.20
03-174 - Elevated Slab 8.280.00 8.279.04 -0.96
03-210 - Rebar 6.700.00 6.684.16 -15.84
03-362 • Pumping 1.525.00 2.885.00 1,360.00
03-600 - Grouting 270.00 1.360 19 1.090.19
Total 03 Concrete 38.955 00 40.621 15 1.666 15
04 Masonry
0±2 6 X00 7.042 80 162.80
q(P424 - Coral Stone Tile 19.550 270.32 -19.279.68
04.450 = Na m Stone Veneer 21.000'00 20.659 20 .340.80
Total 04 Masonry 47.430.00 27.972.32 -19,457.68
06 Carpentry
06-050 - Fasteners - Material 1.500.00 1.459.04 40.96
06.100 - Rough Carpentry - L 3.200,00 1,423.60 -1.776.40
06-101 - Rough Carpentry - M 3.000.00 0.00 -3.000.00
G3 50 FEET 06-200 - Finished Carpentry 10,000.00 7.250.00 -2.750.00
„Li r Total 06 Carpentry 17.700.00 10.132.64 -7.567.36
11.414*) 08 Doors and Windows
ist"- Arii-de 08-100 • Metal Doors & FramesM
08.101 - Metal Doors & FramesL
08.711 - Finish Hardware - L
3100.00
480.00
240.00
3.080.29
866.00
0,00
•19.71
386.00
-240.00
Total 08 Doors and Windows 3.820.00 3.946.29 126.29
09 Finishes
5.500.00 5.4 -69.13
(09-310 - Ceramic Tile Floor „? 8,500.00 -211.00
09:910 • Exterior Painting 500.00 -500.00
09.920 - Interior Painting 1,000.00 0.00 -1.000.00
Total 09 Finishes 15.500.00 13.719.87 -1.780.13
10 Specialities
10-520 - Fire Extinguishers 500.00 0.00 -500.00
10-670 - Storage Shelving 3.500.00 0.00 -3.500.00
Total 10 Specialities 4,000 00 0.00 4.000.00
Page 1
EFTA01110396
11 c8 AM LSJ. LLC
12 23 10 Job Estimates vs. Actuals Detail for 1006 - Laundry
All Transactions
Est Cost Act. Cost ($) Ddf.
11 Equipment
11-452 • Laundry Equipment 10.000.00 8.400.00 -1.600.00
Total 11 Equipment 10.000.00 8.400.00 •1.600.00
15 Mechanical
15-400 • Plumbing 20885.00 6.683.05
15-600 - AC System -14.201.95
6.000.00 5.080.00 -920.00
Total 15 Mechanical 26.885.00 11.763.05 -15.121.95
16 Electrical
16-000 • Electrical Complete 15,750.00 18.303A1 2.553.41
Total 16 Electrical 15.750.00 18.303.41 2.553.41
Total Laundry 221.006.00 166.018.00 -54.988.00
Total Service 221.006.00 166,018 00 -54,988.00
TOTAL 221,006.00 166,018.00 -54,988.00
Page 2
EFTA01110397
PhilipMark Sub-Contractor
LICENSED
OFNE BUlt.OER • CISTERN CLEANING • ROOFS
FILING • PAINTING • SWIMING 6•00..S FINISH WORK
WINTSERG
NO I -Ib 6
ST THOMAS US VI OCan.,
10741- 66 ler AA . 677.6r1
10
TX! f-441)5.6-180 .7;
,4#1---
EFTA01110398
LSJ C.ONSTRUC,TiON
Subcontractor Payout
Project: Laundry #1006
December 6, 2010
Trade: Tile Flooring
Requisition #01
Suocontractor Phillip Mark
Insurance ex iraticn
Invoice # Requisition r101 Partial Final
Phase # 09-310
X
Orlin& CanIfJC? Sum
$6.780.00
Change Orders Submitted & Approved
So 00
New Change Orders:
SO .00
Total Work Contracted to Date:
$6.780.00
Total Work Completed to Date
100% $6,780.00
Less Retainage
$0 00
Total Payments Made to Date.
SO 03 /
Total Current Payment Due
$6,780.00
Balance to Finish including Retainage.
$0.00
Saes Tax Liability:
a Subcontractor/Supplier is liable. exploit crily • tax
i - ,::Itif!!:!fl in contrart
b. Non-resident Subcontractor/Supplier Bond Applicable:
c Use Tax to be paid by our company
d Shipping
`.:
Total Outlays for this contract incl. Sales or Use Tax'
$6 780 00
JEE approval attached
Invoice Attached
YES NO YES NO
X
Submitted Bill
App'Gvea by Gary
Sygno,.:
pri7r .
Date •
ACIL,rOved Ili
EFTA01110399
ℹ️ Document Details
SHA-256
9cbe17eec8652ec2242569acd2197fea541c45d4914c9f77dfb03301641636b2
Bates Number
EFTA01110396
Dataset
DataSet-9
Document Type
document
Pages
4
Comments 0