EFTA02412285.pdf
👁 1
💬 0
📄 Extracted Text (421 words)
To: Jeffrey Epsteingeevacation mail.com]
Cc: ; Gary Kemey , Doug
Schoettle
From:
Sent: Sun 6/13/2010 11:37:53 PM
Subject: Island - June
Hi all,
Gary did a great job of putting this together. I've added some comments below and the specific
things I'm taking care of in a separate email.
Thank you,
PLANS
Pick up latest marked drawings from Robert's otlice on Tuesday 15th, will make copy and send to Doug this week.
DOCK
See attached image.
LIBRARY
Status interior
1.interiors complete by construction
Outstanding issues
1meiling treatment Ion to visit week after next to start painting - work duration 2- 3 weeks - estimated
completion date July 8th
2.cabinet finishes awaiting panel from Paris. delay now due in this week by the 19th
3.floor finishes Je to decide on next visit to Island. decision made by July 1st.
Status exterior
1.courtyard paving underway complete by the July 31
2.irragation main ine underway complete by July 15
3. wall sconces to replace existing, will get info on them from Robert's office
Outstanding issues
1.landscape plans
a.plants 'gala to fill in area behind tiki hut with plants we chose awaiting new images from him
b.irragatiion plans
c.fighting will send sample lighting options via email this week
EFTA_R1_01473856
EFTA02412285
2.Igala has trees tagged ready for delivery as soon as barge is ready
MASTER SUITE
Status interior
1.const under way ,subject to decisions being made should finish by Oct 31
Outstanding issues
1.steam bench
2.out side shower
3.lites over bed
4.lighting in bedroom
5.electrical in bath area
6.tub deck and surround
7.selection of wood floor
8.sourcing thassos slabs
9.powderroom vanity plan
10.shop drawings for stone
rug for bathroom
I
I
.order
Status exterior
1.wall under way, complete by Aug 31
Outstanding issues
1.landscape plans..liting irr.
KITCHEN
Status
1.assume we get permit by July 1 should be complete by Nov.31
Outstanding issues
1.kitchen design
2.stair and wall design to master
LAUNDRY
1.assume we get permit July 1 should complete by Oct 31
COTTAGES
1.const underway should complete by Sept 30
Outstanding issues
1.shower design
Other guest cottage to be built in same complex: revisit idea on next visit
EFTA_R1_01473857
EFTA02412286
MAIN HOUSE REMODEL
Status no estimate to compleation tit program complete
1.courtyard side plan final,proceeding
2.roofing proceeding
Outstanding issues
1.north side program
MECHINICAL ELECTRICAL Status under way should complete by Sept 30
MECHANICAL DESAL Status under way should complete by Nov 30
POOUTHEATER
1.Gensler allow three months for plans
2.two months for permits Nov 30
3.pool by Mar 31
4. theater by Jun 30
EFTA_R1_01473858
EFTA02412287
ℹ️ Document Details
SHA-256
bc5a77bf073df2b5b231ac891d9d4633ad83ad4d978d1fc7b50be459e76f291e
Bates Number
EFTA02412285
Dataset
DataSet-11
Type
document
Pages
3
💬 Comments 0