12:43 PM LSJ, LLC
12/19107 Job Estimates vs. Actuals Detail for 1 - Office Pavilion
All Transactions
Est. Cost Act. Cost (5) DIM.
Service
Office Pavilion
Concrete
03.120 - Complete Sub 379,500.00 23,841.50 -355,658.50
03.130 -4000# Concrete 120,000.00 10,633.16 -109,366.84
03-362 - Pumping 25,000.00 0.00 -25,000.00
Total Concrete 524.500.00 3.4,474.66 -490,025.34
Doors and Windows
08.210 - Doors 8 Frames Labor 1.800.00 0.00 -1,800.00
08.210 - Exterior Door 8 Frame 28.10000 0.00 -28,100.00
08.211 - Interior Door 8 Frame 5.25000 0.00 -5,250.00
08.212 - UKility Door&Frame M 2.840.00 0.00 -2,840.00
08.610 - Wood Windows L 1.680.00 0.00 -1,680.00
08.610 - Wood Windows M 29.96300 0.00 -29,963.00
08.710 - Door Hardware 12.000.00 0.00 -12,000.00
08.810 - Mirror Glass L 8 M 675.00 0.00 -675.00
Total Doors and Windows 82.308.00 0.00 42,308.00
Electrical
16-000 - Electrical Complete 40,000.00 0.00 -40,000.00
16-510 -Additional Fixture 25,000.00 0.00 -25,000.00
16-700 - Communications Wiring 15,000.00 0.00 -15,000.00
Total Electrical 80,000.00 0.00 -80,000.00
Equipment
11.451 - Kitchen Equipment 2.504.40 0.00 -2,504.40
Total Equipment 2.504.40 0.00 -2,504.40
Finishes
09.120 - Ceiling Support Coff. 36.750.00 0.00 46,750.00
09.120 - Ceiling Support Flat 14.640.00 0.00 -14,640.00
09.200 - Plaster 8 Lath 34.300.00 0.00 -34,300.00
09.220 - Cementitious Coatings 7.040.00 0.00 -7,040.00
09.230 - Aggregate Coatings 25.00000 0.00 -25,000.00
09-350 - Portugese Tile L 4.500.00 0.00 -4,500.00
09.600 - Stone Flooring L 20.79000 0.00 -20,790.00
09.920 - Interior Painting 43,20000 0.00 -43200.00
Total Finishes 186.220.00 0.00 -186,220.00
Furnishings
12-310 - Granite Countertop 5,250.00 0.00 -5,250.00
Total Furnishings 5,250.00 0.00 -5.250.00
General Requirements
01.514 - Temp Phones 4,200.00 0.00 -4200.00
01.516 - Temporary Toilet 1,500.00 0.00 -1,500.00
01.517 - First Aid Supplies 900.00 0.00 -900.00
Page 1
EFTA00603101
12:43 PM LSJ, LLC
12/19/07 Job Estimates vs. Actuals Detail for 1 - Office Pavilion
All Transactions
Est. Cost Act. Cost (5) DIN.
