Scope of Work GSJ
Infrastructure
• Main link
o The same type of WAPA power cable used for LSJ
(Power copper for the outer rings and single mode
fiber in the middle.
o The GSJ Fiber run
■ Starts from LSJ Data Center (the location of the
Power Transformer to should be close to LSJ
Data Center)
■ Upgrade Main Switch /add second switch - to
provide for more fiber ports
o Phones
■ Option 1
• Upgrade existing switch for more
extensions
• Add more service lines / split existing
service line between LSJ and GSJ
■ Option 2
• New phone switch
• GSJ has its own Phone Numbers
o Internet
■ LSJ shares bandwidth with GSJ
• GSJ Data Center
o Location to be determined by JE
o Equipment needed
■ Rack
■ Switches
■ Battery Backup {Danny / JE to verify if GSJ will
have its own generators or will LSJ be able to
Share power}
EFTA01120411
• Pull Through
o Verify with Danny on the strategic areas for (2) Main
pull vaults and manhole
■ JE to approve GSJ tour with Danny
• Possible Fiber crew if JE approves
■ Document and Map vault and manholes as we
progress
Buildings
• JE to approve types of building and what services to be
installed in each such as the following:
1. ( Theater - Phones, Audio /Video, wireless network,
and Computer)
a. Blackboxes in each area with a switch, battery
backup, and patch panel
b. Access Points in all Buildings
Questions:
Is Solar an option?
Should cameras be installed?
EFTA01120412
ℹ️ Document Details
SHA-256
ae800bcf50476bd6d034e4db616cc43838e621f658a55e05f80d164bab745a09
Bates Number
EFTA01120411
Dataset
DataSet-9
Document Type
document
Pages
2
Comments 0