📄 Extracted Text (1,449 words)
-mow
TSG
MAKING EVERY DROP COUNT US. Virgin Islands Operations
www.tsgwater.com 6501 Red Hook Plaza, Suite 201
St. Thomas, Virgin Islands 00802-1306
Little St. James Service Report:
Feb. 24th. 2014
February 18'h, 2014 we started the contracted work at Little St. James Island (LSJ) of replacing
the entire contents of the SWRO high voltage control panel that had received severe damage
following an incident that sprayed high pressure seawater throughout the panel.
Upon entering the SWRO plant Tuesday 2/18/2014 there had been another pipe burst
incident and seawater was all over the floor and on the skid of new replacement parts had been
sprayed with seawater too. There were several burst tubing connections due to the SWRO plant
being operated manually and allowed to run at 980psi. We checked the contents of the new
parts and it was determined that the parts inside the wet cartons were not damaged by this
latest incident, so we moved forward with replacing the components of the damaged control
panel. Below are photos of the parts removed from the damaged control panel. NOTE: ALL
components inside the panel were replaced.
Georgia • Florida • US Virgin Islands • British Virgin Islands • Anguilla • Turks and Caicos • Bahamas
EFTA01109916
There was a lot of salt and rust on the components inside the panel as noted above. Great care
was taken to clean the panel completely before installing any new components. The finished
product was a completely new high voltage control panel as is pictured below.
During our Service on 2/18/14, I instructed the LSJ operating crew to remove the end caps from
the membrane vessels to look for foreign objects that could be causing the high membrane
feed pressure that initially caused this incident. Below is what was found with the lead
membranes in all four vessels severely fouled from FOD (Foreign Objects & Debris) Membrane
pictures are below:
Georgia • Florida • US Virgin Islands • British Virgin Islands • Anguilla • Turks and Caicos • Bahamas
EFTA01109917
These two membranes show rocks, gravel, dirt, and debris that has passed through the
cartridge filters and entered the membrane vessels.
The membranes pictured below show severe fouling due to dirt and rust. The picture left shows
mechanical damage noted by gaps in the membrane material
It was determined that the best approach for getting the system back to acceptable operational
membrane feed pressures was to replace the two lead membrane elements in all four tubes as
they were the most severely fouled. Eight membranes were all that TSG had available, and it is
suggested that the other 16 of the 24 total membranes be replaced in the LSJ SWRO plant as
soon as is possible to bring the system back to its original design pressure parameters of 780-
850 psi membrane feed pressure.
Georgia • Florida • US Virgin Islands • British Virgin Islands • Anguilla • Turks and Caicos • Bahamas
EFTA01109918
2/19/2014: We arrived on the morning Barge and set out to complete the electrical installation
as we waited for approval from LSJ to replace 8 of the 24 membranes in the SWRO. After
completing the electrical panel, we had issues connecting the SWRO systems virtual machine
computer due to corrosion on the Ethernet port. LSJ's IT person was called in to repair it.
Nothing could be checked without the plant running, so we decided to further our investigation
into the root cause for the severe membrane fouling and high membrane feed pressure. We
found operational issues that were documented by photos below.
The picture below shows debris left in the Media filters after backwash. Filters backwashed
using flow rates too high cause media to be backwashed out of the filter, into the piping and
transferred to the Cartridge filters. I explained to Smiley how to watch and balance MMF
Backwashing.
We then focused our attention on the Cartridge Filter Housing. Filters were removed, the spool
piece connection was removed and the housing was thoroughly cleaned out. Dirt, sand and
rocks were removed from the housing. Pictures are below.
ip
The remainder of the day was spent changing out the membranes and locking down the end
caps.
Georgia • Florida • US Virgin Islands • British Virgin Islands • Anguilla • Turks and Caicos • Bahamas
EFTA01109919
2/20/2014. We arrived with TSG's Virtual Machine Computer. Power was restored to the SWRO
plant, electrical connections were checked, and the PLC program was gone through, checked,
and tested by our controls engineer in Gainesville, Fl. By mid-morning, we were ready to start
the plant only to have issues with low feed water pressure and several more leaks. We had to
backwash the MMF's, change out all of the high pressure tubing on the systems
instrumentation connections, Repair the HP Pump oil pressure gauge, and replace the high
pressure flange gasket on the high pressure pump.