01.518 -Temporary Fire Protect 600.00 0.00 -800.00
01.522 -Temporary Enclosures 3.000.00 0.00 -3,000.00
01.562 - Dust Control L 10.400.00 0.00 -10,400.00
01.562 - Dust Control M 9,372.00 0.00 -9,372.00
01.590 - Field Office Supplies 1.200.00 0.00 -1.200.00
01.610 - Material Handling 24.960.00 0.00 -24.960.00
01.621 - Temporary Protect 6,000.00 0.00 -6.000.00
01.624 - Construction Cleaning 10.400.00 0.00 -10.400.00
01.625 - Final Cleaning 1,850.00 0.00 -1.850.00
01.628 - Safety 9,000.00 0.00 -9.000.00
01.640 - Personnel Transport 114,206.04 0.00 -114.206.04
01.645 - Expendables 18.000.00 0.00 -18.000.00
01.665 - Equipment Operation 36.000.00 0.00 -36.000.00
01.712 - Super. Transport 5,400.00 0.00 -5.400.00
01.712 - Superintendent 83.980.00 0.00 -83.980.00
01-714 - Clerk 46.113.60 0.00 -46,113.60
01.715 - Time Keeper 46.113.60 0.00 -46,113.60
01.803 - Photographs 900.00 0.00 -900.00
01.850 - Plans Reproduction 9,000.00 0.00 -9,000.00
01.900 - General Office Require 131,700.00 0.00 -131,700.00
Total General Requirements 574,79524 0.00 -574,795.24
Masonry
04425 - Limestone Veneer 300,000.00 0.00 -300,000.00
04450 - Native Stone Veneer 120,000.00 0.00 -120,000.00
Total Masonry 420,000.00 0.00 -420,000.00
Mechanical
15-400 - Plumbing 66,550.00 0.00 -66,550.00
15400 - HVAC 166,980.00 0.00 -166,980.00
Total Mechanical 233,530.00 0.00 -233,530.00
Metals
05-120 - Structural Steel 323,553.00 34,613.25 -288,939.75
05-380 - Steel Erection 84,617.00 0.00 -84,617.00
Total Metals 408,170.00 34.613.25 373,556.75
Moisture/Thermal
07.110 - Membrane Water Proof 1.440.00 0.00 -1,440.00
07.160 - Bituminous Damp Proof. 4.000.00 0.00 -4,000.00
07.170 - Protection Board 1.395.00 0.00 -1,395.00
07.212 - Rigid Insulation L 3.200.00 0.00 -3,200.00
07.212 - Rigid Insulation M 11.520O0 0.00 -11,520.00
07-325 - Concrete Roof Tiles L 10.000.00 0.00 -10,000.00
07-325 - Concrete Roof Tiles M 16.700O0 0.00 -16,700.00
07.623 - Wood Windows L 4.600O0 0.00 4,800.00
07.623 - Wood Windows M 32.000O0 0.00 -32,000.00
07.632 - Door Hardware 6.000O0 0.00 -6,000.00
Page 2
EFTA00603102
12:43 PM LSJ, LLC
12/19/07 Job Estimates vs. Actuals Detail for 1 - Office Pavilion
All Transactions
Est. Cost Act. Cost ($)
07.900 - Mirror Glass L 8 M 3,000.00 0.00 -3,030.00
Total Moisture/Thermal 94.055.00 0.00 -94,055.00
Sitework
02-005 - Survey 20.000.00 1.125.92 -18,874.08
02.120 - Erosion Control L 3.200.00 0.00 -3,200.00
02.120 - Erosion Control M 5.100.00 759.44 -4,340.56
02.160 - Rock Anchors 39.811.00 11.114.00 -28,697.00
02.200 - Earthwork 131.376.00 0.00 -131,376.00
02.211 - Rock Removal 294.720.00 0.00 -294,720.00
02.281 - Pest Control 1.750.00 0.00 -1,750.00
02.713 - Pot. Water UG Piping 5.000.00 0.00 -5.000.00
02.740 - Waste Disposal Systems 36.520.00 0.00 -36.520.00
Total Sitework 537.477.00 12,999.36 -524,477.64
Specialities
10400 - Toilet Accessories 120.00 0.00 -120.00
Total Specialities 120.00 0.00 -120.00
Wood
06-050 - Fasteners Material 4,500.00 0.00 -4,500.00
06-100 - Rough Carpentry L 26,400.00 0.00 -26,400.00
06-100 - Rough Carpentry M 24,429.00 0.00 -24,429.00
Total Wood 55,329.00 0.00 -55,329.03
Total Office Pavilion 3,204,258.64 82,087.27 -3,122,171.37
Total Service 3,204,258.64 82,087.27 4,122,171.37
TOTAL 3,204,258.84 82,087.27 4,122,171.37
Page 3
EFTA00603103
ℹ️ Document Details
SHA-256
af2997c8c9df8cb51af2fe22347767db83c78aad6df4d7022ab2e2e4c7d7c1b6
Bates Number
EFTA00603101
Dataset
DataSet-9
Document Type
document
Pages
3
Comments 0