From: jeffrey E. <[email protected]>
Sent: Thursday, April 12, 2018 7:59 PM
To: Amy Dempsey
Subject: Re: ACE - Cables and Non-compliance
we pulled out the barge ramp across month ago. =we can pull out xmas cove , i would like to do so if that is t=e hold
up. i thought we would asking for the deliniation weeks=ago
On =hu, Apr 12, 2018 at 3:55 PM, Amy Dempsey wrote:
Army Corp= called late this morning and said that enforcement has decided to hold up=the VIWAPA cable
project because of the LSJ non-compliance issues. A=my Corps suggested that we removed the LSJ-GSJ cable so the
ca=le system can move ahead.
I ended up talking with Jonathon Pempek as well as Sindulfo Cast=llo and they said although it is unusual to hold
up a project that the app=icant was not the violator on they felt this was good leverage.
So Jonathon said get the barge ramp= out and pull the fill material back out around the wetland near the
point=closest to LSJ. I am waiting on old wetland delineation from Ryan Wi=ehart so I can mark it and we can get the
material moved back a couple of =eet and plant a few mangroves.
Jonathon suggest that if you really want one of the barge ram=s we could pull it out and then ask for a permit
for it.
He stressed that he wants you to get all=the things you want but we have to go through the permit process.
conversation-id 9696 date-last-viewed 0 date-received 1523563129 flags 8590195713 gmail-label-ids 7 6
remote-id 812065
1
EFTA_R1_01587964
EFTA02475030
ℹ️ Document Details
SHA-256
a147b66be3a3ed4d1922c915c43755a69e384bc133954edfbb324f402073043b
Bates Number
EFTA02475030
Dataset
DataSet-11
Document Type
document
Pages
1
Comments 0