NOTE: There were NO gaskets or fittings onsite, and we had to get a LSJ boat to take one TSG
engineer from LSJ Island to Red Hook to pick up parts brought to us by another TSG employee.
See pictures below:
Afterwards, we started the SWRO plant only to have issues with the SW intake pumps
continually loosing prime. The LSJ crew tried for two-three hours to get the pumps primed
without success. At 3:30pm, Danny had found a cracked basket strainer lid on the intake pump
system that was causing the intake pumps to loose prime.
Georgia • Florida • US Virgin Islands • British Virgin Islands • Anguilla • Turks and Caicos • Bahamas
EFTA01109920
2/21/2014. We arrived at LSJ after being assured by Danny that the intake pumps were
operational. We started the SWRO Plant. The plant started automatically without issue and ran
without problems. Several of the SWRO plant's safety alarm features were tried including;
1. Low pressure alarm shut-down (25psi)
2. High pressure alarm shut down (950psi)
3. E-stop
4. High Conductivity (1,000 uS/cm)
5. Low permeate flow (45gpm)
6. High permeate pressure (60psi)
7. Low Boost pump flow alarm shut down (60gpm)
All of the above alarms were simulated during the initial run and found to be operating
correctly.
It was noticed during the initial service run that the Membrane Feed Pressure was still higher
than normal and shows that there has been irreversible damage done to more of the
membranes than was initially replaced. We were able to get the pressures down to just above
900 PSI after increasing the SWRO plants brine discharge and Boost Pump flow. The screen shot
below shows run parameters.
C t •1 TSG
a a
U- poi to DATA
SIDRA
WARM IMAI MASI LOG)
MUG
Georgia • Florida • US Virgin Islands • British Virgin Islands • Anguilla • Turks and Caicos • Bahamas
EFTA01109921
We then set about the task of calibrating instrumentation, batching pre-treatment chemicals,
replacing the tubing on the Sulfuric Acid Chemical feed pump, priming and adjusting all
chemical feed pumps using the chemical calibration columns that were provided to L.S1 during
the initial installation and commissioning of the SWRO Plant. Pictures are below.
We completed the service at 3:00 pm, and left the plant running in auto. I called Monday
morning @ 8:30, talked to Danny who attested that the plant ran all weekend without issue
and shut down automatically after filling the main cistern completely.
Georgia • Florida • US Virgin Islands • British Virgin Islands • Anguilla • Turks and Caicos • Bahamas
EFTA01109922
In closing, TSG suggests that we be contracted by you for a complete evaluation of the LSJ
SWRO plant and report our findings to insure that LSJ has all necessary information so that the
SWRO plant can be brought back to its original operational condition. This evaluation would
include; Critical spares list needed to be purchased and stored onsite for future issues that may
occur with the SWRO plant. The condition of the SW intake pumps, priming system, and SW
intake pipe. The High Pressure pump running condition including both power and fluid sides of
the HP pump. Booster Pump liquid end, PX pressure exchangers, and assessment of the post
treated water quality.
It would also be beneficial to LSJ that the SWRO plant operator be given some professional
training allowing him to receive sufficient experience to be more proactive when maintaining
the LSJ SWRO Plant.
Respectfully Submitted,
Patitid idiam4
Patrick Adams
TSG - USVI Ouerations Manager
Cc; Bob Petersen — TSG
John Leet-TSG
Georgia • Florida • US Virgin Islands • British Virgin Islands • Anguilla • Turks and Caicos • Bahamas
EFTA01109923
Georgia • Florida • US Virgin Islands • British Virgin Islands • Anguilla • Turks and Caicos • Bahamas
EFTA01109924
ℹ️ Document Details
SHA-256
a5ca577f08eae3bd5e632c236955a89d500a70c35b832deaf39ef5cbd489bd18
Bates Number
EFTA01109916
Dataset
DataSet-9
Document Type
document
Pages
9
Comments 0