From:
To: [email protected]
CC:
Subject: Gil update
Date: Fri, 18 Mar 2011 15:11:55 +0000
just
Gentlemen,
The right gear is completed and will be shipped today. We should receive this by Monday.
The left gear is in the machine shop, they have performed an NDT of the effected area and it appears there is enough
material to remove the corrosion and remain within limits. They will proceed this weekend with the machining and check the
remaining thickness again on Monday and get engineering involved for approval as well. There is still a good chance the
corrosion is beyond acceptable limits. I should have an answer no later that Tuesday on this gear leg.
Everything else is just about wrapped up.
If you have any further questions, please feel free to contact me.
Have a great weekend!
Best Regards
Jet Aviation St. Louis, Inc.
Joe Allen
Gulfstream Customer Support Manager
an update from Midcoast:
EFTA00655264
ℹ️ Document Details
SHA-256
9d69bdcfc51c56174c84c2d7d38d83f47d955c1fe65132f08d5a706c8c8c41e2
Bates Number
EFTA00655264
Dataset
DataSet-9
Type
document
Pages
1
💬 Comments 0